Handing over 100% of the project site of the belt connecting Ho Chi Minh City - Dong Nai

HÀ ANH CHIẾN |

For the Ho Chi Minh City Ring Road 3 project, the section passing through Dong Nai province, Nhon Trach district has so far handed over 65 hectares, reaching 100% of the project area.

On January 19, information from the Dong Nai Province Traffic Construction Investment Project Management Board said that the Ho Chi Minh City Ring Road 3 project (section through Dong Nai province) has so far been handed over to Nhon Trach district with an entire area of ​​about 65 hectares, reaching 100% of the project area.

The area of ​​land that can be constructed is about 64 hectares, reaching about 99% of the total area.

About 1 hectare has not been constructed because some households have received compensation but have not yet relocated their assets on the land.

According to the Dong Nai Province Traffic Construction Investment Project Management Board, contractors are currently implementing 21 construction projects along the entire route with a total of about 200 motorbikes and equipment, 70 engineers and more than 300 workers.

Up to now, the total value of the implementation of 3 construction packages of the project has reached more than 370 billion VND out of the total contract value of more than 1,800 billion VND, reaching 20% ​​of the contract value.

Of which, with package number 26, construction of the section from the beginning of the route to the intersection with provincial road 25C, the implemented output reached 70 billion VND out of the total contract value of nearly 467 billion VND, reaching about 15% of the contract value.

With package No. 29, constructing the section from the intersection of provincial road 25C to the intersection of provincial road 25B, the output reached 180 billion VND out of the total contract value of more than 681 billion VND, reaching about 26% of the contract value.

Package No. 32, construction of the section from the intersection with Provincial Road 25B to the end of the route, the implemented output reached 120 billion VND out of the total contract value of nearly 705 billion VND, reaching about 17% of the contract value.

HÀ ANH CHIẾN
RELATED NEWS

Ho Chi Minh City's Ring Road 3 sprints to the finish line

|

After more than 18 months of delays due to a lack of sand supply for filling, the Beltway 3 project through Ho Chi Minh City is entering the accelerated construction phase. Some sections will be technically opened to traffic in 2025, the entire route is expected to be completed in 2026.

More than 1,300 billion VND to build a 4.4km long belt road in Dong Nai

|

Dong Nai - On December 21, Long Khanh City People's Committee started construction of Ring Road 1 - Long Khanh City, with a total investment of more than 1,300 billion VND.

Image of the large bridge on Ring Road 4 in the Capital region under construction

|

The 27-span railway overpass (part of package 8 - construction of the parallel road to Ring Road 4) has taken shape and is expected to be completed in April 2025.

Cold air is about to cause thunderstorms, the North has places below 19 degrees Celsius

|

Forecast of the first cold air wave of the season with weak intensity, the North turns cool at night and in the morning, the Northern mountainous region has places with the lowest temperature below 19 degrees Celsius.

Businesses mobilize bonds with interest rates up to 13%, behind the trillion-VND capital flow

|

The interest rate of corporate bonds in some lots is 13%/year, while the purpose of capital mobilization ranges from project investment to debt restructuring.

Turning on AI music at coffee shops, on passenger cars, why can copyright fees still be charged

|

When AI music appears in cafes, restaurants, and buses, a question arises: Is it necessary to pay copyright fees if you don't turn on the recording of the real singer?

Infrastructure upgrade project messy in the center of Da Nang city

|

Da Nang - The tens of billions of VND infrastructure project in the city center is under construction in a mess, unfinished, disrupting daily life and lurking at the risk of accidents for people.

Ho Chi Minh City's Ring Road 3 sprints to the finish line

MINH QUÂN |

After more than 18 months of delays due to a lack of sand supply for filling, the Beltway 3 project through Ho Chi Minh City is entering the accelerated construction phase. Some sections will be technically opened to traffic in 2025, the entire route is expected to be completed in 2026.

More than 1,300 billion VND to build a 4.4km long belt road in Dong Nai

HÀ ANH CHIẾN |

Dong Nai - On December 21, Long Khanh City People's Committee started construction of Ring Road 1 - Long Khanh City, with a total investment of more than 1,300 billion VND.

Image of the large bridge on Ring Road 4 in the Capital region under construction

HỮU CHÁNH |

The 27-span railway overpass (part of package 8 - construction of the parallel road to Ring Road 4) has taken shape and is expected to be completed in April 2025.