On September 20, the Dong Nai City Land Fund Development Center - Long Thanh Branch just coordinated with the Long Thanh Ward People's Committee to publicly list the expected compensation and support plan of organizations, households, and individuals under the Long Thanh Airport Outside Area Drainage Project (phase 1).
Accordingly, the total recovered land area is 134 plots/239,054m2; there are a total of 35 cases, with a compensation and support value of more than 10.5 billion VND.
According to the Dong Nai City Land Fund Development Center, the Long Thanh airport outer area drainage project (phase 1) started the compensation and site clearance work in July 2026 and will be completed in December 2026.
The drainage project outside Long Thanh airport includes 2 component projects: The drainage project in the area outside Long Thanh airport (phase 1), invested by Area 5 Project Management Board, with a total investment of more than 836 billion VND, and the compensation, support, and resettlement project for investment and construction of drainage in the area outside Long Thanh airport (phase 1), invested by Dong Nai City Land Fund Development Center - Long Thanh Branch, with a total investment of more than 436 billion VND.
According to Dong Nai City People's Committee, the drainage project in the area outside Long Thanh airport is expected to start construction in October 2026. The total length of the Long Thanh airport drainage line (phase 1) is about 19km, including 2 drainage lines: Bung Mon stream about 12km long and Da Vang stream about 7km long. Regarding the scale of implementation, the project will construct dredging and reinforcing embankments, service roads, sidewalks, and green trees.
In which, Bung Mon stream is the main drainage route for regulating lakes No. 2 and No. 3; Da Vang stream is the drainage route for regulating lakes No. 4 and No. 5 of Long Thanh airport.