Localities and contractors are "out of sync", the project to upgrade National Highway 19 through Binh Dinh is sluggish

Xuân Nhàn |

As the completion deadline (October 31, 2024) approaches, the XL-01 package of the Central Highlands Traffic Connectivity Enhancement Project (National Highway 19), section through Tay Son district, Binh Dinh, remains in disarray due to the lack of consensus between local authorities and contractors.

Serious "bottleneck"

XL-01 is the most sluggish package among the 8 packages invested by Project Management Board 2, Ministry of Transport. On the route Km50 - Km66+515, XL-01 has nearly 10km passing through residential areas of Tay Thuan and Tay Giang communes; the rest is the section crossing An Khe pass. The package is constructed by Trung Nam 18 E&C Construction Joint Stock Company. Both components are unfinished and behind schedule.

In Tay Giang commune, the Ba La bridge project has been "inactive" for many times. Without access roads, the bridge looks like a truncated back. Two-way traffic as well as the lives and activities of residents in the area are increasingly unsafe due to the prolonged makeshift construction and pollution.

Ba La Bridge, Bau Sen and the road section through it are serious “bottlenecks”. The roadbed is too high, houses are “pulled” down deep; the rolling and compacting work cracks the walls; the dust and dirt surrounds day and night… are the reasons for the wave of fierce reactions.

According to the contractor, there are sections where the C19 asphalt layer was completed in April 2024 but has not been completed yet. The section between Bau Sen and Ba La bridges, the contractor wanted to pour the aggregate before paving the asphalt, but was forced to stop because the locals fiercely opposed it. Some people even lay down in front of the car!

Meanwhile, when reporting to the People's Committee of Binh Dinh province, Project Management Board 2, and Tay Son district People's Committee, they did not hesitate to complain: "Roadbed rolling construction caused damage and cracks in houses and structures, but the appraisal and compensation work for affected households is still very slow. Only 228/1,156 households with houses and structures cracked due to construction have been compensated. The slow construction progress and prolonged dust emissions have affected people's lives. The system of ditches and drainage pipes along both sides of the road has not been completed, including locations where clean land has been handed over."

Nha dan bi giai toa tai xa Tay Giang de thi cong Quoc lo 19. Anh: Xuan Nhan
Houses were cleared in Tay Giang commune to construct the National Highway 19 upgrade project. Photo: Xuan Nhan

"The monk says the monk is right, the nun says the nun is right"

Vice Chairman of Tay Son District People's Committee Nguyen Van Khanh said: "No other project has the local government been as persistent in following as with Highway 19. Every week, we are present at the scene. I even know by heart the names and circumstances of each complaint case. Regarding enforcement and construction protection, Tay Son is also ready with a plan."

Mr. Khanh did not avoid the question about the “out of sync” relationship between the locality and the contractor: “The district requested to provide a construction plan to have a basis for coordination, but they did not respond! The difficulty and delay are on An Khe Pass, but down here, if we focus on the work, it will only take 7-10 days to complete the service road. They are just looking for ways to delay.”

On the other hand, the contractor's representative... complained: "When people obstructed, the authorities immediately used the cracked house construction as an excuse to settle the score, making the matter even more difficult to resolve. We asked for intervention many times, but the authorities did not understand or share."

This person explained: “Support, compensation for site clearance and compensation for property damage during construction are two different issues. The project did not fulfill its responsibility to the people in site clearance, leading to obstruction of construction, we accept. But if the house cracks due to rolling and compacting, that is a civil relationship. The responsibility belongs to us; it is just that we cannot compensate immediately if we want to. There are also surveys, assessments, appraisals, estimates, consultations with related parties, and even arbitration. All projects are like that, construction first, compensation for damages later. If we continue to drag our feet and obstruct, how can we have the land to work?”

The project to enhance traffic connectivity in the Central Highlands region has a length of 143km through Gia Lai and Binh Dinh; total investment of 155.8 million USD (more than 3,600 billion VND); of which, the World Bank (WB) lends 150 million USD, non-refundable aid from the Australian Government 2.1 million USD; domestic counterpart capital 3.7 million USD. Instead of completing in June 2023, the project encountered many difficulties and the investment policy was adjusted, allowing it to be extended until December 31, 2024.

Xuân Nhàn
RELATED NEWS

Court accepts labor lawsuit against Mai Linh Group for social insurance debt

|

The People's Court of Region 1 - Khanh Hoa has just accepted the social insurance dispute between employees and Mai Linh Group Joint Stock Company.

Chay River landslide: People suspect it is due to hydropower, businesses refute

|

Lao Cai - People believe that hydropower plants accumulating water for operation are the main cause of riverbank erosion on the Chay River.

Bad news

|

Mrs. Ha Thi Trac, born in 1930, is the mother of comrade Nguyen Dinh Chuc - former Deputy Editor-in-Chief of Lao Dong Newspaper; hometown: Thai Hoa commune, Phu Tho province; passed away at 9:45 am on January 11, 2026 (ie, November 23rd of the year At Ty), at the age of 96.

White dolphins appear near Thanh Hoa beach

|

Thanh Hoa - A herd of dolphins suddenly appeared in the area near Sam Son beach, including white dolphins.

Witnesses witness the fire at a row of houses at Binh Trung market in Ho Chi Minh City

|

Ho Chi Minh City - Witnesses recounted the moment smoke and fire flared up fiercely in a row of houses in Binh Trung market, a large fire that caused many people to panic and flee.

Personnel transfer and appointment in Phu Tho, Hue, Quang Tri, Dong Nai

|

Hue, Quang Tri, Phu Tho, Dong Nai... are localities that have just implemented decisions to transfer, appoint, and appoint personnel last week.

Risk of power shortage as series of power projects fall behind schedule

Anh Tuấn |

The Ministry of Industry and Trade believes that the delay in implementing power source projects poses a huge risk of power source capacity shortage in the 2026-2030 period.

Handling of wind power projects on forest land in Quang Tri according to regulations

HƯNG THƠ |

The Forestry Department requested Quang Tri province to strictly handle organizations and individuals involved in the wind power project built on forest land according to the law.

Proposal for designating a contractor for the new Phong Chau bridge construction project

Tô Công |

Phu Tho Department of Transport proposed to apply a special mechanism, appointing a shortened bid to speed up the implementation of the new Phong Chau bridge construction project.