Speed up the progress of the 691 billion VND Van Mieu Park project in Bac Ninh

Vân Trường |

Bac Ninh - Vice Chairman of the Provincial People's Committee Le Xuan Loi has just chaired a conference to remove difficulties and obstacles in the Van Mieu Park project ( Vo Cuong ward).

Reporting at the conference, the leader of Vo Cuong ward said that the investment project to build technical infrastructure and auxiliary works of Van Mieu Park has a total investment of more than 691 billion VND, with implementation progress from 2024 - 2027.

The project is built on an area of about 4.7 hectares, divided into 3 areas.

On July 16, 2025, the People's Committee of Vo Cuong Ward approved the first phase of compensation, support and resettlement plan for the project with a total area of over 10,000 m2, the number of households with recovered land is 48 households, the total compensation and support cost is over 361 billion VND. To date, Kinh Bac Land Fund Development Center Branch has paid 3/48 households with a budget of more than 11 billion VND.

Regarding investment and construction, up to now, Zone 1 has implemented construction and completed 85%; expected to be completed in July 2025. Areas No. 2 and 3 are under construction; expected to start construction in August 2025 and be completed in December 2025.

During the project implementation, there were some difficulties and problems due to some cases where additional documents have not been completed to develop a compensation and support plan and no consensus has been reached on relocating resettlement locations; part of the area within the administrative boundaries of the old Tien Ninh Ve ward (now Kinh Bac ward) has not been handed over to the investor; investment capital has not been disbursed because the units do not have account codes...

Concluding the conference, Vice Chairman of the Provincial People's Committee Le Xuan Loi affirmed that this is a particularly important project, of interest to Party and State leaders and that General Secretary To Lam personally attended the groundbreaking ceremony in January 2025.

The Vice Chairman of the Provincial People's Committee emphasized that the province has committed to the General Secretary that it will basically complete the project's construction items in December 2025, so the project investor needs to urgently direct contractors to speed up the construction progress of packages to ensure quality, safety and technical and aesthetic aspects; conduct weekly progress counting and regular work reports.

Particularly for items in the Uncle Ho Temple area invested with socialized sources, focusing on implementing and completing the designs of lotus ponds and bridges to the Temple according to the approved plan.

The Vice Chairman of the People's Committee of Bac Ninh province also requested Vo Cuong ward to urge investors to implement investment projects to build resettlement housing areas for technical infrastructure projects and auxiliary works of the Temple of Literature Park.

Regarding the proposals and recommendations, Mr. Le Xuan Loi agreed to complete the Council for selecting the architectural design and art of relief. At the same time, it is recommended that the Department of Finance study and issue documents guiding procedures related to budget allocation to implement the project in accordance with regulations.

Vân Trường
TIN LIÊN QUAN

Investor of 50-hectare industrial park in Bac Ninh requests guidance on construction licensing

|

Bac Ninh - Bac Giang Import-Export Joint Stock Company requested guidance on implementing procedures in the construction sector with Viet Nhat Industrial Park.

Bac Ninh reviews the renovation and construction of old apartment buildings

|

Bac Ninh - The Provincial People's Committee requested a synthesis and report on the situation and results of the renovation and reconstruction of old apartment buildings in the province.

Traffic organization at the 1,500 billion VND bridge connecting Bac Ninh - Hai Phong

|

Bac Ninh - The Provincial People's Committee approved the traffic organization plan at the Km3+500 route of the Dong Viet bridge project.

Proposal to establish another commune-level professional department in Hanoi and specific provinces

|

Hanoi - The Department of Home Affairs proposed to allow the city and some localities with large scale and development characteristics to establish an additional professional department at the commune level.

The psychology of blaming victims after the Ha Long Bay tragedy and the deterioration of compassion

|

After the tragic accident in Ha Long Bay, instead of sympathy, many people blamed the victims. This reflects the erosion of compassion.

Starting construction of trade union social housing project in Dong Thap province

|

Dong Thap - On the morning of July 26, in Dong Thap, the groundbreaking ceremony for the trade union social housing project under the trade union institution construction project in My Tho Industrial Park, Trung An Industrial Cluster took place.

Image of the first wild elephant born in the wild in Da Nang

|

Da Nang - The image of baby elephants appearing through camera traps is a valuable result after many years of efforts to preserve forests and wildlife in Da Nang.

Starting construction of My An - Cao Lanh Expressway worth over VND6,100 billion

|

Dong Thap - My An - Cao Lanh Expressway Phase 1, 26.6 km long, has an investment capital of more than VND 6,100 billion.

Investor of 50-hectare industrial park in Bac Ninh requests guidance on construction licensing

Vân Trường |

Bac Ninh - Bac Giang Import-Export Joint Stock Company requested guidance on implementing procedures in the construction sector with Viet Nhat Industrial Park.

Bac Ninh reviews the renovation and construction of old apartment buildings

Vân Trường |

Bac Ninh - The Provincial People's Committee requested a synthesis and report on the situation and results of the renovation and reconstruction of old apartment buildings in the province.

Traffic organization at the 1,500 billion VND bridge connecting Bac Ninh - Hai Phong

Vân Trường |

Bac Ninh - The Provincial People's Committee approved the traffic organization plan at the Km3+500 route of the Dong Viet bridge project.