Coastal road project construction is slow, Quang Tri will replace weak contractors

HƯNG THƠ |

Quang Tri - Coastal road project is behind schedule, the investor will propose replacing the contractor to construct sparingly.

Lack of manpower at construction site

The Coastal Road Project connecting the East-West Economic Corridor of Quang Tri province phase 1 is expected to create a new driving force for the coastal area, connecting economic and tourism centers with the East-West trade corridor. However, after a long period of implementation, the project progress is still slow, in which the prominent reason is that many contractors have not mobilized sufficient manpower, vehicles, and equipment as committed.

The project has a total adjusted investment of more than 2,731 billion VND, with a length of about 48km. The project started in April 2022, and the implementation time has been extended to 2027. To date, localities have handed over about 90% of the site, and nearly 4.5km is mainly located in residential areas. However, the construction value of the entire project has only reached nearly 46%.

Đoạn kết nối với bến xe ở phường Nam Đông Hà thi công dang dở và không có dấu hiệu thi công, chỉ xuất hiện chiếc máy múc làm việc cầm chừng ở giữa đoạn. Ảnh: Hưng Thơ
The section connecting to the bus station in Nam Dong Ha ward is under construction and there are no signs of construction, only an excavator working halfway in the middle of the section appears. Photo: Hung Tho

Records at the construction site in mid-May 2026 show that many sections of the route are deserted of workers and construction machinery. At the end of the route in Nam Dong Ha ward, according to the plan, the contractor must carry out crushed stone reinforcement and loading waiting for subsidence, but in reality, the roadbed embankment has not been completed.

In the section about 5km long through Trieu Binh commune constructed by Taco Truong Son Joint Stock Company, the achieved volume is very low. This is the most difficult area in the soil embankment item, but the implementation progress is slow in the context that the rainy and storm season is only a few months away.

Hiện trạng ngổn ngang tại đoạn đường do Công ty Cổ phần Taco Trường Sơn thực hiện. Ảnh: Hưng Thơ
Current state of chaos at the road section implemented by Taco Truong Son Joint Stock Company. Photo: Hung Tho

The above reality is contrary to the commitment in the working minutes dated April 28, 2026 between the Project Management Board and the construction units. Accordingly, the contractors committed to focusing maximum manpower and equipment to accelerate before May 10, 2026. But after this milestone, in many locations, only small construction teams still appear.

Một hạng mục cầu không có công nhân thi công. Ảnh: Nguyễn Luân
A bridge item without construction workers. Photo: Nguyen Luan

Some contractors raised difficulties regarding high fuel and material prices, scarcity of embankment soil and filling sand. However, when most of the site has been handed over and capital has been allocated, the slow construction raises questions about contractor responsibility.

Will handle slow contractors

To overcome the above situation, the Quang Tri Provincial Construction Investment Project Management Board has requested contractors to sign commitments to mobilize human and material resources to simultaneously construct from May 10. However, so far the construction site has not had clear changes.

Mr. Vo Phong Luan - Deputy Director of the Quang Tri Provincial Construction Investment Project Management Board - said that in case by May 15, 2026, any unit still does not meet the requirements, the Project Management Board will base on the contract to handle it, and at the same time report to the Provincial People's Committee to consider terminating the contract and replacing the contractor to ensure project progress.

Công nhân, máy móc triển khai thi công khu tái định cư. Ảnh: Nguyễn Luân
Workers and machinery deploy construction of the resettlement area. Photo: Nguyen Luan

Besides the subjective reasons from the contractor, the investor admitted that site clearance work is still "sloppy", some sections have been handed over but access roads are narrow, causing difficulties for transporting materials and equipment. The situation of land and sand shortage and increased input prices are also real pressure.

However, with a project of more than 2,700 billion VND, about 90% of the site and capital are ready, prolonged delays will cause waste of time, increase the risk of delays, and even affect disbursement plans.

The issue at this time is not only to remove objective difficulties, but also to tighten responsibility, thoroughly handle construction contractors who are not decisive, and avoid allowing key projects to continue to be delayed.

HƯNG THƠ
RELATED NEWS

No workers at the coastal road construction site worth more than 2,700 billion VND

|

Quang Tri - The Coastal Road project connecting the East-West Economic Corridor has handed over 90% of the site, but the construction site is deserted, causing investors to worry about slow progress.

Hue requests clarification of responsibilities of many units for slow replacement forest planting

|

Hue has only planted 223/508.6ha of replacement forest, many units are behind schedule, and are required to review and clarify responsibilities.

Lao Dong Newspaper warns of capital increase for coastal road project before inspection conclusion

|

Quang Tri - Before the Government Inspectorate pointed out violations, Lao Dong Newspaper reported abnormalities in the proposal to adjust and increase capital in the coastal road project.

State encourages the development of new e-commerce business models

|

From July 1st, the Law on E-commerce takes effect, this Law stipulates that the State encourages the development of new types and models of e-commerce business.

Train driver charged after fatal bus accident

|

Thai police have charged the train driver for negligence after the accident in Bangkok.

Traffic cleared after many days of overcoming coastal road landslides in Ha Tinh

|

Ha Tinh - After basically handling all the soil and rocks that pose a risk of landslides, the coastal road has been cleared, and vehicles are allowed to pass.

Tornadoes knock down corrugated iron roofs, traffic at Tan Son Nhat airport gateway jammed

|

Ho Chi Minh City - Heavy rain accompanied by strong thunderstorms in Ho Chi Minh City has collapsed corrugated iron roofs, causing traffic congestion at the airport gateway area.

Draft Report of the Executive Committee of the Vietnam General Confederation of Labor (XIII term) at the XIV Congress of the Vietnam Trade Union, term 2026 - 2031

|

Building a comprehensively strong Vietnam Trade Union; focusing on representing, caring for, and protecting union members and workers; promoting the pioneering role, spirit of innovation and creativity, contributing to realizing the aspiration to build a rich, prosperous, civilized, and happy country.

No workers at the coastal road construction site worth more than 2,700 billion VND

HƯNG THƠ - NGUYỄN LUÂN |

Quang Tri - The Coastal Road project connecting the East-West Economic Corridor has handed over 90% of the site, but the construction site is deserted, causing investors to worry about slow progress.

Hue requests clarification of responsibilities of many units for slow replacement forest planting

PHÚC ĐẠT |

Hue has only planted 223/508.6ha of replacement forest, many units are behind schedule, and are required to review and clarify responsibilities.

Lao Dong Newspaper warns of capital increase for coastal road project before inspection conclusion

HƯNG THƠ |

Quang Tri - Before the Government Inspectorate pointed out violations, Lao Dong Newspaper reported abnormalities in the proposal to adjust and increase capital in the coastal road project.