Localities and contractors are "out of sync", the project to upgrade National Highway 19 through Binh Dinh is sluggish

Xuân Nhàn |

As the completion deadline (October 31, 2024) approaches, the XL-01 package of the Central Highlands Traffic Connectivity Enhancement Project (National Highway 19), section through Tay Son district, Binh Dinh, remains in disarray due to the lack of consensus between local authorities and contractors.

Serious "bottleneck"

XL-01 is the most sluggish package among the 8 packages invested by Project Management Board 2, Ministry of Transport. On the route Km50 - Km66+515, XL-01 has nearly 10km passing through residential areas of Tay Thuan and Tay Giang communes; the rest is the section crossing An Khe pass. The package is constructed by Trung Nam 18 E&C Construction Joint Stock Company. Both components are unfinished and behind schedule.

In Tay Giang commune, the Ba La bridge project has been "inactive" for many times. Without access roads, the bridge looks like a truncated back. Two-way traffic as well as the lives and activities of residents in the area are increasingly unsafe due to the prolonged makeshift construction and pollution.

Ba La Bridge, Bau Sen and the road section through it are serious “bottlenecks”. The roadbed is too high, houses are “pulled” down deep; the rolling and compacting work cracks the walls; the dust and dirt surrounds day and night… are the reasons for the wave of fierce reactions.

According to the contractor, there are sections where the C19 asphalt layer was completed in April 2024 but has not been completed yet. The section between Bau Sen and Ba La bridges, the contractor wanted to pour the aggregate before paving the asphalt, but was forced to stop because the locals fiercely opposed it. Some people even lay down in front of the car!

Meanwhile, when reporting to the People's Committee of Binh Dinh province, Project Management Board 2, and Tay Son district People's Committee, they did not hesitate to complain: "Roadbed rolling construction caused damage and cracks in houses and structures, but the appraisal and compensation work for affected households is still very slow. Only 228/1,156 households with houses and structures cracked due to construction have been compensated. The slow construction progress and prolonged dust emissions have affected people's lives. The system of ditches and drainage pipes along both sides of the road has not been completed, including locations where clean land has been handed over."

Nha dan bi giai toa tai xa Tay Giang de thi cong Quoc lo 19. Anh: Xuan Nhan
Houses were cleared in Tay Giang commune to construct the National Highway 19 upgrade project. Photo: Xuan Nhan

"The monk says the monk is right, the nun says the nun is right"

Vice Chairman of Tay Son District People's Committee Nguyen Van Khanh said: "No other project has the local government been as persistent in following as with Highway 19. Every week, we are present at the scene. I even know by heart the names and circumstances of each complaint case. Regarding enforcement and construction protection, Tay Son is also ready with a plan."

Mr. Khanh did not avoid the question about the “out of sync” relationship between the locality and the contractor: “The district requested to provide a construction plan to have a basis for coordination, but they did not respond! The difficulty and delay are on An Khe Pass, but down here, if we focus on the work, it will only take 7-10 days to complete the service road. They are just looking for ways to delay.”

On the other hand, the contractor's representative... complained: "When people obstructed, the authorities immediately used the cracked house construction as an excuse to settle the score, making the matter even more difficult to resolve. We asked for intervention many times, but the authorities did not understand or share."

This person explained: “Support, compensation for site clearance and compensation for property damage during construction are two different issues. The project did not fulfill its responsibility to the people in site clearance, leading to obstruction of construction, we accept. But if the house cracks due to rolling and compacting, that is a civil relationship. The responsibility belongs to us; it is just that we cannot compensate immediately if we want to. There are also surveys, assessments, appraisals, estimates, consultations with related parties, and even arbitration. All projects are like that, construction first, compensation for damages later. If we continue to drag our feet and obstruct, how can we have the land to work?”

The project to enhance traffic connectivity in the Central Highlands region has a length of 143km through Gia Lai and Binh Dinh; total investment of 155.8 million USD (more than 3,600 billion VND); of which, the World Bank (WB) lends 150 million USD, non-refundable aid from the Australian Government 2.1 million USD; domestic counterpart capital 3.7 million USD. Instead of completing in June 2023, the project encountered many difficulties and the investment policy was adjusted, allowing it to be extended until December 31, 2024.

Xuân Nhàn
TIN LIÊN QUAN

Nguy cơ thiếu điện khi loạt dự án điện chậm tiến độ

Anh Tuấn |

Bộ Công Thương cho rằng, việc chậm triển khai các dự án nguồn điện gây nguy cơ thiếu hụt công suất nguồn điện rất lớn trong giai đoạn 2026-2030.

Xử lý theo quy định dự án điện gió trên đất rừng ở Quảng Trị

HƯNG THƠ |

Cục Kiểm lâm đề nghị tỉnh Quảng Trị xử lý nghiêm theo quy định của pháp luật đối với tổ chức, cá nhân có liên quan vụ dự án điện gió xây trên đất rừng.

Đề xuất phương án chỉ định thầu dự án xây cầu Phong Châu mới

Tô Công |

Sở Giao thông Vận tải Phú Thọ đề xuất áp dụng cơ chế đặc thù, sẽ chỉ định thầu rút gọn để đẩy nhanh tiến độ triển khai dự án xây dựng cầu Phong Châu mới.

Thụy Sĩ giải cứu 2 nhà leo núi Việt Nam ở độ cao hơn 3.500m

Song Minh |

Hai nhà leo núi Việt Nam đã được giải cứu khỏi đỉnh núi Matterhorn ở Thụy Sĩ khi rơi vào tình huống nguy hiểm đến tính mạng.

Cựu TGĐ Vạn Thịnh Phát muốn dùng tiền lương trả cho trái chủ

Tâm Tú |

TPHCM - Sáng 25.9, TAND TPHCM tiếp tục xét hỏi về hành vi “Rửa tiền” và “Vận chuyển tiền tệ trái phép qua biên giới” trong vụ án Vạn Thịnh Phát giai đoạn 2.

Quảng Nam sơ tán khẩn cấp hàng trăm người dân vì sạt lở

Hoàng Bin |

Mới đầu mùa mưa, miền núi Quảng Nam đã xuất hiện những điểm sạt lở mới, đe dọa các khu dân cư và nhiều tuyến giao thông. Hàng trăm người dân phải sơ tán, tìm nơi ở mới.

Cập nhật giá vàng sáng 25.9: Ồ ạt tăng cao

Khương Duy |

Cập nhật giá vàng sáng 25.9: Kim loại quý trên thị trường thế giới ồ ạt tăng lên, phá mọi kỷ lục.

Người dân trong vụ sạt lở ở Sa Pa sẽ có nơi ở mới

Đinh Đại |

Lào Cai - Các hộ dân trong vụ sạt lở tại xã Mường Hoa (thị xã Sa Pa) sẽ được bố trí xây nhà mới để ổn định cuộc sống.

Risk of power shortage as series of power projects fall behind schedule

Anh Tuấn |

The Ministry of Industry and Trade believes that the delay in implementing power source projects poses a huge risk of power source capacity shortage in the 2026-2030 period.

Handling of wind power projects on forest land in Quang Tri according to regulations

HƯNG THƠ |

The Forestry Department requested Quang Tri province to strictly handle organizations and individuals involved in the wind power project built on forest land according to the law.

Proposal for designating a contractor for the new Phong Chau bridge construction project

Tô Công |

Phu Tho Department of Transport proposed to apply a special mechanism, appointing a shortened bid to speed up the implementation of the new Phong Chau bridge construction project.