National Highway 46 expansion project is stuck in land clearance, provincial leaders give urgent instructions

QUANG ĐẠI |

Nghe An - Provincial leaders requested to complete the handover of the site for the project to renovate and expand National Highway 46 Vinh - Nam Dan section before June 20, 2025..

On April 29, information from Nghe An Provincial People's Committee said that Vice Chairman of the Provincial People's Committee Hoang Phu Hien chaired a working session with departments, branches, Nam Dan district and Project Management Board 85 to remove obstacles to site clearance for the National Highway 46 renovation and expansion project, Vinh - Nam Dan section.

Accordingly, Vice Chairman of Nghe An Provincial People's Committee Hoang Phu Hien requested Nam Dan District People's Committee to complete the handover of the entire site before June 20, 2025.

Pho Chu tich UBND tinh Nghe An yeu cau UBND huyen Nam Dan ban giao toan bo mat bang truoc ngay 20.6.2025. Anh: Quang Dai
The Vice Chairman of Nghe An Provincial People's Committee requested Nam Dan District People's Committee to hand over the entire site before June 20, 2025. Photo: Quang Dai

Specific milestones are set: Handover of vacant land plots before May 30.4; remaining agricultural land before May 10.5; residential land and resettlement infrastructure before May 20. The inventory and counting work must be completed before May 20.

For the technical infrastructure system, the People's Committee of Nam Dan district must urge the relocation of water supply and telecommunications works before May 30.; lighting infrastructure, trees before May 20 and medium and low voltage power before May 30. In case of difficulties, there must be a document promptly proposing a specific plan.

The Department of Construction is assigned to preside over and urge site clearance; the Department of Finance must promptly advise on funding for relocating the project within 3 days from receiving the proposal. The Department of Agriculture and Environment is also required to prioritize handling related records to remove obstacles.

Project Management Board 85 was directed to proactively coordinate with localities, update detailed progress of each household, and report to the Provincial People's Committee periodically and suddenly. At the same time, the contractor must concentrate machinery and human resources to construct the sections where the site is available, ensuring traffic safety, environmental sanitation and irrigation systems for production.

Notably, Nghe An Water Supply Joint Stock Company is also required to urgently relocate water pipes before May 10 for sections that have been cleared, while maintaining staff at the site to coordinate construction.

Vice Chairman of the Provincial People's Committee Hoang Phu Hien emphasized: Localities and units must resolutely carry out their tasks, not to let the project progress be affected, because this is a key project, contributing to promoting infrastructure connectivity and socio-economic development of the province.

Previously, as reported by Lao Dong Newspaper, the project to renovate and expand National Highway 46 from Nam Giang commune to Nam Dan town (Nam Dan district), with a total investment of 500 billion VND from the central medium-term capital, is facing the risk of being behind schedule due to problems in site clearance.

According to Nam Dan District People's Committee, only about 6km/10.69km of the route length has been handed over so far (56%). The remaining site is facing many difficulties and problems, while according to the requirement, the site must be handed over in May, ensuring the project completion progress in 2025.

QUANG ĐẠI
RELATED NEWS

Thai Nguyen removes obstacles to the site clearance of a traffic project worth hundreds of billions of VND

|

Thai Nguyen - The hundred-billion-dong traffic road project in Pho Yen City is being focused on removing obstacles in terms of land, expected to be completed in 2025.

Urgently clear the construction site for the Son My 1 Industrial Park project

|

Binh Thuan - The progress of the Son My 1 Industrial Park project is still slow, so the locality is speeding up compensation and site clearance to have a site for construction.

The 500 billion VND national highway expansion project in Nghe An is stuck in land clearance

|

Nghe An - The National Highway 46 expansion project, Vinh - Nam Dan section, still faces many barriers in site clearance, with the risk of being behind schedule.

14th Party Congress: The role of connecting the past and future

|

The 14th Congress plays an important role in development, when discussing policies to achieve the goals to 2030, realizing the vision to 2045.

People celebrate Tet early, gardeners are busy supplying flowers to the market

|

Although there is still about 1 month until Tet Nguyen Dan, the Tet flower market is already bustling.

Minister Nguyen Manh Hung: Science and technology, innovation elevate Vietnam's position in the new era

|

On the occasion of the 14th National Party Congress - an important milestone opening a new stage of development for the country, Minister of Science and Technology Nguyen Manh Hung shared about the role of science and technology, innovation and digital transformation in becoming the central driving force for rapid and sustainable development of Vietnam.

Looking towards the 14th Party Congress, Can Tho is brilliant with flags, flowers, and banners

|

Can Tho - Heading towards the 14th Party Congress, many central streets of Can Tho are brilliant with flags, flowers, and banners, creating a solemn and exciting atmosphere.

The 4th Party Congress through historical pages in Lao Dong Newspaper

|

At the 4th Congress of the Party (1976), Lao Dong Newspaper strongly conveyed the atmosphere full of excitement and the great stature of the victorious congress.

Thai Nguyen removes obstacles to the site clearance of a traffic project worth hundreds of billions of VND

Nguyễn Hoàn |

Thai Nguyen - The hundred-billion-dong traffic road project in Pho Yen City is being focused on removing obstacles in terms of land, expected to be completed in 2025.

Urgently clear the construction site for the Son My 1 Industrial Park project

Duy Tuấn |

Binh Thuan - The progress of the Son My 1 Industrial Park project is still slow, so the locality is speeding up compensation and site clearance to have a site for construction.

The 500 billion VND national highway expansion project in Nghe An is stuck in land clearance

QUANG ĐẠI |

Nghe An - The National Highway 46 expansion project, Vinh - Nam Dan section, still faces many barriers in site clearance, with the risk of being behind schedule.