Energizing the 500kV line of circuit 3 in Quynh Luu - Thanh Hoa

Trần Lâm |

After a period of competition with the spirit of "just work", on the morning of August 19, the 500kV 3- section circuit line Quynh Luu - Thanh Hoa was energized and completed.

Accordingly, at 11:10 a.m. on August 19, the National Power Transmission Corporation (EVNNPT) and the Central Power Project Management Board (CPMB) coordinated with relevant units to energize the 500kV line project. The 3-arc circuit in the Quynh Luu - Thanh Hoa section meets the Prime Minister's direction.

The 500kV Quynh Luu - Thanh Hoa line project is invested by EVNNPT, CPMB manages and operates the project, and Power Transmission Company 1 takes over operation. The project has a length of 92km, passing through Nghe An and Thanh Hoa provinces. The project has 200 foundation locations, with 99 corridor intersections.

The project will be implemented from January 18, 2024 and agreed to be energized by the Investor-level Acceptance Council on the morning of August 19, 2024.

The project helps reduce load and avoid overload for existing 500kV lines, ensuring N-1 criteria. The line also helps improve transmission capacity at the North - Central interface, combined with the 500kV Line 3 circuit segments of Quang Trach - Quynh Luu, Thanh Hoa - Nam Dinh I, Nam Dinh I - Pho Noi to contribute Adding capacity from power sources in the North Central region to the load center in the Northern region.

According to EVNNPT Leaders, the implementation process of the 500kV Circuit 3 Line project always receives the attention and direction of the Prime Minister, ministries, branches, and leaders of Vietnam Electricity Group. Along with that is the support of authorities at all levels where the 500kV Circuit 3 Line project passes through; The consensus and joint efforts of the people gave up land for the project and participated in supporting the construction of the foundation excavation phase.

Rushing days on the 500kV 3-section circuit construction site in Thanh Hoa. Photo: Quach Du
Rushing days on the 500kV 3-section circuit construction site in Thanh Hoa. Photo: Quach Du

Also according to EVNNPT leaders, to meet the required progress as directed by the Prime Minister, in a short period of time many work items were implemented simultaneously such as construction, pole erection, wire pulling, and installation. Set the positioning frame and make technical adjustments. Therefore, in addition to the main force of EVNNPT's units and construction contractors, EVN has mobilized 5 Power Corporations to participate in construction support with a large number of highly qualified human resources. technique, experience, skills.

With the important nature of the 500kV Circuit 3 Line project, not only for EVNNPT, EVN's power corporations and other units have shown high spirit and responsibility when participating in full support. enthusiasm, effort, not afraid of difficulties and hardships.

The completion and energization of the 500kV circuit 3 line project in Quynh Luu - Thanh Hoa is a great motivation for the entire construction site of the 500kV circuit 3 line project to complete acceptance and inaugurate in the coming days under the direction of the Prime Minister. Government.

Trần Lâm
TIN LIÊN QUAN

Gấp rút hoàn thành đường dây 500kV mạch 3 qua Quảng Bình

CÔNG SÁNG |

Công đoạn cuối cùng kéo dây của đường dây 500kV mạch 3 qua Quảng Bình đang được đơn vị thi công thực hiện.

Bắt đối tượng chống người thi hành công vụ dự án 500kV

Trần Lâm |

Đối tượng Nguyễn Thị Tuyết ở Nghi Sơn, Thanh Hóa đã dùng xô chất bẩn hất vào cán bộ công an, cố tình cản trở người thi hành công vụ.

EVNCPC khen thưởng tập thể, cá nhân thi công đường dây 500kV

Tường Minh |

Tổng Công ty Điện lực miền Trung (EVNCPC) khen thưởng 47 tập thể và cá nhân xuất sắc tham gia thi công đường dây 500kV mạch 3.

Ra mắt Tủ sách điện tử Tổng Bí thư Nguyễn Phú Trọng

Vương Trần |

Tủ sách điện tử Tổng Bí thư Nguyễn Phú Trọng là cơ sở dữ liệu quý, phục vụ nghiên cứu, học tập và vận dụng trong sự nghiệp xây dựng và bảo vệ Tổ quốc.

Hezbollah kêu gọi ngừng bắn, nếu không sẽ giáng đòn "đau đớn"

Bùi Đức |

Hezbollah quyết giáng một đòn “đau đớn” lên Israel nếu chiến tranh vẫn tiếp tục ở Lebanon.

Du khách quốc tế bất ngờ với phố Halloween giữa lòng Thủ đô

HOÀNG LỘC - NGỌC LINH |

Hà Nội - Nhiều du khách quốc tế không khỏi bất ngờ, thích thú khi đến khu phố Hàng Mã (Hoàn Kiếm) hiện đang ngập tràn các mặt hàng Halloween.

Trang trại nuôi vịt xả thải gây ô nhiễm vẫn dây dưa tái phạm

An Long |

Long An - Dù đã bị nhắc nhở và xử phạt nhiều lần nhưng chủ trang trại vẫn liên tiếp tái đàn, xả thải gây ô nhiễm môi trường.

Nút giao 4 tầng sắp xây trên đại lộ Phạm Văn Đồng ở Thủ Đức

MINH QUÂN |

TPHCM - Nút giao Phạm Văn Đồng với Vành đai 2 tại TP Thủ Đức sẽ được thiết kế 4 tầng, bao gồm một hầm chui và ba cầu vượt.

Gấp rút hoàn thành đường dây 500kV mạch 3 qua Quảng Bình

CÔNG SÁNG |

Công đoạn cuối cùng kéo dây của đường dây 500kV mạch 3 qua Quảng Bình đang được đơn vị thi công thực hiện.

Bắt đối tượng chống người thi hành công vụ dự án 500kV

Trần Lâm |

Đối tượng Nguyễn Thị Tuyết ở Nghi Sơn, Thanh Hóa đã dùng xô chất bẩn hất vào cán bộ công an, cố tình cản trở người thi hành công vụ.

EVNCPC khen thưởng tập thể, cá nhân thi công đường dây 500kV

Tường Minh |

Tổng Công ty Điện lực miền Trung (EVNCPC) khen thưởng 47 tập thể và cá nhân xuất sắc tham gia thi công đường dây 500kV mạch 3.