Appearance of the 118 billion VND road to Phan Thiet airport just opened to traffic

DUY TUẤN |

Binh Thuan - The Phan Thiet airport access road project (phase 2) has been opened to traffic; vehicles are moving smoothly after nearly 1 year of construction.

According to the investor, the Management Board of Investment and Construction of Traffic Works of Binh Thuan Province, the Phan Thiet Airport access road project (phase 2) has been opened to traffic. This is the road connecting Phan Thiet International Airport (Phan Thiet Airport) with the Vo Nguyen Giap coastal road (leading to Mui Ne - Bau Trang).

Duong vao san bay Phan Thiet vua thong xe. Anh: Duy Tuan
The road to Phan Thiet airport has just opened to traffic. Photo: Duy Tuan
Bien chi dan tren duong Vo Nguyen Giap chi duong vao san bay Phan Thiet. Anh: Duy Tuan
Sign on Vo Nguyen Giap Street showing the way to Phan Thiet airport. Photo: Duy Tuan

The project is 3.63km long, with a 36m wide roadbed, of which the road surface is 13.5m wide and the sidewalks on each side are 5m wide. The project also includes a drainage system, trees, lighting, and fire-fighting water supply.

Mat duong tham nhua lang min voi vach son ke duong vua ke xong. Anh: Duy Tuan
Smooth asphalt road surface with newly painted road markings. Photo: Duy Tuan
He thong cap nuoc chua chay bo tri doc tuyen duong. Anh: Duy Tuan
Fire water supply system is arranged along the road. Photo: Duy Tuan

The entire route has been completed with asphalt, painted road markings, lighting system, trees, drainage; traffic lights have been installed.

Cac bien bao hieu va he thong tu dien tren duong. Anh: Duy Tuan
Road signs and electrical cabinets. Photo: Duy Tuan

Many cars and motorbikes were circulating smoothly on the road.

Via he duoc lat gach. Anh: Duy Tuan
The sidewalk is paved with bricks. Photo: Duy Tuan
Doan chua hoan thien lat gach via he dang duoc thi cong. Anh: Duy Tuan
The unfinished section of the sidewalk is under construction. Photo: Duy Tuan

On the left side of the sidewalk, there are some sections where the paving has not been completed, so some workers are still working on paving the sidewalk. However, this does not affect the traffic flow.

He thong den chieu sang 2 ben duong da hoan thien. Anh: Duy Tuan
The lighting system on both sides of the road has been completed. Photo: Duy Tuan
Cac bien chi dan, cay xanh trong ven tuyen duong. Anh: Duy Tuan
Signs and trees planted along the road. Photo: Duy Tuan
Den tin hieu giao thong tai dau duong vao san bay Phan Thiet ket noi voi duong Vo Nguyen Giap. Anh: Duy Tuan
Traffic lights at the entrance to Phan Thiet airport connecting to Vo Nguyen Giap street. Photo: Duy Tuan

The project, with a total investment of about 117.9 billion VND, started construction at the end of January 2024 and was completed on schedule at the end of December 2024.

Phan Thiet Airport is located in Thien Nghiep Commune, Phan Thiet City, Binh Thuan Province with a total area of ​​543 hectares, approved by the Prime Minister in 2009. This is a dual-use airport serving both military and civilian purposes. The project started in January 2015.

Up to now, the military items have been completed and the Air Defense - Air Force is operating military flights. As for the civil items, due to adjustments from the airport level and project scale, they are currently carrying out procedures according to regulations.

DUY TUẤN
TIN LIÊN QUAN

Busy laying asphalt to complete the road to Phan Thiet airport

|

Binh Thuan - About 1km of road is still being paved to complete the Phan Thiet airport road project as planned.

Phan Thiet airport civil works expected to start in 2025

|

Binh Thuan - The progress of the Phan Thiet Airport project, civil project under BOT contract form, is waiting for the Prime Minister to review and approve the investment policy.

The collective leadership of Dak Nong Department of Construction asks to learn from experience

|

Dak Nong - The collective leadership of the provincial Department of Construction would like to accept reviewing and drawing experience due to shortcomings in the work of arranging and assigning leaders at the department level.

The maximum average retail price of electricity is VND 2,444.09/kWh

|

According to the new regulations, the minimum average retail price for electricity is VND 1,826.22/kWh; the maximum average retail price for electricity is VND 2,444.09/kWh.

829 projects in Hanoi are subject to handling

|

Hanoi - The city will focus on handling 712 projects and 117 projects that are behind schedule and slow to be implemented by the People's Committees at the district level that propose and propose handling.

A series of projects violated planning in Bac Ninh, Ba Ria - Vung Tau

|

The Government Inspectorate has just pointed out a series of projects violating planning in Bac Ninh, Ba Ria - Vung Tau.

France and the UK still consider sending troops to Ukraine

|

The UK and France are still pushing for plans to establish peacekeeping forces in Ukraine despite domestic opposition.

Pay attention to training cadres, meeting the requirements of restructuring the apparatus

|

In the coming time, it is necessary to pay attention to training and fostering cadres, meeting the requirements of restructuring the apparatus...

Busy laying asphalt to complete the road to Phan Thiet airport

Duy Tuấn |

Binh Thuan - About 1km of road is still being paved to complete the Phan Thiet airport road project as planned.

Phan Thiet airport civil works expected to start in 2025

Duy Tuấn |

Binh Thuan - The progress of the Phan Thiet Airport project, civil project under BOT contract form, is waiting for the Prime Minister to review and approve the investment policy.

Sân bay Phan Thiết hạng mục dân dụng sẽ có nhà đầu tư mới

DUY TUẤN |

Bình Thuận - Sau khi Thủ tướng Chính phủ phê duyệt điều chỉnh chủ trương đầu tư dự án sân bay Phan Thiết hạng mục dân dụng, Bình Thuận sẽ lựa chọn nhà đầu tư mới.