Basically completed the main route of Van Ninh - Cam Lo Expressway

CÔNG SÁNG |

Quang Binh - The Van Ninh - Cam Lo expressway project has basically completed the main route, reached the progress of site handover and construction, ready for the next phase.

On June 30, speaking with a reporter from Lao Dong Newspaper, a representative of the Ho Chi Minh Road Project Management Board said that the Van Ninh - Cam Lo expressway project has basically completed the main route.

Site clearance is facing difficulties

According to the representative of the Ho Chi Minh Road Project Management Board, the site clearance (GPMB) for this project has now been 100% completed for the main route.

Quang Binh province (old) has handed over the entire area of 33.017km, equivalent to 100% of the required area, while Quang Tri (old) has also completed the handover with 32.534km. However, at some locations such as the service road, site clearance is still a problem.

In Quang Binh (old), the remaining site has not been handed over at 8.5km of service road because the locality has not yet approved the compensation and support plan. In addition, some intersections on the route such as National Highway 9C still have problems with traffic turning points and toll stations.

In Quang Tri (old), although the site clearance work has reached 100% for the main route, there is still 1.48km of service road that has not been handed over due to the compensation and support plan not being approved. Some traffic turning points and toll stations at the intersections of National Highway 9D, DT75 and National Highway 9A also encountered similar problems.

The North-South Expressway Project has been divided into 2 main construction packages, including XL1 and XL2 packages. Both packages are currently under construction on schedule.

Cac cong nhan thuc hien cac khau cuoi cung tren cao toc. Anh: Van Tuan
Workers carry out the final stages on the expressway. Photo: Van Tuan

The XL1 package, constructed from Km675+400 to Km708+350, has completed a number of important items such as bridges, culverts, underpasses, earth filling, and road surface construction. Similarly, package XL2 is also under construction from Km708+350 to Km740+884 with bridge, culvert, underpass and weak soil treatment items.

"Regarding construction progress, the project is speeding up construction progress to complete the BTN (hot asphalt concrete) and traffic safety (traffic safety) pavement for the main route today (June 30)," said a representative of the Ho Chi Minh Road Project Management Board.

Overpass projects are still facing difficulties due to the failure to hand over the site to the locality on schedule. It is expected that the overpasses will be completed around mid-July 2025.

Difficulties in site clearance for service roads

Regarding problems in site clearance, a representative of the Ho Chi Minh Road Project Management Board said that localities need to urgently resolve the problems to ensure the progress of the project.

In particular, Quang Tri (old) needs to urgently approve the compensation and support plan for the remaining 1.48km of service road, as well as solve problems with the location of vehicle turning and toll stations, rest stops.

Quang Binh (old) also needs to speed up the approval of compensation and support plans for 8.5km of service roads that have not been handed over, and at the same time, localities need to complete the handover of land at intersection locations.

"We recommend that the Provincial People's Committee soon direct localities to deploy methods to resolve problems related to site clearance to ensure uninterrupted project progress," said the Ho Chi Minh Road Project Management Board.

Cao toc Van Ninh - Cam Lo nhin tu tren cao. Anh: Van Tuan
Van Ninh - Cam Lo Expressway seen from above. Photo: Van Tuan

In particular, the locality needs to promptly carry out compensation and support for affected households, in order to facilitate further construction.

Although the overall progress of the project is being implemented quite well, if the problems with site clearance are not resolved in time, it can affect the construction progress of the entire project.

The North-South Expressway Project is not only an important traffic project but also a symbol of the development of the North-South region, contributing to promoting the economy, society and improving the quality of life of people in the area.

CÔNG SÁNG
TIN LIÊN QUAN

Starting construction of Bao Loc - Lien Khuong expressway worth nearly 18,000 billion VND

|

Lam Dong - Bao Loc - Lien Khuong Expressway has a total investment of nearly VND18,000 billion, will shorten travel time between Ho Chi Minh City - Da Lat from 6 hours to 3 hours.

Binh Phuoc signs BOT contract with Vingroup - Techtra Joint Venture to build 124 km of expressway

|

Binh Phuoc - The Provincial People's Committee signed an investment contract to build the North-South expressway in the West, Gia Nghia (Dak Nong) - Chon Thanh (Binh Phuoc) section.

Expanding the Ho Chi Minh City - Long Thanh Expressway with VND16,386 billion must select a capable contractor

|

Dong Nai - The project to expand the Ho Chi Minh City - Long Thanh expressway section, nearly 22km long, connects Ho Chi Minh City with Bien Hoa - Vung Tau expressway and Long Thanh airport.

An Giang Provincial Party Secretary holds the position of Deputy Head of the Central Internal Affairs Commission

|

The Politburo transferred, assigned and appointed Mr. Le Hong Quang to hold the position of Deputy Head of the Central Internal Affairs Commission.

Heavy rain causes local congestion on many streets in Hanoi

|

Hanoi - Due to heavy rain on the evening of June 30, some streets in Hanoi experienced local congestion.

Mr. Tran Thanh Lam holds the position of Deputy Head of the Central Propaganda and Mass Mobilization Department

|

The Secretariat decided to transfer and appoint Mr. Tran Thanh Lam to the position of Deputy Head of the Central Propaganda and Mass Mobilization Department.

20h News: Ministry of Education and Training talks about marking high school graduation exams when merging provinces and cities

|

20h News on September 30: The marking of high school graduation exams is not affected by the merger of provinces and cities; Forecast of very heavy rain in the next 3 days...

Vietnam General Confederation of Labor offers incense to commemorate the late General Secretary Nguyen Van Linh

|

Hung Yen - On the afternoon of June 30, a working delegation of the Vietnam General Confederation of Labor led by Comrade Nguyen Dinh Khang - Member of the Party Central Committee, President of the Vietnam General Confederation of Labor offered incense to commemorate the late General Secretary Nguyen Van Linh at the memorial house in Nguyen Van Linh commune, Yen My district (Hung Yen).

Starting construction of Bao Loc - Lien Khuong expressway worth nearly 18,000 billion VND

Lam Hồng |

Lam Dong - Bao Loc - Lien Khuong Expressway has a total investment of nearly VND18,000 billion, will shorten travel time between Ho Chi Minh City - Da Lat from 6 hours to 3 hours.

Binh Phuoc signs BOT contract with Vingroup - Techtra Joint Venture to build 124 km of expressway

ĐÌNH TRỌNG |

Binh Phuoc - The Provincial People's Committee signed an investment contract to build the North-South expressway in the West, Gia Nghia (Dak Nong) - Chon Thanh (Binh Phuoc) section.

Expanding the Ho Chi Minh City - Long Thanh Expressway with VND16,386 billion must select a capable contractor

HÀ ANH CHIẾN |

Dong Nai - The project to expand the Ho Chi Minh City - Long Thanh expressway section, nearly 22km long, connects Ho Chi Minh City with Bien Hoa - Vung Tau expressway and Long Thanh airport.