Dak Lak - Businesses in the area cannot receive management and operation of irrigation projects that have broken water pipes many times from local authorities.

On March 10, a source from Lao Dong Newspaper said that local authorities had just held a meeting to discuss the handover of irrigation infrastructure assets under the Sub-project of irrigation water supply for coffee trees in Tien Cuong village (Quang Phu commune) to Dak Lak Irrigation Works Management Co., Ltd. for management.

At the meeting, representatives of Dak Lak Irrigation Works Management Co., Ltd. mentioned many reasons, both subjective and objective, causing the unit not to be able to receive management and operation of the project.

According to the company representative, the enterprise is only the unit assigned to manage, so there is no opinion on whether to accept or not accept. In case the Provincial People's Committee assigns it, the unit will receive it, but the handover must ensure full conditions according to regulations.

Doanh nghiệp trên địa bàn chưa vội tiếp nhận bàn giao, quản lý, vận hành dự án từ chính quyền địa phương. Ảnh: Bảo Trung
Businesses in the area cannot receive the handover, management, and operation of projects from local authorities. Photo: Bao Trung

Meanwhile, this project has had many pipeline burst incidents and has not been completely repaired to this day. The enterprise also does not know clearly whether in the incidents, the investor has prepared a complete quality management dossier, adjusted and re-approved the project or not.

If so, the company requests to be handed over full repair records that have been approved by competent authorities for monitoring and management.

In addition, the project's canal route mostly passes through people's fields, many locations have been re-encroached upon, and the scope of site clearance is narrow. When an incident occurs, bringing machinery and vehicles for repair will be difficult.

Currently, some households have fenced off land or planted trees with high economic value, which may affect the overcoming of incidents, especially when people need irrigation water.

Chi tiết thiết kế, công suất, mục đích triển khai của dự án. Ảnh: Bảo Trung
Detailed design, capacity, and project implementation purpose. Photo: Bao Trung

The company representative also raised the issue that if management and operation are undertaken but incidents occur leading to slow water supply, violations of water supply contracts for people, it is necessary to clarify the responsibilities of the related parties.

According to actual records, the project is still not operating at full capacity, and many farming households in the cultivated area have not benefited as initially expected.

Previously, at the end of January 2026, the Department of Agriculture and Environment of Dak Lak province had a report sent to the Provincial People's Committee on the allocation of irrigation infrastructure assets of this sub-project.

By the end of February 2026, the Office of the Provincial People's Committee will continue to have a document requesting the Department of Agriculture and Environment to receive and explain the comments on the draft decision. However, the leaders of the Provincial People's Committee have not yet agreed with the draft on the allocation of irrigation infrastructure assets of the above-mentioned sub-project.

As Lao Dong Newspaper has reported, the sub-project to supply water to coffee trees in Tien Cuong village (Quang Phu commune) is invested by the Department of Agriculture and Environment of Dak Lak province, with a total initial investment of more than 65 billion VND.

After that, the project adjusted to increase the capital to about 72 billion VND (due to increased irrigation area). From 2023 to now, the project has continuously cracked and broken dozens of times, and the main pipeline has also broken many times.

In mid-2025, Dak Lak Provincial Police intervened to verify and investigate the incident at the above construction site.

BẢO TRUNG
RELATED NEWS

Thanh Hoa's largest waste treatment plant cannot receive more waste because nearly 3,000 tons are still in stock

|

Thanh Hoa - Due to the amount of accumulated waste reaching thousands of tons, the largest waste treatment plant in Thanh Hoa still cannot receive more daily domestic waste.

Resolving the water pipe break that has plagued thousands of households

|

Nghe An - On April 18, Mr. Nguyen Quang Loc - Chairman of the People's Committee of Kim Lien Commune, Nam Dan District - said that the water pipe failure had been fixed.

Construction broke water pipes, thousands of households lacking water

|

Nghe An - The process of expanding construction of National Highway 46, underground water pipeline broke, causing thousands of households in Kim Lien commune to fall into the situation of losing their daily life for many days.

Ukraine launches cheap weapons to counter Iran's drone fleet

|

Ukraine confirms deployment of specialized interceptor weapons and experts to protect strategic infrastructure in the Middle East from attacks from Iran.

Three teenagers who rode motorbikes 250km and ran away from home were supported by the police to return

|

Dak Lak - Functional agencies have just discovered three teenagers riding motorbikes for about 250km after leaving home.

Salary debt, May Fivestar Ha Tinh Joint Stock Company continues to break promises on payment dates

|

Ha Tinh - By March 10, May Fivestar Ha Tinh Joint Stock Company continued to fail to promise the date of payment of salary arrears to more than 300 workers.

Khanh Hoa corrects the stamp "Secret" for the document responding to petitions about the Lo River project

|

Khanh Hoa - The locality has just issued a document correcting the stamp "Secret" in the citizen response document related to the Lo River project.

Sand pirates on the Gianh River disappear after functional agencies intervene

|

Quang Tri - Sand pirates on the Gianh River are absent after Lao Dong Newspaper and functional agencies intervened.

Thanh Hoa's largest waste treatment plant cannot receive more waste because nearly 3,000 tons are still in stock

QUÁCH DU |

Thanh Hoa - Due to the amount of accumulated waste reaching thousands of tons, the largest waste treatment plant in Thanh Hoa still cannot receive more daily domestic waste.

Resolving the water pipe break that has plagued thousands of households

QUANG ĐẠI |

Nghe An - On April 18, Mr. Nguyen Quang Loc - Chairman of the People's Committee of Kim Lien Commune, Nam Dan District - said that the water pipe failure had been fixed.

Construction broke water pipes, thousands of households lacking water

QUANG ĐẠI |

Nghe An - The process of expanding construction of National Highway 46, underground water pipeline broke, causing thousands of households in Kim Lien commune to fall into the situation of losing their daily life for many days.

Vỡ ống nước ra đảo Nha Trang, dân đảo phải xếp hàng nhận nước miễn phí

Hữu Long |

Khánh Hòa - Đường ống nước sạch vượt biển sang đảo Trí Nguyên ở Nha Trang bị vỡ khiến cuộc sống của người dân bị đảo lộn. Trong lúc chờ khắc phục sự cố đơn vị đang phối hợp lực lượng biên phòng sử dụng tàu thuyền chở nước sạch từ đất liền ra đảo cung cấp miễn phí cho người dân.