The road project connecting Dong Nai with the expressway to Ho Chi Minh City is stuck in land clearance

HÀ ANH CHIẾN |

Dong Nai - The Huong Lo 2 - Section 1 project, nearly 2km long, to connect the Ho Chi Minh City - Long Thanh - Dau Giay expressway, is stuck with 250m of site clearance.

On March 26, the Dong Nai Province Traffic Construction Investment Project Management Board is proposing that the Bien Hoa City People's Committee completely resolve problems related to compensation and site clearance for households and sections through Long Hung commune to continue the construction of the Huong Lo 2 - 1 road investment project (Bien Hoa city).

The Huong Lo 2 - Section 1 project has a route length of nearly 2km, the starting point of the route intersects with National Highway 51 and the end point of the existing asphalt concrete road intersection (An Hoa - Long Hung), with a total investment of nearly 783 billion VND from the provincial budget.

Hang muc cau An Hoa 2, moi thi cong duoc 1 mo va 2 tru, vuong 250m dai mat bang chua giai phong. Anh tu lieu: HAC
The An Hoa 2 bridge project, which has only completed 1 abutment and 2 pillars, is stuck with 250m of unreserved land. Documentary photo: HAC

The project implementation progress by the end of 2024 has completed the road with a total length of more than 1.3 km. However, for the An Hoa 2 bridge item, which is stuck with 250m of site clearance through Long Hung commune, Bien Hoa city, the site has not been handed over.

There are 42 households in Long Hung commune that have approved compensation plans but have not yet paid compensation due to encroachment on the boundaries of the two projects of Long Hung open urban economic zone and Huong Lo 2 road.

Currently, the contractor has to temporarily suspend construction.

Du an cau Vam Cat Sut nam tren tuyen Huong lo 2 da co ban hoan thanh nhung phia duong ket noi ra cao toc TPHCM - Long Thanh - Dau Giay van co moc um tum. Anh tu lieu: HAC
The Vam Cat Sut bridge project on Huong Lo 2 route has been basically completed, but the road connecting to the Ho Chi Minh City - Long Thanh - Dau Giay expressway is still overgrown with grass. Documentary photo: HAC

Huong Lo 2 route is planned to be a new traffic axis connecting Bien Hoa City with Ho Chi Minh City, shortening the distance and travel time; at the same time, contributing to reducing traffic volume on National Highway 51.

Huong Lo 2 - section 1, from National Highway 51 to the intersection with the existing asphalt road (An Hoa - Long Hung road, Long Hung commune, Bien Hoa city) is under construction investment. However, with section 2 of Huong Lo 2, connecting from the border of Long Hung commune to the Ho Chi Minh City - Long Thanh - Dau Giay expressway, not yet constructed, the Dong Nai Province Traffic Construction Investment Project Management Board is taking steps to propose an investment policy.

At the same time, Vam Cai Sut bridge (total length of the entire route is about 649m) on Huong Lo 2 has completed construction.

HÀ ANH CHIẾN
TIN LIÊN QUAN

Opening a 2km long road through 2 districts of Dong Nai connecting to the airport

|

Dong Nai - The project to build a 25C road of more than 2km long from National Highway 51 to Huong Lo 19 through Long Thanh and Nhon Trach districts connects Long Thanh airport.

Handing over 100% of the project site of the belt connecting Ho Chi Minh City - Dong Nai

|

For the Ho Chi Minh City Ring Road 3 project, the section passing through Dong Nai province, Nhon Trach district has so far handed over 65 hectares, reaching 100% of the project area.

Revealing the shape of the 17,800 billion VND expressway through Dong Nai

|

After more than 1 year of construction, the Bien Hoa - Vung Tau expressway with a total investment of 17,800 billion VND (section through Dong Nai province) has taken on an increasingly clear shape.

Close-up of the proposed street named Hang Long

|

Hanoi - The name of Hang Long ancient town is proposed to be restored, giving the name to the road from Tran Binh Trong intersection to Yet Kieu intersection.

Noi Bai - Lao Cai Expressway is expected to be expanded to 4 lanes in September 2025

|

Lao Cai - The Standing Committee of the Provincial Party Committee and the Vietnam Expressway Corporation (VEC) agreed to soon upgrade the Yen Bai - Lao Cai Expressway to 4 lanes.

Hundreds of dead pigs discovered floating on canals in Thanh Hoa

|

Thanh Hoa - Since the beginning of July, nearly 100 dead pigs have been thrown floating on the North Canal and related canals, causing serious environmental pollution.

The situation of arranging cadres in the old Binh Duong to work in Ho Chi Minh City after the merger

|

HCMC - Eight departments have transferred cadres and civil servants from Binh Duong to HCMC for work, while seven departments still have a department in the Binh Duong area.

Opening a 2km long road through 2 districts of Dong Nai connecting to the airport

HÀ ANH CHIẾN |

Dong Nai - The project to build a 25C road of more than 2km long from National Highway 51 to Huong Lo 19 through Long Thanh and Nhon Trach districts connects Long Thanh airport.

Handing over 100% of the project site of the belt connecting Ho Chi Minh City - Dong Nai

HÀ ANH CHIẾN |

For the Ho Chi Minh City Ring Road 3 project, the section passing through Dong Nai province, Nhon Trach district has so far handed over 65 hectares, reaching 100% of the project area.

Revealing the shape of the 17,800 billion VND expressway through Dong Nai

HÀ ANH CHIẾN - NHƯ QUỲNH |

After more than 1 year of construction, the Bien Hoa - Vung Tau expressway with a total investment of 17,800 billion VND (section through Dong Nai province) has taken on an increasingly clear shape.