Workers work overtime, working through holidays at the Chau Doc-Can Tho-Soc Trang expressway construction site

Tạ Quang |

Can Tho - On the occasion of National Day September 2, many workers at the Chau Doc - Can Tho - Soc Trang expressway construction site still work overtime and increase shifts to speed up the project progress.

Workers are assured to stick to the construction site

Mr. Nguyen Van Mai (born in 1972, Thanh Quoi commune, Can Tho city), a construction worker on the Chau Doc - Can Tho - Soc Trang expressway at component project 2, has been attached to the construction site for 2 years. Every day, he operates bulldozers, starts working from 7 am and ends around 5 pm. At times when work needs to be accelerated, he often works overtime and overtime is calculated separately.

Ông Nguyễn Văn Mai hằng ngày vận hành xe ủi. Ảnh: Tạ Quang
Mr. Nguyen Van Mai operates a bulldozer every day. Photo: Ta Quang

With a salary of more than 10 million VND/month, Mr. Mai said it is relatively stable, especially compared to work in his hometown. Besides salary, the contractor also takes care of lunch for workers.

On holidays and Tet, workers are rewarded. Especially on these days, if workers still go to work, the working day is doubled. This is a benefit that helps workers have more income when they have to work on holidays, and at the same time creates motivation for workers to feel secure in sticking to the construction site, contributing to ensuring construction progress," Mr. Mai said.

Nhiều mũi thi công vẫn được triển khai dịp lễ. Ảnh: Tạ Quang
Many construction fronts are still being deployed during the holiday. Photo: Ta Quang

Mr. Nguyen Van Ut Nho (52 years old, Thoi Lai commune, Can Tho city) has also been attached to the work at the construction site. His daily job is to work as a seeker, sewing fabric to spread sand.

On overtime days, he works from 7 am to 7 pm, sometimes lasting until 8 pm. During holidays, including National Day September 2, he still happily stays at the construction site to ensure progress.

Ông Nguyễn Văn Út Nhỏ (bên trái) làm công việc kẻ bấc thấm ngang, may vải để trải cát lên. Ảnh: Tạ Quang
Mr. Nguyen Van Ut Nho (left) does the work of stitching across, sewing fabric to spread sand. Photo: Ta Quang

According to Mr. Ut Nho, part-time workers are fully guaranteed regimes, wages are calculated by multiplying by 2 or 3. Workers are also additionally compensated and supported with meals during overtime days.

Mr. Nguyen Dang Son - Deputy Director of Ngoc Bao Trading Construction Co., Ltd. said that the unit is focusing on loading, and at the same time preparing the necessary conditions to deploy the next items.

During the construction process, the biggest difficulty before was the sand material source. Up to now, the sand source has basically been supplied, helping contractors have conditions to accelerate the loading on the route.

During holidays, the contractor still arranges construction workers to ensure progress. Workers working on holidays are entitled to allowances, and there are separate bonuses for overtime workers.

Stone resources need to continue to be allocated

Mr. Hoang Quang Tam - Deputy General Director of Ruby Group Construction Investment Company, the unit currently constructing packages 11, 13, 14 and 22 of Component Project 2 of the Chau Doc - Can Tho - Soc Trang expressway, informed that the source of materials is an issue of particular concern to the contractor.

Dự án thành phần 2 đoạn qua TP Cần Thơ hiện đạt khoảng 62% tiến độ. Ảnh: Tạ Quang
Component project 2 section passing through Can Tho City currently reaches about 62% progress. Photo: Ta Quang

For sand, the investor has basically allocated enough, helping contractors proactively bring materials to the construction site. Currently, the new stone source is allocated about 25% of the demand, and the remaining part is still being considered and allocated.

Mr. Tam added that when the material source is guaranteed, the group will focus maximum resources to accelerate progress. On the occasion of National Day September 2, the unit organized continuous construction, increased shifts, increased crews, mobilized more machinery, equipment, manpower and organized many construction teams.

Mr. Dang Hoang Vinh - Head of Project Management Department 1, Can Tho City Traffic and Agricultural Construction Investment Project Management Board informed that component project 2 section passing through Can Tho City is currently about 62% progress.

Công nhân tăng ca, làm xuyên lễ trên công trường cao tốc. Ảnh: Tạ Quang
Workers work overtime, working through holidays at the expressway construction site. Photo: Ta Quang

Stone for the expressway is mainly mined from An Giang, currently meeting about 40% of the demand. Can Tho City is proposing to the People's Committee of An Giang province to consider expanding and increasing the capacity of stone mines to increase supply.

Contractors are required to increase machinery, equipment, manpower, organize overtime, increase shifts, including holidays and Tet, not to let the construction site be interrupted.

The Chau Doc - Can Tho - Soc Trang expressway construction investment project phase 1, component project 2 section passing through Can Tho City has a total investment of 9,725.097 billion VND, implementation time from 2022 - 2027, with a total length of about 37.42 km.

Tạ Quang
RELATED NEWS

Ca Mau - Dat Mui expressway opens the door to marine economy

|

The Ca Mau - Dat Mui expressway is expected to expand development space, connect industry and logistics with the marine economy, creating new momentum for the southernmost region.

Can Tho studies commercial sand purchase for Chau Doc - Can Tho - Soc Trang expressway project

|

Can Tho - Faced with the shortage of filling sand, the investor is considering a commercial sand purchase plan for the expressway project worth more than 31,000 billion VND.

Can Tho Chairman sets 2 milestones for completing the expressway worth more than 31 trillion VND

|

Can Tho - Mr. Truong Canh Tuyen requested contractors to urgently adjust the construction progress of the expressway, closely following the two completion milestones of July 30, 2027 and December 31, 2027.

Fire broke out at Dak Sak market in Lam Dong, 16 kiosks burned down

|

Lam Dong - A fire broke out at night at Dak Sak market, destroying 16 kiosks of 9 households, with estimated damage of more than 4 billion VND.

Coach Yutaka Ikeuchi: U20 Vietnam still has a chance in the U20 Asian Cup qualifiers

|

Coach Yutaka Ikeuchi affirmed that U20 Vietnam still has a chance and will try to win in the remaining two matches.

Ministry of Health requests to focus efforts on rescuing victims of passenger car overturning in Gia Lai

|

The Ministry of Health requests Gia Lai and hospitals to focus on rescuing 20 victims injured in the passenger car overturning that killed 4 people.

Folk dances take to the streets, Dien Bien is brilliantly colored with Carnival

|

Dien Bien - The colors in the performances have made people many times admire in the international folk dance carnival night.

Lionel Messi announces farewell to Argentina national team

|

Lionel Messi decided to put an end to his international career in the Argentina national team jersey.

Ca Mau - Dat Mui expressway opens the door to marine economy

NHẬT HỒ |

The Ca Mau - Dat Mui expressway is expected to expand development space, connect industry and logistics with the marine economy, creating new momentum for the southernmost region.

Can Tho studies commercial sand purchase for Chau Doc - Can Tho - Soc Trang expressway project

Tạ Quang |

Can Tho - Faced with the shortage of filling sand, the investor is considering a commercial sand purchase plan for the expressway project worth more than 31,000 billion VND.

Can Tho Chairman sets 2 milestones for completing the expressway worth more than 31 trillion VND

Tạ Quang |

Can Tho - Mr. Truong Canh Tuyen requested contractors to urgently adjust the construction progress of the expressway, closely following the two completion milestones of July 30, 2027 and December 31, 2027.