Key project in Hue still entangled with 14 land plots

PHÚC ĐẠT - NGUYỄN LUÂN |

The Nguyen Hoang road project in Hue has cleared more than 89.6% of the site, but there are still 14 land plots with problems, which may need to be forced to recover.

Encountering site clearance

These days, at the Nguyen Hoang road expansion project construction site (Hue City), hundreds of workers and many machines and vehicles are being mobilized to speed up the construction progress of items.

Along both sides of the route, many households have handed over the site, construction forces are urgently dismantling the works, leveling and transporting rubble to create a clean site to serve the project. Trucks continuously enter and exit the construction site to transport materials, soil and rocks, creating a bustling construction atmosphere throughout the route. Despite the hot weather and high traffic density, construction teams are still deployed simultaneously to ensure project progress.

The Hue City Traffic Construction Investment Project Management Board said that the project to expand Nguyen Hoang road and Nguyen Hoang bridge coincides with the center line of Ring Road 3, with a total investment of more than 2,281 billion VND. The project affects 134 households in Kim Long ward. Up to now, most people have agreed to hand over the site for construction.

According to the design, the road is more than 1km long, the starting point connects the North roundabout of Nguyen Hoang bridge, the ending point is at the Ly Nam De intersection, Kim Long ward. The project is invested according to urban main street standards with a design speed of 60km/h, a cross-section width of 43m including 6 car lanes, a median strip of 5m wide and sidewalks of 8.5m wide on each side.

However, according to the investor, the overall progress of the project is still affected because some households have not handed over the land.

Will be forced to hand over the land

Mr. Bui Ngoc Chanh - Head of Site Clearance Department, Area 1 Investment Project Management Board - Hue City - said that the Nguyen Hoang road and Huong River overpass project have currently cleared more than 89.6% of the affected area.

To date, functional agencies have approved 20 decisions to recover land and relocate technical infrastructure for 134 land plots, with a total compensation and support cost of more than 292.7 billion VND. Of which, more than 227.2 billion VND has been paid, and about 60.5 billion VND has not been paid. Currently, 120/134 land plots have been handed over to the Hue City Traffic Construction Investment Project Management Board for construction. However, there are still 14 land plots that have not been handed over due to obstacles. Among them, the section from Kim Long street to Pham Thi Lien street still has 13 cases that have not agreed on a compensation plan. Some households have proposed land compensation according to location 1, requested additional residential land compensation, arranged resettlement in the form of "land for land exchange" or proposed consideration for support for the area outside the land use right certificate.

Kim An Pagoda has not yet agreed to receive money and hand over the site due to complaints related to agricultural land compensation. In the section from Pham Thi Lien street to Ly Nam De street, a contract inheritance case also requested to be compensated for the entire area of residential land that was recovered. Currently, functional agencies are submitting for approval additional compensation, support and resettlement values for households...

PHÚC ĐẠT - NGUYỄN LUÂN
RELATED NEWS

Dong Nai publicizes compensation plan for road 25B expansion project

|

Dong Nai - Long Thanh Ward People's Committee publicly announces compensation and support plan (phase 7-supplement) for the project to upgrade and expand road 25B.

Khanh Hoa inspects 11 social housing projects monthly

|

Khanh Hoa - To complete the assigned social housing target, the locality will organize periodic inspections of the progress of 11 projects being implemented.

Da Nang removes procedures for 39 projects, completing social housing target

|

Da Nang - Da Nang City People's Committee has just informed about the licensing situation of 39 investment projects and the implementation of the social housing construction plan for the next phase.

Tighten high-tech fraud before the 2026 high school graduation exam

|

Before the 2026 high school graduation exam, localities are recommended to use police technical equipment to detect high-tech equipment cheating on exams.

Ho Chi Minh City seeks expert opinions for 100-year vision master plan

|

Ho Chi Minh City is building a master plan with a 100-year vision, aiming for a 1,200 billion USD megacity, to be included in the group of 100 most livable cities in the world.

Russia launches fierce attack on Kiev

|

Kiev suffered a wave of fierce attacks from Russia, many people are believed to be trapped under the rubble of an apartment building.

Stock market has not shown signs of bottoming out

|

The stock market will continue to adjust to retest support zones if demand does not improve soon in the coming sessions.

Expecting Vietnam Trade Union to have a large-scale program on AI and digital skills universalization

|

That is the expectation of Ms. Tran Thuy Duong - Member of the Executive Committee of FPT Corporation Trade Union, Chairwoman of FPT University Trade Union.

Dong Nai publicizes compensation plan for road 25B expansion project

HÀ ANH CHIẾN |

Dong Nai - Long Thanh Ward People's Committee publicly announces compensation and support plan (phase 7-supplement) for the project to upgrade and expand road 25B.

Khanh Hoa inspects 11 social housing projects monthly

Hữu Long |

Khanh Hoa - To complete the assigned social housing target, the locality will organize periodic inspections of the progress of 11 projects being implemented.

Da Nang removes procedures for 39 projects, completing social housing target

Nguyễn Linh |

Da Nang - Da Nang City People's Committee has just informed about the licensing situation of 39 investment projects and the implementation of the social housing construction plan for the next phase.