Special mechanism will remove obstacles to the Duong Bridge project site

Minh Hạnh |

Hanoi - The Duong Bridge construction project, a key traffic project of the capital, is behind schedule due to problems with site clearance (GPMB).

According to people's reflection, the Duong bridgehead area is currently often congested because the existing bridge is too narrow, not meeting the increasing traffic volume. Meanwhile, the new bridge has completed two main pillars, the railway bridge part is also basically finished but still has to wait for connection because the site has not been cleared.

According to Mr. Nguyen Manh Tuan (residing in Group 10, Viet Hung Ward), his family is subject to land acquisition and enjoys a special mechanism of resettlement by land, his house is over 90m2, exchanged to a 78m2 plot of land, and there is even a surplus compensation. Most households agreed, just hoping that the city would soon hand over the land and pay compensation so that we could stabilize our lives.

The Duong River waterway upgrade project has a total investment of VND 1,848 billion, of which the cost of site clearance in phase 1 is VND 650.8 billion from the State budget. The Railway Project Management Board (Ministry of Construction) is the investor.

The road bridge is 382m long, with a cable-stayed structure, 18.5m wide; starting point at the old Duong bridge intersection on Ngo Gia Tu street (Viet Hung ward), ending point at the Ha Huy Tap - Phan Dang Luu intersection (Phu Dong commune), about 100m downstream from the old bridge. The railway bridge is 1km long, with 6 steel spans, designed for 1,000mm and 1,435mm cages, at a speed of 80km/h.

According to the representative of the Viet Hung Ward Infrastructure Investment Project Management Board, the difficulty at the end of the bridge on the Long Bien side is that a unit requested an inventory of the underground low-voltage underground power system but there were no records, leading to prolonged controversy. By October 16, after the parties reviewed and agreed, this problem had been resolved.

At the head of the Gia Lam bridge, the project still has 89 households. Although the mobilization work has lasted for many years, no household has yet handed over the site. Hanoi has issued a specific compensation policy, allowing resettlement by land, and at the same time supporting the difference if the actual area is less than 80m2, which is the standard area for the resettlement area.

In particular, in October 2025, Hanoi continued to approve a new special mechanism, allowing compensation for the entire portion of illegal construction on land with a red book. This policy is expected to remove the final bottleneck in the site clearance process.

Mr. Nguyen Van Thuyet - Vice Chairman of Phu Dong Commune People's Committee - said: "The government is focusing highly on completing the approval of the compensation plan. It is expected that by October 22, all documents will be approved. The city aims to complete the handover of the site for the construction of the Duong River Bridge by the end of December 2025".

According to Mr. Mai Xuan Tan - Director of the Duong River Water Transport Upgrade Project (Rel Project Management Board), the progress of the railway bridge depends on the road bridge. "When the road bridge is completed, we can dismantle the old iron bridge to move the railway to the new bridge," said Mr. Tan.

With the site clearance problems gradually being resolved, it is expected that the Duong River bridge project, an important project connecting the center of Hanoi with the northern districts, will soon be restarted, contributing to reducing traffic congestion, promoting socio-economic development on both sides of the river and reducing traffic congestion in the area.

Minh Hạnh
RELATED NEWS

Hanoi is about to hand over enough land, 2 billion-dollar bridges across the Duong River will be completed next year

|

Hanoi - In the fourth quarter, the locality will hand over the site to the investor to build 2 road and railway bridges across the Duong River, completing the project in 2026.

Hanoi is slow to hand over the site, Duong River bridge delays progress

|

Hanoi's delay in handing over the site has hindered the progress of the Duong River bridge project, even though the railway industry has made 10 requests.

Image of the project worth nearly VND1,850 billion to replace Duong Bridge in Hanoi

|

Hanoi - Some new railway and road bridge items across the Duong River, with an investment capital of nearly VND1,850 billion, are gradually emerging after more than 2 years of construction.

Inside the world's most honored tourist village in Tuyen Quang

|

Tuyen Quang - Lo Lo Chai community tourism village still retains its rustic features, rich in indigenous culture and is a favorite destination for tourists.

Culture of self-respecting taxes - the foundation of a strong nation

|

Vietnam has achieved almost comprehensive tax management digitalization: 99% of businesses declare and pay taxes online, hundreds of foreign suppliers declare via electronic portals, millions of declarations are processed automatically each year. Vietnam's digital tax infrastructure has reached the point that many developing countries still dream of. But when data has gone very far, a bigger question arises: Is the level of self-awareness of taxpayers keeping pace with technology?

Harry Kane scores, Bayern extends their winning streak since the beginning of the season to 12 matches

|

In the early morning of October 23 (Vietnam time), Harry Kane continued his impressive scoring form, contributing to Bayern Munich's defeat of Club Brugge 4-0.

Close-up of the traffic hotspots in the East of Ho Chi Minh City about to build overpasses and underpasses

|

HCMC - Binh Thai Intersection (formerly Thu Duc City) will build an overpass and underpass to relieve traffic jams. The main packages are expected to start construction at the end of 2025.

Thailand struggles with cross-border fraud related to Cambodia

|

Every year, Thailand's economy suffers about $27 billion in losses from cross-border fraud networks, many of which are linked to Cambodia.

Hanoi is about to hand over enough land, 2 billion-dollar bridges across the Duong River will be completed next year

CHÁNH TIẾN |

Hanoi - In the fourth quarter, the locality will hand over the site to the investor to build 2 road and railway bridges across the Duong River, completing the project in 2026.

Hanoi is slow to hand over the site, Duong River bridge delays progress

Chánh Tiến |

Hanoi's delay in handing over the site has hindered the progress of the Duong River bridge project, even though the railway industry has made 10 requests.

Image of the project worth nearly VND1,850 billion to replace Duong Bridge in Hanoi

CHÁNH TIẾN |

Hanoi - Some new railway and road bridge items across the Duong River, with an investment capital of nearly VND1,850 billion, are gradually emerging after more than 2 years of construction.