Workers and machinery are busy day and night at metro No. 2 construction site before the start date

Anh Tú |

Ho Chi Minh City is accelerating the relocation of technical infrastructure for metro line 2, many construction teams are working through the night to prepare the ground for the expected start of construction in early 2026.

Ho Chi Minh City is focusing on speeding up the relocation of technical infrastructure for the Ben Thanh - Tham Luong metro line No. 2 to prepare for the groundbreaking ceremony in early 2026.

Recorded at many open-cut locations and stations such as S3 (Dan chu), S7 (Bait Hien), machinery and equipment operate continuously day and night, workers handle complex infrastructure sections located densely on the road.

Due to the construction on crowded routes such as Hoang Van Thu, Cach Mang Thang Tam and Truong Chinh, construction units must have flexible barriers to ensure labor safety, while limiting traffic congestion.

May moc va cong nhan thi cong di doi ha tang ky thuat tren tuyen metro so 2. Ảnh: Anh Tu
Machinery and construction workers relocate technical infrastructure on metro line 2. Photo: Anh Tu
 Thi cong dao ho tai ga S3 (Dan Chu) trong dieu kien giao thong dong duc. Ảnh: Anh Tu
Constructing open excavation at S3 station (Dan Chu) in crowded traffic conditions. Photo: Anh Tu

According to Mr. Phan Cong Bang - Head of the Ho Chi Minh City Urban Railway Management Board (MAUR), after the request of the Government and Ho Chi Minh City leaders to speed up the implementation of metro project No. 2, the Board launched a 60-day and night emulation movement with the goal of "Determination to accelerate, double productivity". This is a key stage to handle the remaining work before the project starts construction.

 Ghi nhan ga S2 Tao Dan (day la nha ga dau tien cua tuyen Metro so 2, ket noi vao he thong nha ga trung tam Ben Thanh) cong tac giai phong mat bang, di doi ha tang da hoan tat. Ảnh: Anh Tu
Recorded at S2 Tao Dan Station (this is the first station of Metro Line 2, connecting to the Ben Thanh Central Station system), site clearance and infrastructure relocation have been completed. Photo: Anh Tu
Doc tuyen duong Cach Mang Thang 8, nhieu thiet bi thi cong duoc huy dong tang cuong phuc vu cong tac chuan bi cho tuyen metro so 2. Ảnh: Anh Tu
Along Cach Mang Thang 8 route, many construction equipment were mobilized to serve the preparation for metro line 2. Photo: Anh Tu

To date, the accumulated construction volume has reached about 70%, of which some stations have completed the entire relocation of technical infrastructure. The restoration work includes medium and low voltage power, water supply and drainage, telecommunications, lighting, trees and traffic lights. Due to limited urban conditions, tangled underground works and many sections arising outside the design documents, handling the scene and technical agreements takes a lot of time. The packages mainly focus on construction from 11pm to 4am to reduce the impact on traffic.

Cong nhan thi cong xuyen dem tai ga S7 (Bay Hien) de xu ly ha tang ky thuat phuc vu tuyen metro so 2.
Workers work through the night at S7 station ( Bay Hien) to handle technical infrastructure for metro line 2. This is a complicated stage in Metro No. 2 project (Ben Thanh - Tham Luong). Photo: Anh Tu

Currently, MAUR is arranging 11 construction teams at the same time at key locations such as CC1 (Ben Thanh - Tao Dan open excavation section), Station S3 (Dan Chu), Station S6 (Pham Van Hai), Station S7 (Ba Hien), Station S9 (Ba Queo) and Station S10 (Pham Van Bach). All aim to basically complete the relocation and reconstruction of technical infrastructure by the end of 2025.

Cac goi thau di doi ha tang du an Metro 2 chu yeu thi cong ban dem, tu 23 gio den 4 gio sang, nen tien do chiu anh huong boi thoi tiet va mat do giao thong.
The infrastructure relocation packages of Metro 2 project are mainly constructed at night, from 11pm to 4am, so the progress is affected by weather and traffic density. Photo: Anh Tu

Along with construction activities outside the site, the preparation of project documents is also being promoted to submit to the Ho Chi Minh City People's Committee before December 15, as a basis for implementing the selection of the main contractor and aiming to start construction of metro line No. 2 around January 15, 2026.

Metro Line 2 is more than 11 km long, including 10 stations (9 underground, 1 above ground) and 2 open-cut sections, connecting from Ton Duc Thang - Ham Nghi intersection to Tham Luong depot with an area of 22.3 hectares. The total investment approved in 2019 is VND 47,890.84 billion. When completed, the route will contribute to significantly reducing the load on the Cach Mang Thang Tam - Truong Chinh axis, connecting the city center with Tan Binh and the Northwest region, and connecting with metro line 1.

Du kien cong tac di doi ha tang ky thuat se hoan thanh cuoi nam 2025, chuan bi cho viec khoi cong metro so 2 dau nam 2026. Ảnh: Anh Tu
It is expected that the relocation of technical infrastructure will be completed by the end of 2025, preparing for the start of metro line 2 in early 2026. Photo: Anh Tu

According to the plan, Ho Chi Minh City plans to allocate about VND10,000 billion per year to implement the project during the construction phase. The city also requires relevant departments, branches and localities to speed up the processing of procedures, apply technology to shorten the time for handling documents, and at the same time strengthen progress monitoring. The entire project aims to be constructed in 57 months, completed and operated in 2030.

Anh Tú
RELATED NEWS

Ho Chi Minh City has a 5-year plan for Metro Line 2, don't lose your promise any more!

|

Metro Line 2 (Ben Thanh - Tham Luong) of Ho Chi Minh City will start construction on January 15, 2026, applying many specific mechanisms to speed up progress, expected to be completed in 2030.

Construction of An Phu, My Thuy intersections, Metro No. 2 HCMC causes damage to roads, traffic jams

|

HCMC - The construction of An Phu intersection, My Thuy intersection, and relocation of Metro 2 infrastructure has caused many degraded and damaged roads, causing traffic congestion.

HCMC finalizes the groundbreaking of Metro Line 2 on January 15, 2026

|

Ho Chi Minh City finalizes the groundbreaking of Metro Line 2 (Ben Thanh - Tham Luong) on January 15, 2026, applying many specific mechanisms to speed up progress.

Checking signs of illegal social housing trading in Thai Nguyen

|

Thai Nguyen - The authorities have stepped in to verify signs of illegal buying and selling and transferring at the social housing project in Dai Thang residential area.

A crane fell into a house, two children escaped the accident

|

Hanoi - This afternoon, November 15, a crane about 30m long tilted and collapsed part of the house next door, the two children were lucky to escape.

Nearly half of Westerners feel overlooked by the government

|

A major survey shows that 45% of Westerners are dissatisfied with democracy, feel overlooked by the government and worry about a worsening future.

Car lost control and crashed into two vehicles traveling in the same direction in front

|

Hanoi While traveling on the elevated Ring Road 2, a car suddenly lost control and pushed forward, crashing into two other vehicles.

Foreign investors still sell net in the stock market

|

Foreign investors continue to record the 16th consecutive week of net selling in the stock market, focusing on banking stocks.

Ho Chi Minh City has a 5-year plan for Metro Line 2, don't lose your promise any more!

Lê Thanh Phong |

Metro Line 2 (Ben Thanh - Tham Luong) of Ho Chi Minh City will start construction on January 15, 2026, applying many specific mechanisms to speed up progress, expected to be completed in 2030.

Construction of An Phu, My Thuy intersections, Metro No. 2 HCMC causes damage to roads, traffic jams

MINH QUÂN |

HCMC - The construction of An Phu intersection, My Thuy intersection, and relocation of Metro 2 infrastructure has caused many degraded and damaged roads, causing traffic congestion.

HCMC finalizes the groundbreaking of Metro Line 2 on January 15, 2026

MINH QUÂN |

Ho Chi Minh City finalizes the groundbreaking of Metro Line 2 (Ben Thanh - Tham Luong) on January 15, 2026, applying many specific mechanisms to speed up progress.