Hanoi starts construction of nearly VND56,300 billion expressway, to be completed in 2028

HỮU CHÁNH - VĂN ĐỨC |

Hanoi - Component project 3, construction of the 113km Ring Road 4 expressway in the Capital region, with a total investment of nearly VND 56,300 billion, is expected to be completed in 2028.

On September 6, in Noi Bai commune (Hanoi), the Hanoi People's Committee and the City Traffic Construction Investment Project Management Board coordinated with Hanoi Ring Road 4 Expressway Joint Stock Company to organize the groundbreaking ceremony of Component Project 3: Investing in the construction of the expressway under the public-private partnership (PPP) method under the Hanoi Ring Road 4 project.

Hanoi Ring Road 4 Expressway Joint Stock Company is the representative of the joint venture of City Real Estate Investment Company Limited, Saigon Huong Duong Flowers Company Limited, Vietnam Expressway Development Investment Corporation and Horizon Investment Joint Stock Company Limited.

Identified as a national key project, Ring Road 4 has strategic significance in developing transport infrastructure, enhancing regional connectivity, directly connecting Hanoi with neighboring provinces and synchronizing with the expressway system - radial axis.

This will be the new traffic artery of the Capital region, contributing to promoting socio-economic development, attracting investment, forming new satellite cities and growth poles.

Cac dai bieu tham du le khoi cong. Anh: Le Khanh
Delegates attending the groundbreaking ceremony. Photo: Le Khanh

Component project 3 - the central expressway section of the route is about 113.52km long, with a cross-section of 17m. The large bridges across the river are 24.5m wide, ensuring modern technical standards. In phase 1, the cross-section of the route is designed to meet the traffic volume of 4 lanes.

The entire route has 13 elevated sections with a total length of 80.985km, accounting for more than 71%. The project will arrange 3 large bridges across the river including Hong Ha, Me So and Hoai Thuong, along with 8 interconnecting intersections and one comprehensively completed intersection.

According to Decision 6479/QD-UBND dated December 20, 2023 of the Hanoi People's Committee, the total investment of component project 3 is VND 56,293 billion. Of which, the State budget capital accounts for 47.5%, while 52.5% is capital guaranteed by investors under the public-private partnership (PPP) mechanism. The construction period according to the signed contract is 30 months.

Pho Chu tich Quoc hoi Vu Hong Thanh phat bieu tai le khoi cong. Anh: Huu Chanh
Vice Chairman of the National Assembly Vu Hong Thanh spoke at the groundbreaking ceremony. Photo: Huu Chanh

Speaking at the ceremony, Vice Chairman of the National Assembly Vu Hong Thanh emphasized that the Ring Road 4 project in the Capital Region, especially component 3, not only has the meaning of opening new development space for the Capital and neighboring provinces, but is also an important driving force for regional economic development, job creation, and improving people's lives.

Mr. Thanh requested ministries, branches, localities, investors and construction units to promote the highest sense of responsibility, ensuring progress, quality, safety and transparency throughout the implementation process.

Mr. Truong Viet Dong, Chairman of the Board of Directors of Vietnam Expressway Corporation - VEC, said that the contractor is committed to mobilizing sufficient finance, equipment, and human resources to strive to complete and hand over the Component Project 3 for operation before the contract deadline.

With the role of "new traffic corridor" of the Capital region, the expressway on Ring Road 4 is expected to create a strong breakthrough, promote investment attraction, develop satellite cities, form new growth poles, thereby contributing to realizing the goal of building Hanoi into a modern, civilized, beautiful city, spreading development momentum to the Northern provinces.

HỮU CHÁNH - VĂN ĐỨC
RELATED NEWS

Hanoi proposes to soon construct 3 bridges across the Red River on Ring Road 4

|

Hanoi recommends that investors and project enterprises focus on mobilizing capital and soon select contractors to construct the entire route, especially the 3 large bridges on Ring Road 4.

Hanoi is about to start construction of Ring Road 4 expressway, many bridges across the Red River

|

During major holidays from now until the end of the year, Hanoi will start many important transport projects, including the Ring Road 4 and 4 expressways across the Red River.

Hanoi Ring Road 4 project faces obstacles, risk of missing the completion date by the end of this year

|

Hanoi - 11/17 wards and communes have not yet handed over enough land to the contractor, causing the project to build the Ring Road 4 parallel road to risk missing the completion date by the end of 2025.

Mr. Pham Duc An is introduced to be elected Chairman of the People's Committee of Da Nang City

|

Mr. Pham Duc An - Chairman of the People's Committee of Quang Ninh province, was transferred and appointed as Deputy Secretary of the Da Nang City Party Committee to introduce and elect the Chairman of the Da Nang City People's Committee.

Gold price increases sharply, surpassing 135 million VND/tael

|

On September 6, domestic gold prices continued to escalate, gold bars hit a new peak of over 135 million VND/tael, the highest level ever.

Ho Chi Minh City soldiers tell about beautiful memories when participating in A80 in Hanoi

|

HCMC - Returning after the A80 mission, the soldiers are not only proud, but also carry the memories and love of the people of the North for them.

Hanoi starts construction of nearly VND56,300 billion expressway, to be completed in 2028

|

Hanoi - Component project 3, construction of the 113km Ring Road 4 expressway in the Capital region, with a total investment of nearly VND 56,300 billion, is expected to be completed in 2028.

EVN Hanoi responds to Lao Dong Newspaper about electricity bills that are identical to each figure

|

EVN Hanoi has sent a document to Lao Dong Newspaper after a customer's reflection that the August electricity bill is identical, without any wrong numbers.

Hanoi proposes to soon construct 3 bridges across the Red River on Ring Road 4

HỮU CHÁNH |

Hanoi recommends that investors and project enterprises focus on mobilizing capital and soon select contractors to construct the entire route, especially the 3 large bridges on Ring Road 4.

Hanoi is about to start construction of Ring Road 4 expressway, many bridges across the Red River

SÓNG HỮU |

During major holidays from now until the end of the year, Hanoi will start many important transport projects, including the Ring Road 4 and 4 expressways across the Red River.

Hanoi Ring Road 4 project faces obstacles, risk of missing the completion date by the end of this year

SÓNG HỮU |

Hanoi - 11/17 wards and communes have not yet handed over enough land to the contractor, causing the project to build the Ring Road 4 parallel road to risk missing the completion date by the end of 2025.