Ke Go Lake upgrade project under pressure of upcoming rainy and flood season

TRẦN TUẤN |

Ha Tinh - After more than a year and a half of construction, the project to upgrade and repair Ke Go Lake is currently under pressure for progress as the rainy and flood season is approaching.

On July 27, reporters of Lao Dong Newspaper recorded that the project to upgrade and repair Ke Go lake in Cam Due commune has entered the final stage.

The contractor is a joint venture of Construction Joint Stock Company 47 - Lilama 10 Joint Stock Company - Construction Joint Stock Company 465, which is focusing on construction to complete and hand over the project.

Currently, workers are focusing on constructing concrete for the Doc Mieu flood spillway and repairing the water intake tower.

Cầu vượt tràn Dốc Miếu đã hoàn thành. Ảnh: Trần Tuấn
Doc Mieu overpass has been completed. Photo: Tran Tuan
Nhà thầu sắp hoàn thành thi công đổ bê tông tràn Dốc Miếu. Ảnh: Trần Tuấn
The contractor is about to complete the construction of concrete pouring for the Doc Mieu flood spillway. Photo: Tran Tuan

Mr. Nguyen Minh Hieu - official of the Irrigation Investment and Construction Management Board 1 - said that the project to upgrade and repair Ke Go Lake has now reached a total construction volume of about 98%.

The project of pouring concrete for the Dốc Miếu flood spillway has now been almost completed. Recently, the contractor has focused maximum manpower to accelerate the construction progress. However, in recent days there has been afternoon rain, which has affected the construction," Mr. Hieu shared.

According to Mr. Hieu, the project will be completed and handed over on December 31, 2026. With the construction volume achieved as it is now, it is expected that the completion and handover of the entire project will ensure the set schedule. However, it is still necessary to make great efforts to accelerate in favorable weather days before the rainy and flood season comes.

The project to upgrade and repair Ke Go Lake has a total investment of 350 billion VND from central capital, invested by the Irrigation Investment and Construction Management Board 1, and started on December 27, 2024.

Hạng mục sửa chữa, nâng cấp đập chính cũng sắp hoàn thành. Ảnh: Trần Tuấn.
Main dam repair and upgrade item is about to be completed. Photo: Tran Tuan.

The project includes items: Repairing and upgrading the main dam, auxiliary dams 1 and 2, Doc Mieu spillway, water intake culvert, Doc Mieu spillway management and operation building and behind the main dam; building a new flood discharge spillway.

Ke Go reservoir was built in 1976, with a capacity of 345 million m3, and is the most important irrigation project in Ha Tinh.

Ke Go Lake not only serves irrigation for tens of thousands of hectares of agricultural land but also has the task of cutting and reducing floods for downstream areas, supplying domestic water and maintaining the ecological environment.

Hồ Kẻ Gỗ. Ảnh: Trần Tuấn
Ke Go Lake. Photo: Tran Tuan

The project to upgrade and repair Ke Go reservoir contributes to smooth and effective operation in irrigation, flood cutting and ensuring dam safety, especially during the rainy and flood season.

TRẦN TUẤN
RELATED NEWS

Contractor faces difficulties due to problems at public investment project in Quang Ngai

|

Quang Ngai - The project of the Provincial People's Committee headquarters is unfinished and behind schedule due to not being paid enough construction volume...

Ho Chi Minh City completes 9 flood control projects in 2026

|

Ho Chi Minh City will complete 9 flood control and drainage projects with a total investment of more than 7,100 billion VND in 2026.

The project implemented by Cat Loi Urban Development Investment Company has many shortcomings pointed out

|

Bac Ninh Provincial Inspectorate pointed out many shortcomings in the project implemented by Cat Loi Urban Development Investment Joint Stock Company.

The journey to find the identity for martyrs with science and technology and gratitude

|

Hanoi - The journey to find the identity of martyrs through DNA testing is gradually reconnecting the unfinished memories of martyrs' families.

Clarifying the case of a man suspected of committing suicide after buying land with overlapping boundaries

|

Ho Chi Minh City - Functional agencies are clarifying the case of Mr. H.B.L writing a suicide note about buying land overlapping the boundary, then falling into a deadlock and suspected suicide.

Live football Indonesia vs Cambodia at ASEAN Cup 2026

|

Live football match Indonesia vs Cambodia in Group A ASEAN Cup 2026 at 8:30 PM on July 27.

Former Miss Dieu Van: Titles can be returned, the crown kept as evidence is fake

|

Talking to Lao Dong Newspaper on the afternoon of July 27, former Miss Dieu Van said that she still keeps the crown that was once announced to be worth 3 billion VND as evidence that it is... fake.

5km road in the center of Ho Chi Minh City is expected to have up to 5 steel overpasses

|

Ho Chi Minh City - With 3 steel overpasses expected to be additionally invested, 3 Thang 2 road will have a total of 5 overpasses on a length of only about 5km.

Contractor faces difficulties due to problems at public investment project in Quang Ngai

THANH TUẤN |

Quang Ngai - The project of the Provincial People's Committee headquarters is unfinished and behind schedule due to not being paid enough construction volume...

Ho Chi Minh City completes 9 flood control projects in 2026

MINH QUÂN |

Ho Chi Minh City will complete 9 flood control and drainage projects with a total investment of more than 7,100 billion VND in 2026.

The project implemented by Cat Loi Urban Development Investment Company has many shortcomings pointed out

ĐÌNH TRƯỜNG |

Bac Ninh Provincial Inspectorate pointed out many shortcomings in the project implemented by Cat Loi Urban Development Investment Joint Stock Company.