The 3,500 billion VND traffic project has been under construction for nearly 3 years but is still stalled

Viên Nguyễn |

The Hoang Sa - Doc Soi road project has been under construction for nearly 3 years, however, many authorities in Quang Ngai province have not yet completed the determination of specific land prices. This is one of the reasons why the project is having problems with the site, leading to continuous delays in progress.

Low handover site, not seamless

The Hoang Sa - Doc Soi road project has a route length of 26.88km, starting at the intersection with Tri Binh - Dung Quat road, ending at Hoang Sa road. The planned construction area of the main route is 172.16 hectares. The project is invested by the Provincial Traffic Construction Investment Project Management Board. The total investment is 3,500 billion VND.

Of which, the central budget is 1,300 billion VND, the provincial budget is 2,200 billion VND (capital collected from land use fees). The project implementation period is from 2022 to 2027. This is a multi-purpose project, when completed, it will connect Dung Quat Economic Zone with the central area of Quang Ngai province, ensuring transportation needs from North to South...

Currently, a notice of land reclamation has been issued for 165.88/172.16 hectares; reaching 96.4%; the remaining 6.28 hectares have not been issued. Although it has been under construction for nearly 3 years, the People's Committees of Binh Son, Son Tinh districts and Quang Ngai city (old) have not yet completed the determination of specific land prices for the residential land area (now Binh Son, Van Tuong, Dong Son, Tho Phong communes) with a total area of 9.86 hectares.

About 5.36 hectares of agricultural land have not been specifically priced, including Binh Son commune at 1.25 hectares, Van Tuong commune at 0.26 hectares, Dong Son commune at 1.51 hectares, Tho Phong commune at 2.06 hectares; Tinh Khe commune at 0.16 hectares; Truong Quang Trong ward at 0.12 hectares.

Mr. Nguyen Binh - residing in Hanh Phuc village, Truong Quang Trong ward - said: "The State has reclaimed 750m2 of rice fields from my family to implement the Hoang Sa - Doc Soi road project. I have received compensation of 330 million VND. However, there has been no specific announcement about the compensation for housing and resettlement support for the price and resettlement location. Although construction has started for nearly 3 years, the site has only been handed over 60.05/172.16 hectares, reaching 34.9%.

Tien do thi cong du an duong Hoang Sa - Doc Soi cham tre do dien tich mat bang ban giao con thap, chua lien mach. Hien nay, nha thau chu yeu trien khai thi cong tai cac vi tri cau, cong ngang. Anh: Vien Nguyen
The construction progress of the Hoang Sa - Doc Soi road project is delayed due to the low handover area and not being seamless. Currently, contractors mainly implement construction at bridge and cross-culvert locations. Photo: Vien Nguyen

GPMB work has not had many changes

According to Mr. Do Vu Bao - Deputy Director of the Provincial Traffic Construction Investment Project Management Board, the progress of site clearance for the main route continues to be delayed. To date, only the compensation plan for 48.63/172.16ha has been approved; reaching 28.3%.

From July 1, 2025 to now, the Provincial Land Fund Development Center has only submitted 2 approvals for 4.54 hectares. Currently, 41.93 hectares have been assessed by the provincial Land Fund Development Center but the plan has not been submitted for appraisal and approval, although the investor has urged this unit to speed up the progress of site clearance in the official dispatch dated July 11, 2025, but there have not been many changes so far.

On the other hand, the coordination of the Provincial Land Fund Development Center's tasks with the People's Committees of communes and wards is not yet in order, and there is no consensus on the application of policy mechanisms, especially between the Provincial Land Fund Development Center and the People's Committee of Truong Quang Trong Ward.

The site handover rate has reached 34.9% but is not yet seamless, some locations do not have access roads, so currently the contractor can mainly only implement construction at 14/18 bridges (7/9 bridge locations), 23/156 cross-culverts, 0.926/25.37km of roadbed and construction of precast components, bridge girders, so the progress is not up to requirements.

According to Mr. Do Vu Bao, the project's capital plan for 2025 is nearly 965 billion VND, but the site clearance progress is slow, only 259 billion VND has been disbursed, reaching 26.8%. Of which, the cost of compensation for the new main route was 106 billion VND, reaching 45% of the plan.

To speed up the project implementation and disbursement of the capital plan for 2025, the investor recommends that the Provincial Land Fund Development Center (including the Land Fund Development Center, Binh Son branch) and the People's Committees of communes and wards: Binh Son, Van Tuong, Dong Son, Tho Phong, Tinh Khe and Truong Quang Trong focus on coordinating to speed up the implementation progress, completing all site clearance work for the remaining agricultural and non-agricultural land areas other than residential land (about 110.81ha) and land plots in the frontage of National Highway 24B and Hoang Sa road before April 2026 to ensure the project implementation time.

According to the investor's calculation, the weak land treatment time is 8 months, the roadbed construction time is 12 months, so if the site handover time frame is not guaranteed, the project will not be completed in 2027.

Viên Nguyễn
RELATED NEWS

3,500 billion VND traffic project in Quang Ngai struggles due to land clearance problems

|

Quang Ngai - Slow site clearance and not seamless handover areas have caused many difficulties in the construction progress of the Hoang Sa - Doc Soi road project.

3,000 workers work through the September 2 Ceremony for the progress of the Quang Ngai - Hoai Nhon Expressway project

|

Whether it is a normal day or a holiday or Tet holiday, for more than 2 years, thousands of workers, engineers... have been working tirelessly at the Quang Ngai - Hoai Nhon expressway construction site, determined to complete the project on schedule by the end of 2025.

Hanoi starts construction of nearly VND56,300 billion expressway, to be completed in 2028

|

Hanoi - Component project 3, construction of the 113km Ring Road 4 expressway in the Capital region, with a total investment of nearly VND 56,300 billion, is expected to be completed in 2028.

Forecast of the number of storms and tropical depressions expected to appear in September

|

According to the representative of the meteorological agency, it is forecasted that in September, there will be about 2-4 storms/tropical depressions in the East Sea and 1-2 of them will make landfall.

Close-up of the giant arm-shaped structure on Hai Tien beach devastated by the storm

|

Thanh Hoa - Affected by storm No. 5, hundreds of meters of the embankment in Hai Tien sea have sunk and cracked, in addition, the giant arm project has also had its base overturned and tilted.

Prime Minister directs inspection to determine the situation of manipulation of the gold and stock markets

|

The Prime Minister requested an accurate assessment of developments in the gold and stock markets, determining whether there is any phenomenon of price inflation and market manipulation.

EVN Hanoi responds to Lao Dong Newspaper about electricity bills that are identical to each figure

|

EVN Hanoi has sent a document to Lao Dong Newspaper after a customer's reflection that the August electricity bill is identical, without any wrong numbers.

3,500 billion VND traffic project in Quang Ngai struggles due to land clearance problems

VIÊN NGUYỄN |

Quang Ngai - Slow site clearance and not seamless handover areas have caused many difficulties in the construction progress of the Hoang Sa - Doc Soi road project.

3,000 workers work through the September 2 Ceremony for the progress of the Quang Ngai - Hoai Nhon Expressway project

Viên Nguyễn |

Whether it is a normal day or a holiday or Tet holiday, for more than 2 years, thousands of workers, engineers... have been working tirelessly at the Quang Ngai - Hoai Nhon expressway construction site, determined to complete the project on schedule by the end of 2025.

Nguyên Chủ tịch UBND tỉnh Quảng Ngãi và cấp dưới mắc sai phạm ở dự án cầu Thạch Bích

VIÊN NGUYỄN |

Quảng Ngãi - Quá trình triển khai Dự án cầu Thạch Bích đã mắc sai phạm trong việc tách thửa và đăng ký biến động, chỉnh lý tên người sử dụng đất...