Landslide prevention project in Ho Chi Minh City is slow to construct

MINH QUÂN |

Ho Chi Minh City is implementing a series of large-scale landslide prevention projects, but the construction progress is slow, causing many areas along rivers and canals to continue to be threatened.

Slow deployment

Ho Chi Minh City has 43 landslide locations on riverbanks, canals, and ditches, of which 8 points are particularly dangerous. Although many embankment projects have been approved, the construction progress is slow, causing riverside residents to worry. In Binh Trung ward, two particularly dangerous landslide points appeared on the right and left banks of Giong Ong To canal (near Giong Ong To 1 bridge), with a radius of about 150m each side. This area is located in a densely populated residential area, directly affecting 19 households.

Real-world records show that many houses along the canal are in a state of leaning, with the risk of collapsing into the water. Mr. Do Binh Son, a resident living here, informed that the landslide situation is increasingly serious, while the embankment construction project has been mentioned for a long time but has not been implemented.

A similar situation is happening in the Thanh Da peninsula area (Binh Quoi ward), where more than 10km of riverbank is eroded, affecting many households. The Thanh Da peninsula landslide prevention project was assigned by the Ho Chi Minh City People's Committee to the Department of Transport (now the Department of Construction) to study and propose construction from 2003, which is one of the key projects to prevent landslides on the Saigon River.

By 2006, the Ho Chi Minh City People's Committee approved the investment policy, dividing it into 4 main sections. However, so far, only the landslide prevention project of section 1 of Thanh Da canal has been completed. Sections 2, 3, 4 with many large bidding packages are still under construction, increasing the risk of landslides.

According to Mr. Nguyen Kien Giang - Deputy Head of the Department of Management, Maintenance and Exploitation of Transport Works (Ho Chi Minh City Department of Construction), in the Thanh Da peninsula area, there are currently 3 landslide prevention projects invested by the Project Management Board for Investment and Construction of Transport Works. Among them, the landslide prevention project section 2 (Saigon Domaine Hotel area) has a length of 2.7km, with a total capital of more than 319 billion VND. Up to now, 1.46km has been completed. The underwater part package has reached 95% of the volume, expected to be completed in September 2026; the elevated part has reached 70%, expected to be completed in August 2026.

Project section 3 (Binh Quoi - Cay Bang - Rach Chua) is 4km long, with a total capital of more than 467 billion VND, 3.9km has been completed and is expected to be fully completed on April 30, 2026. Meanwhile, project section 4 (from Ly Hoang villa area to La San Mai Thon church) is 2.7km long, with a total capital of more than 380 billion VND, only 1.24km has been completed. The remaining packages are expected to be completed in the period from June to September 2026.

Need strong enough sanctions

Among the 43 landslide points, 11 locations in Nha Be, Tan Nhat, Thuong Tan, Lai Thieu, Tan Uyen do not have embankment projects. Ho Chi Minh City People's Committee requests urgent surveys and investment proposals. For embankment construction projects with a total length of nearly 18km, total investment of about 3,951 billion VND, Ho Chi Minh City People's Committee requests departments, branches and localities to urgently remove obstacles, accelerate the progress of preparing, appraising and implementing projects in order to soon put them into use.

Dr. Tran Quang Thang - Director of the Institute of Economics and Management of Ho Chi Minh City - assessed that the situation of slow and prolonged landslide prevention projects mainly stems from familiar "bottlenecks" that have not been completely resolved. Among them, the biggest obstacle is site clearance in riverside residential areas, where land laws are complicated, leading to many projects having to be constructed halfway or temporarily suspended.

In addition, the public investment process still has many levels, the allocation of capital is not timely, along with material price fluctuations, making it difficult for contractors to maintain stable progress.

To speed up progress, Mr. Thang said that Ho Chi Minh City needs to prioritize definitively handling the site before deployment, avoiding the situation of "doing while waiting". At the same time, a special mechanism should be applied to urgent projects related to people's safety, streamlining investment procedures and stronger decentralization to localities. In parallel, it is necessary to strengthen supervision, attach specific responsibilities of investors and contractors to project progress. If there are no strong enough sanctions, delays will continue to recur, directly affecting the safety and lives of people.

Một phần căn nhà bị sạt lở xuống rạch Giồng Ông Tố (phường Bình Trưng, TPHCM). Ảnh: Minh Quân
Part of the house was landslide down to Giong Ong To canal (Binh Trung ward, Ho Chi Minh City). Photo: Minh Quan
MINH QUÂN
RELATED NEWS

Anti-landslide project waiting for capital, land clearance is stuck

|

From the banks of the Co Chien River to the East Sea in Duyen Hai (Tra Vinh), landslides are becoming increasingly serious, washing away production land, threatening houses and people's lives. Meanwhile, many projects with embankments worth hundreds of billions of VND are still struggling due to slow site clearance, lack of capital...

Ben Tre people feel more secure after anti-landslide projects

|

Ben Tre - Anti-landslide projects in Ben Tre have been completed and put into use, contributing to helping people feel secure in living and producing.

Forecast of the time to welcome a new cold air mass causing thunderstorms in the North

|

According to the meteorological agency, it is forecast that due to the influence of cold air, from around the evening of April 28, the Northern region is likely to change to rain, with locally heavy rain.

Delegation of outstanding and typical grassroots trade union chairmen reports to Uncle Ho

|

Hanoi - In the afternoon of April 27, the delegation of outstanding and typical grassroots trade union presidents held a ceremony to report achievements to Uncle Ho at the Mausoleum of President Ho Chi Minh.

Quang Ngai - Hoai Nhon expressway operates from April 29, tolls not yet collected

|

The 88km long Quang Ngai - Hoai Nhon expressway will be opened to traffic from 11:30 am on April 29, 2026, but tolls are not yet collected.

Scene of discovering the wreckage of a war tank rising to Quy Nhon beach

|

Gia Lai - It is expected that on April 29, the Provincial Military Command will salvage the wreckage of a tank that surfaced at Quy Nhon beach. The discovered scene is being cordoned off for protection.

Anti-landslide project waiting for capital, land clearance is stuck

HOÀNG LỘC |

From the banks of the Co Chien River to the East Sea in Duyen Hai (Tra Vinh), landslides are becoming increasingly serious, washing away production land, threatening houses and people's lives. Meanwhile, many projects with embankments worth hundreds of billions of VND are still struggling due to slow site clearance, lack of capital...

Ben Tre people feel more secure after anti-landslide projects

Thành Nhân |

Ben Tre - Anti-landslide projects in Ben Tre have been completed and put into use, contributing to helping people feel secure in living and producing.

Chậm triển khai dự án chống sạt lở 60 tỉ ở vùng rốn lũ

TRẦN TUẤN |

Hà Tĩnh - Hiện Dự án khắc phục sạt lở bờ sông Ngàn Sâu đoạn qua xã Hà Linh (Hương Khê) vẫn chưa triển khai thi công, nguy cơ không kịp giải ngân trong năm 2024.