The 2,000 billion VND road project in Lang Son is behind schedule due to land clearance

Khánh Linh |

Lang Son - The project to upgrade section Km18-Km80, National Highway 4B had to request an extension due to difficulties in site clearance.

Land issues have to ask for extension of progress

The project to upgrade section Km18-Km80, National Highway 4B was approved by the Ministry of Transport in Decision No. 516, dated April 28, 2023. The project has a total length of 62.56km, passing through Loc Binh and Dinh Lap districts.

The project's starting point is at Km18+00 - the existing National Highway 4B route (connecting with the National Highway 4B renovation and upgrade project, section Km3+700 - Km18+00 under construction), the end point is at Km80+00 - the existing National Highway 4B route (border of Lang Son and Quang Ninh provinces) in Dinh Lap district.

The land use scale of the whole project is 198.8 hectares. Of which, in Loc Binh district 76.13 hectares, Dinh Lap district 122.67 hectares.

On November 18, informing reporters, a representative of the Steering Committee for compensation and site clearance for key projects in Lang Son province said that up to now, Loc Binh district has counted, measured, and counted 975 households and individuals/71.86 hectares.

a
The Project to Upgrade Section Km18-Km80, National Highway 4B is facing many difficulties. Photo: Khanh Linh

At the same time, the provisional plan was approved for 506 households, funds were paid to 486 households, compensation and support funds were advanced to 7 households. The result was the handover of 66.2 hectares of land (92.12%).

In Dinh Lap district, the project has measured and counted 1,032 cases/50.7 hectares, reaching 98.7%. Approved and paid for 19 compensation and provisional support plans for 500 cases with the amount of 34.8 billion VND.

Currently, the project is calculating and making a provisional plan to advance money from the investment project to make advance payments to affected households and individuals with a total amount of 9.99 billion VND.

The result of handing over the site is 49.2ha (95%) equivalent to the route length of 38/41.3km (92%).

Regarding the project progress, the leader of the Project Management Board for Upgrading Section Km18-Km80, National Highway 4B said that with the current difficulties, the project is unlikely to be completed in 2024. Therefore, the Department of Transport of Lang Son province has proposed to extend the project completion date to 2025.

Efforts to overcome difficulties in handing over clean land for the project

Talking about the difficulties and obstacles in site clearance work, the Steering Committee for compensation and site clearance for key projects in Lang Son province said that the project in Na Duong town and Loi Bac commune, Loc Binh district had previously carried out site clearance work to implement the project to renovate and upgrade National Highway 4B and the project to expand Na Cay Lake (from 2002-2006).

Due to the lack of measurement records, the project investor has not yet transferred data information to the Department of Natural Resources and Environment of Loc Binh district, so the determination of boundaries, previously recovered land area and the recovered land area for the new project are easily overlapped, causing difficulties in the process of making compensation and support plans.

a
The National Highway 4B upgrade project is one of the key projects of Lang Son province. Photo: Khanh Linh

In addition, land records have changed and have not been adjusted in a timely manner. Some land plots have differences in boundaries and areas between reality and the Land Use Rights Certificate. It is necessary to check and verify the land use process and determine the land user.

Some households illegally build houses, buildings, and structures on agricultural land, are not eligible for compensation, and moving infrastructure systems such as power lines and telecommunications cables also faces many difficulties.

Previously, on November 12, Vice Chairman of the Provincial People's Committee Luong Trong Quynh chaired a thematic meeting to consider and resolve difficulties and problems in site clearance for the project to upgrade section Km18-Km80, National Highway 4B.

The provincial leaders requested the districts to urgently remove obstacles and complete the handover of 100% of the site to the investor before November 20, 2024.

Khánh Linh
TIN LIÊN QUAN

Lang Son clears land for 2 key highways

|

Lang Son - 2 key expressways are urgently clearing land to reach the finish line.

Why is the largest industrial park in Lang Son still slow in clearing land

|

VSIP Lang Son Industrial Park (IP) is still behind schedule in site clearance.

Lang Son declares natural disaster emergency at 2 irrigation lakes

|

Lang Son - The Provincial People's Committee has just decided to declare a natural disaster emergency to repair two irrigation lakes in Van Lang district.

New deal could see Nord Stream 2 slip out of Russia's hands

|

American businessman is looking to buy the Swiss company that controls Russia's Nord Stream 2 pipeline.

Forecast of new storms and low pressure around the East Sea

|

The latest storm and low pressure forecast says that new low pressure in and near the East Sea is likely to appear continuously in the coming days.

Tiny house in alley in Hanoi costs 2 billion VND

|

Many houses in alleys in Hanoi without red books, with an area of ​​less than 20 square meters, are being sold for about 2 billion VND.

Fierce fire at rice husk warehouse in Dong Thap, expected to last all night

|

Dong Thap - The rice husk warehouse is burning fiercely and over a large area. Local authorities mobilized firefighting forces throughout the night to control the spread of the fire.

Dak Lak today has transformed and grown strongly

|

Dak Lak - In the period of 2021 - 2023, the province's economic growth will average 7%/year, and the economic scale will increasingly expand.

Lang Son clears land for 2 key highways

Khánh Linh |

Lang Son - 2 key expressways are urgently clearing land to reach the finish line.

Why is the largest industrial park in Lang Son still slow in clearing land

Khánh Linh |

VSIP Lang Son Industrial Park (IP) is still behind schedule in site clearance.

Lang Son declares natural disaster emergency at 2 irrigation lakes

Khánh Linh |

Lang Son - The Provincial People's Committee has just decided to declare a natural disaster emergency to repair two irrigation lakes in Van Lang district.