Removing the site, speeding up the construction of Nhat Le 3 bridge

CÔNG SÁNG |

The Nhat Le 3 Bridge project is accelerating construction but is still stuck with site clearance in Bao Ninh commune, affecting the progress of key projects in Quang Binh.

Speed up construction progress

In mid-April, the construction atmosphere at the Nhat Le 3 bridge project and the routes at both ends of the bridge took place urgently. This is a component project 2 of the province's key infrastructure development program, with a total investment of 1,300 billion VND. The project is expected to create a breakthrough for transportation and tourism development in Bao Ninh sea area.

According to the reporter of Lao Dong Newspaper, at the construction site of Nhat Le 3 bridge, dozens of workers and machines are working continuously many shifts a day.

Technical officer Le Minh Tri - who is directly in charge of supervising the construction - said: "The total output currently implemented is more than 80% of the contract volume. We have completed pouring concrete for the main girder ( Pi girder), constructing cable stretching, and pumping water for the sections of Pi girder No. 1 and No. 8. However, the access road on the Bao Ninh commune side is still stuck with site clearance, so it cannot be implemented synchronously".

Nhat Le 3 Bridge Project has a length of 561.4m, a bridge with 23.5m wide, connecting the center of Dong Hoi City through Bao Ninh commune. The entire component project 2, including the two -end road with a total length of more than 2.8 km, is invested by the Department of Finance of Quang Binh province. The construction unit is Dat Phuong Group Joint Stock Company. Expected implementation time is from 2022 to 2026.

According to the basic infrastructure project management board for comprehensive development of Quang Binh province, the total land area to be recovered to serve the project is 15.33ha. Of which, 3.6ha in the old Luong Ninh commune (Quang Ninh district), the remaining 11.73ha is located in Bao Ninh commune (Dong Hoi City). The ground clearance (GPMB) has now been completed 8.58 ha, the remaining 6.75ha, mainly in Bao Ninh commune is continuing to implement.

Finding a solution

The biggest difficulty at present is supporting resettlement for people. Some problems related to basic legal policies have been resolved. Currently, the authorities are entering the counting stage, developing specific compensation plans.

Mr. Nguyen Thang Long - Vice Chairman of Dong Hoi City People's Committee - said: "The city is resolutely coordinating with relevant parties to promptly resolve the backlog in the land acquisition. The resettlement area for people has been arranged, and is expected to hand over the site in May, creating conditions to speed up construction in June".

Component project 2 - Nhat Le 3 bridge and the road at both ends of the bridge, is identified as a key traffic project, playing a role in linking coastal economic regions and serving the urban development of the East of Dong Hoi city. When completed, the project will contribute to reducing traffic pressure on Nhat Le 1 and 2 bridges, while creating momentum for tourism and service development in Bao Ninh commune and surrounding areas.

The People's Committee of Quang Binh province requires investors, contractors, relevant departments, branches and localities to continue to closely coordinate and thoroughly remove remaining problems, especially in site clearance, a key factor determining the progress of the entire project.

The province has also assigned specific tasks to each unit, organize periodic inspections, urge and promptly adjust construction organization plans to suit the actual situation. The goal is to complete the project on schedule, ensure quality and promote efficiency immediately after being put into use.

Nhat Le 3 Bridge is not only a traffic infrastructure, but also a symbol of the future connection of Quang Binh, opening up new development space for the city on the Nhat Le River.

CÔNG SÁNG
TIN LIÊN QUAN

The project to open the road 575 billion dong in Ha Tinh is still entangled

|

Ha Tinh - Ham Nghi Street project extended with a total investment of 575 billion VND is still entangled in site clearance after the delayed progress has had to apply for an extension.

Many key projects in Nghe An, Quang Tri have difficulty because of clearance

|

Many key projects in Nghe An and Quang Tri have large investment capital, facing the risk of delayed progress due to site clearance (GPMB) facing many difficulties and obstacles.

There is still no blockage of the Titana mine blocking the coastal road project

|

Binh Thuan - Although the provincial People's Committee directs departments and localities to accelerate the procedures soon to have the Titan mine caught segment to construct the DT.719B road, but still entangled.

The brotherhood relationship in "My father, the one who stays" received backlash

|

New developments in the film "My Father, the Remaining Person" are controversial, especially the relationship of the couple An - Nguyen.

People's Artist Ta Minh Tam, Phuong My Chi and more than 1,000 performing artists at the April 30 celebration

|

The special art program with the theme "Rang Dong Tuong Viet Nam" has the participation of more than 1,000 artists and actors such as Phuong My Chi, Ta Minh Tam...

Russia reminds the nuclear red lines, warns the West

|

Russia's revised nuclear doctrine has detailed the conditions under which the country can use nuclear weapons and which anyone can read.

Xuan Son may receive a large signing bonus from the contract with Nam Dinh team

|

Striker Xuan Son can receive about 36 billion VND in signings (excluding salary) at Nam Dinh club, based on a new contract with a term of 6 years.

Vice Chairman - General Secretary of the Central Committee of the Vietnam Fatherland Front meets with the Chairman of the National Political Commissar of China

|

Ms. Nguyen Thi Thu Ha, Member of the Party Central Committee, Vice Chairman - General Secretary of the Central Committee of the Fatherland Front (Fatherland Front) of Vietnam had met with Mr. Vuong Ho Ninh, Member of the Standing Committee of the Politburo of the Chinese Communist Party, President of China.

The project to open the road 575 billion dong in Ha Tinh is still entangled

TRẦN TUẤN |

Ha Tinh - Ham Nghi Street project extended with a total investment of 575 billion VND is still entangled in site clearance after the delayed progress has had to apply for an extension.

Many key projects in Nghe An, Quang Tri have difficulty because of clearance

QUANG ĐẠI - HƯNG THƠ |

Many key projects in Nghe An and Quang Tri have large investment capital, facing the risk of delayed progress due to site clearance (GPMB) facing many difficulties and obstacles.

There is still no blockage of the Titana mine blocking the coastal road project

Duy Tuấn |

Binh Thuan - Although the provincial People's Committee directs departments and localities to accelerate the procedures soon to have the Titan mine caught segment to construct the DT.719B road, but still entangled.