Handing over 100% of the project site of the belt connecting Ho Chi Minh City - Dong Nai

HÀ ANH CHIẾN |

For the Ho Chi Minh City Ring Road 3 project, the section passing through Dong Nai province, Nhon Trach district has so far handed over 65 hectares, reaching 100% of the project area.

On January 19, information from the Dong Nai Province Traffic Construction Investment Project Management Board said that the Ho Chi Minh City Ring Road 3 project (section through Dong Nai province) has so far been handed over to Nhon Trach district with an entire area of ​​about 65 hectares, reaching 100% of the project area.

The area of ​​land that can be constructed is about 64 hectares, reaching about 99% of the total area.

About 1 hectare has not been constructed because some households have received compensation but have not yet relocated their assets on the land.

According to the Dong Nai Province Traffic Construction Investment Project Management Board, contractors are currently implementing 21 construction projects along the entire route with a total of about 200 motorbikes and equipment, 70 engineers and more than 300 workers.

Up to now, the total value of the implementation of 3 construction packages of the project has reached more than 370 billion VND out of the total contract value of more than 1,800 billion VND, reaching 20% ​​of the contract value.

Of which, with package number 26, construction of the section from the beginning of the route to the intersection with provincial road 25C, the implemented output reached 70 billion VND out of the total contract value of nearly 467 billion VND, reaching about 15% of the contract value.

With package No. 29, constructing the section from the intersection of provincial road 25C to the intersection of provincial road 25B, the output reached 180 billion VND out of the total contract value of more than 681 billion VND, reaching about 26% of the contract value.

Package No. 32, construction of the section from the intersection with Provincial Road 25B to the end of the route, the implemented output reached 120 billion VND out of the total contract value of nearly 705 billion VND, reaching about 17% of the contract value.

HÀ ANH CHIẾN
RELATED NEWS

Ho Chi Minh City's Ring Road 3 sprints to the finish line

|

After more than 18 months of delays due to a lack of sand supply for filling, the Beltway 3 project through Ho Chi Minh City is entering the accelerated construction phase. Some sections will be technically opened to traffic in 2025, the entire route is expected to be completed in 2026.

More than 1,300 billion VND to build a 4.4km long belt road in Dong Nai

|

Dong Nai - On December 21, Long Khanh City People's Committee started construction of Ring Road 1 - Long Khanh City, with a total investment of more than 1,300 billion VND.

Image of the large bridge on Ring Road 4 in the Capital region under construction

|

The 27-span railway overpass (part of package 8 - construction of the parallel road to Ring Road 4) has taken shape and is expected to be completed in April 2025.

The situation of jostling and running red lights has significantly decreased, clearly affected by AI cameras

|

Hanoi - After two days of more than 1,800 AI cameras in Hanoi being put into operation, at many intersections, traffic participants stopped to wait for red lights right in front of the line.

Thailand - Cambodia tensions escalate

|

On December 14, Thailand continued to update casualties in clashes at the border with Cambodia, including both civilians and soldiers.

Controlling the fire at a wood company in Ho Chi Minh City

|

HCMC - In Tan Hiep ward, a fire broke out at a wood company, police had to mobilize many specialized fire trucks and dozens of soldiers to put out the fire.

Why is there still a landslide disaster on National Highway 6 despite heavy rain

|

Phu Tho - A serious landslide on National Highway 6 left 3 people dead and 2 injured. Experts warn of potential risks from the Northwest geology.

SEA Games 33 Medal Schedule on December 15

|

Updated total medal table of the 33rd SEA Games on December 15.

Ho Chi Minh City's Ring Road 3 sprints to the finish line

MINH QUÂN |

After more than 18 months of delays due to a lack of sand supply for filling, the Beltway 3 project through Ho Chi Minh City is entering the accelerated construction phase. Some sections will be technically opened to traffic in 2025, the entire route is expected to be completed in 2026.

More than 1,300 billion VND to build a 4.4km long belt road in Dong Nai

HÀ ANH CHIẾN |

Dong Nai - On December 21, Long Khanh City People's Committee started construction of Ring Road 1 - Long Khanh City, with a total investment of more than 1,300 billion VND.

Image of the large bridge on Ring Road 4 in the Capital region under construction

HỮU CHÁNH |

The 27-span railway overpass (part of package 8 - construction of the parallel road to Ring Road 4) has taken shape and is expected to be completed in April 2025.