Urging the progress of Ban Mong Reservoir Project

QUANG ĐẠI |

On the afternoon of January 8, the Ministry of Agriculture and Rural Development held an online meeting of the Steering Committee for the implementation of the Ban Mong Reservoir Project, phase 1, and listened to the project research report for phase 2.

Mr. Nguyen Hoang Hiep - Deputy Minister of Agriculture and Rural Development, Head of the Steering Committee chaired the meeting. Vice Chairman of Nghe An Provincial People's Committee Nguyen Van De attended and chaired at Nghe An bridge. Also attending were Director of the Department of Agriculture and Rural Development Phung Thanh Vinh; leaders of relevant sectors, units and localities.

The Ban Mong Reservoir Project is built on the Hieu River, with a reservoir area of ​​25 square kilometers, mainly located in Quy Hop district (Quy Chau, Nghia Dan, Nghe An province) and part of Nhu Xuan district (Thanh Hoa province).

The unit project is located in Yen Hop commune, Quy Hop district. Ban Mong Reservoir Project Phase 1, Nghe An province has a capacity of 225 million m3, 8 water pumping stations along Hieu river and a 45MW hydropower plant.

Du an Ho chua nuoc Ban Mong do Ban Quan ly dau tu va xay dung thuy loi 4, Bo NNPTNT lam chu dau tu. Anh: Anh Tuan
The Ban Mong Reservoir Project is invested by the Irrigation Construction and Investment Management Board 4, Ministry of Agriculture and Rural Development. Photo: Anh Tuan

Phase 1 of the project has a total estimated investment of 5,552 billion VND, allocated from the state budget. In 2010, the project was started, with the Irrigation Construction and Investment Management Board 4 as the investor of the unit project cluster and the Department of Agriculture and Rural Development of Nghe An as the investor of the compensation, support and resettlement component.

The project was approved by the Prime Minister to adjust the investment policy in Decision No. 1248 dated October 26, 2023; the Minister of Agriculture and Rural Development approved the adjustment of the investment project in Decision No. 532 dated February 7, 2024.

According to the report of the Department of Agriculture and Rural Development of Nghe An, the current site clearance work of the reservoir ensures the set progress. For the downstream of the auxiliary dam III, the compensation elevation has been determined, and the survey outline and measurement records are currently being prepared. After the outline is approved, the bidding plan will be requested for approval; the selection of a consulting contractor will be organized to prepare the records; the counting and approval of the compensation and payment plan will be carried out.

Regarding the Chau Binh Drainage Canal project, the bidding part has been basically completed with the accepted and paid value of 95%. The land clearance of the reservoir area below the elevation of +71.86 is still 29.3 hectares that have not been handed over. The land clearance part to prevent flooding at the tail of the Chau Binh Drainage Canal has not been implemented because the canal treatment plan has not been selected and there is not enough funding...

Speaking at the meeting, Deputy Minister of Agriculture and Rural Development Nguyen Hoang Hiep assessed that after the second meeting of the Steering Committee, Nghe An province has done a lot of work in the past time, but to ensure the completion of all the work content of phase 1 of the project in 2025, there are still many things to be solved and more efforts must be made to ensure progress requirements.

Deputy Minister Nguyen Hoang Hiep noted some contents in implementing site clearance work and adjusting some project construction items.

QUANG ĐẠI
TIN LIÊN QUAN

The expressway project in Binh Duong will run parallel to Suoi Cai for 7km

|

Binh Duong - The Ho Chi Minh City - Thu Dau Mot - Chon Thanh expressway project will run parallel to the Suoi Cai dredging and reinforcement project for a section of about 7km.

Land acquisition issues cause two key projects in Quang Binh to face difficulties in construction

|

Two key projects with a total investment of thousands of billions of VND in Quang Binh province have yet to be implemented smoothly due to land acquisition problems.

Social insurance reduces many units after restructuring and streamlining

|

Vietnam Social Security is expected to become a public service unit of the Ministry of Finance, with 14 departments, 7 units less than at present.

Tao Quan ticket prices skyrocketed by 10 million VND before filming time

|

Before the recording of the Tao Quan program, the price of tickets increased to tens of millions of VND/pair.

Warm hearts of workers in Binh Dinh

|

Union members and workers in Binh Dinh felt warm when leaders of the Party, State and Vietnam General Confederation of Labor visited and presented meaningful gifts.

National Assembly Chairman: Laws must be concise and focused

|

The National Assembly Chairman said that when promulgated, the Law must be concise, focused, and only focus on amending truly necessary issues.

Illegal land exploitation in Soc Son: Consider prosecuting the case and prosecuting the accused

|

Following Lao Dong's article, the People's Committee of Soc Son district said it will strictly handle illegal land exploitation subjects, and criminal cases will be prosecuted.

The expressway project in Binh Duong will run parallel to Suoi Cai for 7km

ĐÌNH TRỌNG |

Binh Duong - The Ho Chi Minh City - Thu Dau Mot - Chon Thanh expressway project will run parallel to the Suoi Cai dredging and reinforcement project for a section of about 7km.

Đồng ý bàn giao mặt bằng dự án VSIP Nghệ An

QUANG ĐẠI |

Nghệ An - Được địa phương tích cực vận động, 2 hộ gia đình đồng ý nhận tiền, bàn giao mặt bằng thi công dự án trọng điểm của tỉnh.

Land acquisition issues cause two key projects in Quang Binh to face difficulties in construction

CÔNG SÁNG |

Two key projects with a total investment of thousands of billions of VND in Quang Binh province have yet to be implemented smoothly due to land acquisition problems.