6-lane road to relieve traffic jam at Tan Son Nhat before opening day

Anh Tú |

HCMC - The Tran Quoc Hoan - Cong Hoa connecting road project is accelerating construction, with phase 1 expected to open to traffic on January 20, reducing congestion at Tan Son Nhat airport.

According to the plan, the Tran Quoc Hoan - Cong Hoa connecting road project will open phase 1 from Phan Thuc Duyen tunnel (from the beginning of the route to Hoang Hoa Tham) and complete all 3 connecting positions from the route to T3 station (above and below ground) on January 20, 2025.

Cau vuot truoc Nha ga T3 san bay Tan Son Nhat da co ban hoan thanh. Ảnh: Anh Tu
The overpass in front of Terminal T3 of Tan Son Nhat airport has been basically completed, the bridge is 988m long, 17m wide with 4 lanes. Photo: Anh Tu

The Management Board of Investment and Construction of Traffic Works in Ho Chi Minh City (Traffic Board) said: "Up to now, the two construction packages of phase 1 of the project have reached more than 98% completion, and contractors are working hard to complete the final items in time for the opening of traffic on January 20."

Nha thau huy dong may moc, cong nhan de day nhanh tien do lu nen, trai nhua cho phan mat duong duoi cau de kip thong xe vao ngay 20.1 toi. Ảnh: Anh Tu
The contractor mobilized machinery and workers to speed up the progress of rolling the ground and paving the road surface under the bridge to open to traffic on January 20. Photo: Anh Tu
Phan cau vuot tren duong noi Tran Quoc Hoan - Cong Hoa da hoan thien, he thong lan can duoc lap dat. Thoi diem nay, cac cong nhan dang thi cong ha tang ky thuat dien, son ke vach...
The overpass section on the road connecting Tran Quoc Hoan - Cong Hoa has been completed, the railing system has been installed. At this time, workers are constructing electrical infrastructure, painting lines... Photo: Anh Tu

According to the Traffic Department, the remaining section (from Hoang Hoa Tham Street to the end of the route) is expected to be handed over before February 20 and completed and opened to traffic before April 30, to serve the T3 terminal of Tan Son Nhat airport which will come into operation on April 30.

Cong tac giai phong mat bang tai doan cuoi du an dang duoc trien khai tich cuc.
Site clearance work at the final stage of the project is being actively implemented. Photo: Tuan Kiet

This section is currently stuck with 68 households. A representative of Tan Binh District People's Committee said that there are currently 22 cases that are partially affected and have not agreed to the compensation plan. According to the plan, before Tet, Tan Binh District will complete the demolition and hand over the site of 46 cases that have agreed to the compensation and resettlement support plan to implement the construction.

O phia cuoi du an duong noi hon 4.800 ty dong, tu duong Nguyen Duc Thuan ra Cong Hoa dai khoang 700m da co ban hoan thanh nhung chua the thong xe toan bo. Nguyen nhan do vuong mat bang khien nhieu hang muc chua the trien khai thi cong.
At the end of the project, from Nguyen Duc Thuan Street to Cong Hoa Street, about 700m long, has been basically completed but cannot be fully opened to traffic. The reason is that land acquisition problems have prevented many items from being constructed. Photo: Tuan Kiet

For the remaining 22 cases on the frontage and alleys 111, 119, 116 Tran Van Du street, the district will increase contact and mobilize households to hand over the premises to the Traffic Department by the end of February 2025.

Construction started at the end of 2022, the Tran Quoc Hoan - Cong Hoa connecting road project is more than 4 km long, with a total investment of more than 4,800 billion VND.

This is a completely new route, starting from the Tran Quoc Hoan - Phan Thuc Duyen intersection and ending at the C12 - Cong Hoa - Truong Chinh intersection.

The main road is 25 m to 48 m wide, with 6 lanes, and two connecting roads with 3 to 4 lanes wide.

a
Previously, the Tran Quoc Hoan - Phan Thuc Duyen underpass and two other road sections of the project, Phan Thuc Duyen connecting road (from Thang Long road to 18E road), and 18E road (from Phan Thuc Duyen connecting road to Cong Hoa road) were also opened to traffic. Photo: Anh Tu

On the route, there is an overpass in front of station T3 and two underpasses at the major intersections of Tran Quoc Hoan - Phan Thuc Duyen and Truong Chinh - Tan Ky Tan Quy.

When completed, this route will connect directly to Tan Son Nhat Airport Terminal 3, opening up additional access to the airport and reducing traffic pressure at the main entrance on Truong Son Street.

Anh Tú
TIN LIÊN QUAN

4,800 billion VND road to "rescue" Tan Son Nhat traffic jam reaches 88% of volume

|

HCMC - The Tran Quoc Hoan - Cong Hoa connecting road, costing over VND4,800 billion, has reached 88% completion, and is expected to open the entire route by the end of February 2025, reducing traffic congestion at Tan Son Nhat airport.

People have convenience when crossing the new road at Tan Son Nhat gateway

|

HCMC - The next two sections of the Tran Quoc Hoan - Cong Hoa connecting road construction project have been officially put into operation, serving the people.

Hoa Binh handles abandoned headquarters after Lao Dong Newspaper's reflection

|

Following the reflection of Lao Dong Newspaper, the Headquarters of the State Bank of Vietnam, Hoa Binh Province Branch, is expected to be handed over to Hoa Binh Newspaper and the Provincial Literature and Arts Association for management and use, ending the situation of abandonment and waste.

Discover the first "giant" Phalaenopsis orchid garden in Dien Bien

|

With just over 10 days left until Lunar New Year, the flower market in Dien Bien is extremely bustling. Besides peach and kumquat, phalaenopsis orchids are very popular.

Mass sale of mini apartments worth tens of billions of dong near Tet

|

Hanoi - Many mini apartment buildings worth tens of billions of dong are being sold by their owners near Tet.

A memorable journey of 30 years of Vietnam - US relations

|

US Ambassador to Vietnam Marc Knapper said that 2025 marks an important milestone in a memorable journey: the 30th anniversary of the establishment of Vietnam-US relations.

Bonsai-style Tet ornamental plants are popular and favored by many people

|

Bonsai trees are being chosen by many people during this year's Lunar New Year.

1 Major General, 6 Army Colonels Receive New Assignments

|

Last week (from January 13 to January 17), the agencies announced and handed over decisions on the transfer and appointment of 1 general officer and 6 colonel-level military officers.

4,800 billion VND road to "rescue" Tan Son Nhat traffic jam reaches 88% of volume

MINH QUÂN |

HCMC - The Tran Quoc Hoan - Cong Hoa connecting road, costing over VND4,800 billion, has reached 88% completion, and is expected to open the entire route by the end of February 2025, reducing traffic congestion at Tan Son Nhat airport.

People have convenience when crossing the new road at Tan Son Nhat gateway

Anh Tú |

HCMC - The next two sections of the Tran Quoc Hoan - Cong Hoa connecting road construction project have been officially put into operation, serving the people.

Thi công xuyên lễ ở công trình cửa ngõ sân bay Tân Sơn Nhất

Nguyên Chân |

TPHCM - Tại công trình xây dựng đường nối đường Trần Quốc Hoàn - Cộng Hòa (quận Tân Bình), hàng chục công nhân vẫn tất bật làm việc xuyên lễ 2.9.