The Tra Khuc 3 bridge project has a total route length of 2.55km, of which the bridge is more than 708m long and the approach road is more than 1.8km long, with a total investment of 850 billion VND. The central budget is 525 billion VND, the rest is the provincial budget, the implementation period is from 2022 - 2025. The project is invested by the Quang Ngai Provincial Traffic Construction Investment Project Management Board. The construction progress of the Tra Khuc 3 bridge project has reached about 87% so far.
Although the project is in the finishing stage, there is still a problem with Mr. Huynh Ngoc Khanh's household, residing in Tinh Ha commune, Son Tinh district - representing the heirs of Mrs. Nguyen Thi Lien's household (deceased), who has not yet handed over the site with an area of over 1,000m², located within the construction area of the road leading to Tra Khuc 3 bridge. The reason Mr. Huynh Ngoc Khanh's household has not handed over the site is because of errors in the process of compensation and site clearance. Accordingly, the People's Committee of Son Tinh district decided to compensate, support and resettle Mr. Huynh Ngoc Khanh with a total compensation and support value of over 1.6 billion VND and was allocated 3 resettlement plots with a total area of 550m². After many times of inviting and mobilizing, by April 3, 2024, Mr. Huynh Ngoc Khanh had received compensation, support and resettlement of over 1.6 billion VND.
However, after reviewing, the People's Committee of Son Tinh district found that the re-determination of the residential land area for the above land plot did not comply with the provisions of law. Therefore, Mr. Huynh Ngoc Khanh was required to return the amount of over 1.6 billion VND received to the District Land Fund Development and Investment Project Management Board to return to the Investor. To carry out the return, the District Land Fund Development and Investment Project Management Board issued 2 notices, requesting Mr. Huynh Ngoc Khanh to return the amount of over 1.6 billion VND. However, both times Mr. Huynh Ngoc Khanh did not come to return the amount received, so the preparation of the adjusted compensation plan encountered obstacles...
Currently, the District People's Committee has assigned the District Inspectorate to establish an Inspection Team to inspect and conclude on the rights and wrongs of the previous re-determination of residential land area to adjust the compensation and resettlement support plan for Ms. Nguyen Thi Lien's household.
Speaking to reporters, a representative of the Management Board of Investment, Construction and Land Fund Development of Son Tinh district said that they will make efforts to persuade Mr. Huynh Ngoc Khanh to hand over the land and hand over 100% of the clean site to the investor in December 2024.