Handing over 100% of the project site of the belt connecting Ho Chi Minh City - Dong Nai

HÀ ANH CHIẾN |

For the Ho Chi Minh City Ring Road 3 project, the section passing through Dong Nai province, Nhon Trach district has so far handed over 65 hectares, reaching 100% of the project area.

On January 19, information from the Dong Nai Province Traffic Construction Investment Project Management Board said that the Ho Chi Minh City Ring Road 3 project (section through Dong Nai province) has so far been handed over to Nhon Trach district with an entire area of ​​about 65 hectares, reaching 100% of the project area.

The area of ​​land that can be constructed is about 64 hectares, reaching about 99% of the total area.

About 1 hectare has not been constructed because some households have received compensation but have not yet relocated their assets on the land.

According to the Dong Nai Province Traffic Construction Investment Project Management Board, contractors are currently implementing 21 construction projects along the entire route with a total of about 200 motorbikes and equipment, 70 engineers and more than 300 workers.

Up to now, the total value of the implementation of 3 construction packages of the project has reached more than 370 billion VND out of the total contract value of more than 1,800 billion VND, reaching 20% ​​of the contract value.

Of which, with package number 26, construction of the section from the beginning of the route to the intersection with provincial road 25C, the implemented output reached 70 billion VND out of the total contract value of nearly 467 billion VND, reaching about 15% of the contract value.

With package No. 29, constructing the section from the intersection of provincial road 25C to the intersection of provincial road 25B, the output reached 180 billion VND out of the total contract value of more than 681 billion VND, reaching about 26% of the contract value.

Package No. 32, construction of the section from the intersection with Provincial Road 25B to the end of the route, the implemented output reached 120 billion VND out of the total contract value of nearly 705 billion VND, reaching about 17% of the contract value.

HÀ ANH CHIẾN
TIN LIÊN QUAN

Ho Chi Minh City's Ring Road 3 sprints to the finish line

|

After more than 18 months of delays due to a lack of sand supply for filling, the Beltway 3 project through Ho Chi Minh City is entering the accelerated construction phase. Some sections will be technically opened to traffic in 2025, the entire route is expected to be completed in 2026.

More than 1,300 billion VND to build a 4.4km long belt road in Dong Nai

|

Dong Nai - On December 21, Long Khanh City People's Committee started construction of Ring Road 1 - Long Khanh City, with a total investment of more than 1,300 billion VND.

Image of the large bridge on Ring Road 4 in the Capital region under construction

|

The 27-span railway overpass (part of package 8 - construction of the parallel road to Ring Road 4) has taken shape and is expected to be completed in April 2025.

Inspection conclusion on AIC related bidding package in Hue

|

The Inspectorate of the Ministry of Education and Training has just concluded the investment project to purchase equipment for the University of Education, Hue University, including the bid package in which AIC participated.

Russia vows to retaliate against UK and Ukraine

|

Russia is ready to respond if Britain and Ukraine strengthen maritime security in the Sea of ​​Azov after signing a 100-year cooperation agreement.

Without Xuan Son, Nam Dinh fails to win for the second consecutive match in V.League

|

Nam Dinh Club lost 0-1 to The Cong Viettel in round 10 of V.League 2024-2025.

Regulations on extra teaching and learning in 2025

|

The Ministry of Education and Training issued Circular No. 29/2024/TT-BGDDT regulating extra teaching and learning, effective from February 14, 2025.

Appointing 5 Deputy Police Directors in 4 provinces and cities

|

Last week, in addition to appointing 2 Deputy Directors of Hanoi Police; Thai Binh, Thanh Hoa, and Ha Nam Provincial Police also recorded the appointment of 3 Deputy Directors.

Ho Chi Minh City's Ring Road 3 sprints to the finish line

MINH QUÂN |

After more than 18 months of delays due to a lack of sand supply for filling, the Beltway 3 project through Ho Chi Minh City is entering the accelerated construction phase. Some sections will be technically opened to traffic in 2025, the entire route is expected to be completed in 2026.

More than 1,300 billion VND to build a 4.4km long belt road in Dong Nai

HÀ ANH CHIẾN |

Dong Nai - On December 21, Long Khanh City People's Committee started construction of Ring Road 1 - Long Khanh City, with a total investment of more than 1,300 billion VND.

Image of the large bridge on Ring Road 4 in the Capital region under construction

HỮU CHÁNH |

The 27-span railway overpass (part of package 8 - construction of the parallel road to Ring Road 4) has taken shape and is expected to be completed in April 2025.