Phu Quoc airport expansion project runway approaches completion date

NGUYÊN ANH |

An Giang - The Phu Quoc International Airport expansion project is one of the key projects to serve APEC 2027.

Only after exactly 3 months of lightning-fast construction, the 1C parking area of the Phu Quoc International Airport expansion project officially put into operation from April 16, 2026. This is not only the first item in the project complex to serve APEC to reach the finish line but also set a record for construction progress in the history of Vietnamese aviation infrastructure.

Along with the joy from parking lot 1C, other key items of the project also recorded impressive growth figures every day.

According to the progress report (recorded until April 17, 2026), runway (CHC) No. 2, 3, 300m long, is very close to completion. The cement concrete (BTXM) layer M150/25 has reached 95% of the workload. This is the most important foundation layer to create stability for the runway. Meanwhile, the high-quality surface concrete layer M350/45, which requires the most stringent construction techniques to withstand the load of wide-body aircraft, has also reached 31%.

Dự án mở rộng Cảng Hàng không Quốc tế Phú Quốc được giao triển khai trong 18 tháng. Ảnh: Sun Group
The Phu Quoc International Airport expansion project is assigned to be implemented in 18 months. Photo: Sun Group

According to the approved roadmap, it is expected that by June 30, 2026, IC No. 2 will be officially technically accepted. Immediately after that, flight standardization work to check navigation systems, traffic lights and flight safety will be deployed. If the indicators meet standards, Phu Quoc International Airport will officially put the second runway into operation in August 2026, helping to double the flight reception capacity here.

As for the station area, the construction atmosphere is also no less urgent. Passenger terminal T2 is designed inspired by the flaming phoenix wing, currently reaching 87% of the rough structure volume. Currently, the project has officially entered the stage of installing roof steel structure. Giant steel frames are gradually shaping the image of flaming phoenix wings reaching out strongly.

In particular, the VIP Terminal - which will welcome heads of state and high-level guests, is the item with the earliest progress in the terminal block. Up to now, 100% of the rough structure has been completed, and the roof steel structure has also reached 70%. The sophistication in the roof structure construction of the VIP Terminal is expected to fully reflect the artistic intention of the architect to turn this place into a "luxury living room" in the region.

At the same time, the parking area of the station area is also being urgently deployed. The M350/45 BTXM layer in area T2 has reached 10% and the VIP area has reached 13%. The synchronous deployment from the station to the parking area ensures that when the project is inaugurated, all links will reach a ready, smooth state and meet the highest service standards.

With a total deployment time of 18 months, the Phu Quoc International Airport expansion project is one of the key projects to serve APEC 2027.

Công nhân làm việc tất bật trên đại công trường. Ảnh: Sun Group
Workers are working busily on the large construction site. Photo: Sun Group

At the Nam Dao large construction site, the overnight construction pace of hundreds of motorized vehicles, along with thousands of workers, created an unprecedented acceleration race.

With this pace of progress, the "Phu Quoc miracle" is gradually becoming a reality, establishing new standards of speed and quality in infrastructure investment in Vietnam, contributing to making Phu Quoc one of the new aviation, tourism and event centers of the world.

NGUYÊN ANH
RELATED NEWS

Super project of 22,000 billion VND in Phu Quoc serving APEC reaches the first item

|

An Giang - Parking area 1C of the Phu Quoc International Airport expansion project officially put into operation from April 16, 2026.

Phu Quoc launches "Security Loudspeaker" applying AI to propagate the law

|

The project aims to implement the Project of An Giang Provincial People's Committee on building Phu Quoc special zone into a "Model unit for security, order and urban civilization".

Mr. Tran Minh Khoa continues to be elected as Chairman of Phu Quoc Special Economic Zone People's Committee

|

An Giang - Mr. Tran Minh Khoa continues to be trusted by delegates to be elected to hold the position of Chairman of Phu Quoc Special Economic Zone People's Committee.

National Assembly finalizes birth certificates, marriage certificates must be signed by the Chairman of the Commune People's Committee

|

The Law on Civil Status (amended) stipulates that the Chairman of the Commune-level People's Committee must directly sign birth certificates and marriage certificates.

Lao Cai gold - the first gold enterprise to list on the stock exchange fluctuates due to debt

|

Losing the right to exploit Minh Luong gold mine, accumulated losses exceeding charter capital, Lao Cai Gold Company is facing the most difficult period since listing on the stock exchange.

The role of trade unions in protecting workers in the digital transformation era

|

Quang Ninh - On the morning of April 23, in Bai Chay, the Vietnam General Confederation of Labor organized a workshop "Trade Unions innovate and improve the efficiency of occupational safety and health in the digital age".

Latest information on the expected support level when converting gasoline cars to electric vehicles

|

Hanoi - When converting gasoline cars to electric vehicles, people are expected to receive a support of 20% of the vehicle value but not exceeding 5 million VND.

Whales reappear, opening their mouths to hunt prey in Mui Ne sea

|

Lam Dong - People again see whales heading up to the sea surface and continuously opening their mouths to hunt prey in Mui Ne sea. This is the 2nd time in the past week.

Super project of 22,000 billion VND in Phu Quoc serving APEC reaches the first item

NGUYÊN ANH |

An Giang - Parking area 1C of the Phu Quoc International Airport expansion project officially put into operation from April 16, 2026.

Phu Quoc launches "Security Loudspeaker" applying AI to propagate the law

NGUYÊN ANH |

The project aims to implement the Project of An Giang Provincial People's Committee on building Phu Quoc special zone into a "Model unit for security, order and urban civilization".

Mr. Tran Minh Khoa continues to be elected as Chairman of Phu Quoc Special Economic Zone People's Committee

NGUYÊN ANH |

An Giang - Mr. Tran Minh Khoa continues to be trusted by delegates to be elected to hold the position of Chairman of Phu Quoc Special Economic Zone People's Committee.