On June 10, at the meeting with voters before the 2025 mid-term session of the 10th term of the City People's Council for the 2021-2026 term, voters gave their opinions on handling the Hoa Xuan bridge intersection (Cam Le district, Da Nang city), although there are barriers during rush hours, traffic congestion in this area still causes difficulties for people when traveling.
Voter Le Minh Cham - Hoa Cuong Nam ward, Hai Chau district - said that currently, the Hoa Xuan bridge area has a very high traffic density, making it very difficult to pass through this area every time, especially during rush hour.
According to Mr. Cham, installing barriers is necessary and also has a certain effect, however, this is only a temporary measure, and cannot completely resolve the congestion. Notably, nearly 2 years have passed since there was information about the project, but people still do not know specifically when the project will be officially implemented.
Responding to voters' opinions, Mr. Le Trung Chinh - Chairman of Da Nang City People's Committee - said that the Hoa Xuan bridge project is expected to be approved in June 2025. According to Mr. Chinh, because this area intersects with many major roads, the development of the plan is facing many difficulties. The city has proposed many different options to optimize this area.
Accordingly, Hoa Xuan Bridge is an important gateway connecting urban areas in the South of Da Nang, becoming a black spot for traffic congestion.
Not only during rush hour, the traffic flow is dense, inching forward on Nguyen Phuoc Lan, Thang Long, Le Thanh Nghi, Cach Mang Thang Tam, Nui Thanh, and Duong 2 Thang 9 streets flowing down to Hoa Xuan bridge. This situation not only makes it difficult for people to travel but also affects the economic and social activities of the area.
Since March 2024, the People's Council of Da Nang City has approved the investment policy for the Le Thanh Nghi - Cach Mang Thang Tam - Thang Long - intersection project - the road leading to Hoa Xuan bridge with a total investment of nearly 1,940 billion VND, expected to be completed in the 2024-2028 period.
The design plan includes building a new 6-lane Hoa Xuan bridge, organizing traffic at different levels on the Cach Mang Thang Tam route, expanding the Thang Long - Cau Hoa Xuan intersection and renovating neighboring intersections.
The architectural planning competition has been held and awarded since November 2024. In particular, the Organizing Committee of the contest awarded the first prize of 400 million VND to the consortium of Chodai & Kiso Jiban Vietnam Co., Ltd. - T&D Vietnam Construction Consulting Joint Stock Company - NH Village Architectural Design Co., Ltd. - Hoa Phong E&C Investment & Development Joint Stock Company.
After awarding the prize, Da Nang plans to research and select good and highly feasible ideas in the competition plans to complete the investment plan for the construction of the new Hoa Xuan Bridge Project and the Hoa Xuan Bridge Intersection Cluster, and submit it to competent authorities for approval for implementation.