500kV Lao Cai - Vinh Yen line, a strategic energy bridge in the Northwest with the whole country

Tuyết Lan |

The 500kV Lao Cai - Vinh Yen line helps transmit electricity from Northwest hydropower plants and opens up potential for cooperation in power supply with other countries in the future.

Contributing to ensuring national energy security

On October 17, 2025, in Xuan Quang commune, Lao Cai province, Vietnam Electricity Group held an inauguration ceremony for the Lao Cai - Vinh Yen 500 kV Power Line project.

Speaking at the ceremony, Deputy Prime Minister Ho Duc Phoc emphasized that the 500 kV Lao Cai - Vinh Yen Power Line project is of special importance in ensuring national energy security, contributing to concretizing the direction of the Politburo in Resolution No. 70 on ensuring national energy security.

Pho Thu tuong Ho Duc Phoc ghi nhan va cam on dong bao, nhan dan cac dan toc tai cac dia phuong da dong tinh ung ho, nhuong cho o, noi tho tu, dat canh tac, noi san xuat, kinh doanh va giai phong ban giao de cong trinh duoc thi cong thuan loi. Anh: Tuyet Lan
Deputy Prime Minister Ho Duc Phoc acknowledged and thanked people in localities for giving up their houses, places of worship, cultivated land, places of production, business and liberation, and handover to facilitate construction. Photo: Tuyet Lan

The Deputy Prime Minister emphasized that Vietnam's socio-economic growth target at this stage requires the electricity industry to focus on development, increasing annual power generation capacity by about 15-18% (equivalent to 8,000-10000 MW) to ensure electricity supply for economic development, attracting domestic and foreign investment.

"The 500 kV Lao Cai - Vinh Yen transmission line project is of special significance, promptly increasing about 3,000MW of power transmission capacity from hydropower plants in the Northwest region and neighboring provinces to the national grid. At the same time, in the future, it will meet the needs of electricity supply cooperation with China; ensure proactiveness and flexibility in direction, operation, balance of electricity supply and ensure national energy security" - the Deputy Prime Minister assessed.

Ong Pham Hong Phuong - Pho Tong giam doc EVN phat bieu tai buoi le. Anh: Tuyet Lan
Mr. Pham Hong Phuong - Deputy General Director of EVN spoke at the ceremony. Photo: Tuyet Lan

Reporting on the project construction process to Deputy Prime Minister Ho Duc Phoc, Mr. Pham Hong Phuong - Deputy General Director of EVN said that during more than 6 months of implementation, the project has faced many difficulties and challenges from harsh weather conditions, difficult mountainous terrain, complex geology, large site clearance volumes to urgent progress requirements.

"With experience in implementation and high determination and outstanding efforts of the units, the project is always implemented urgently, synchronously and effectively. By September 30, 2025, the project had successfully energized the shock absorbers, qualified to complete the procedures to put the project into official operation" - said an EVN representative.

Taking care of and protecting the rights of workers at the construction site

Speaking at the ceremony, Mr. Phan Van Anh - Vice President of the Vietnam General Confederation of Labor (Vietnam General Confederation of Labor) - emphasized that the Lao Cai - Vinh Yen 500kV Power Line Project, a national key project, is a symbol of the spirit of "Patriotism Emulation", a specific product of the emulation movement "Promoting the development of synchronous and modern infrastructure; practicing thrift and fighting waste" launched by the Prime Minister.

Pho Chu tich Tong Lien doan Lao dong Viet Nam Phan Van Anh nhan manh, thanh cong cua phong trao thi dua tai du an la ket qua cua su doan ket, trach nhiem cua tung doan vien, nguoi lao dong hoi tu thanh mot khoi thong nhat. Anh: Tuyet Lan
Vice President of the Vietnam General Confederation of Labor Phan Van Anh emphasized that the success of the emulation movement at the project is the result of the solidarity and responsibility of each union member and employee converging into a unified bloc. Photo: Tuyet Lan

According to the Vice President of the Vietnam General Confederation of Labor, this is a project jointly launched by the Vietnam General Confederation of Labor and EVN with the theme: "Three pioneers - Two responsibilities". The emulation movement at construction sites has become an inspirational flame, connecting the will of tens of thousands of cadres, engineers, and workers, fostering the spirit of solidarity and determination of workers in the common aspiration of "Completing as soon as possible, safest, most effectively".

The Vietnam General Confederation of Labor always accompanies the electricity industry in launching an emulation movement to promote initiatives, improve labor productivity, care for and protect the rights of union members and workers. Trade unions at all levels in the industry were present at every important moment of the project. Since the start of construction, through the arduous days of hot weather or storms, when each group of workers had to stay in high hills, wade in the wind and rain to build poles and pull ropes, until the entire line was energized today" - Mr. Phan Van Anh emphasized.

Ba Ha Thi Nga - Uy vien Trung uong Dang, Pho chu tich UBTW Mat tran To quoc Viet Nam trao qua tai buoi le. Anh: Tuyet Lan

Ms. Ha Thi Nga - Member of the Party Central Committee, Vice President of the Central Committee of the Vietnam Fatherland Front presented gifts at the ceremony. Photo: Tuyet Lan

According to Mr. Phan Van Anh, the Trade Unions at all levels have organized more than 100 visits, encouragement, and gift giving to workers at the construction site, including many "Union Meals" right at the construction site. The timely gifts of encouragement have increased spiritual strength, helping the brothers and sisters "overcome the sun, overcome the rain" to soon complete the project ahead of schedule, ensuring absolute safety, quality and technique, in accordance with the direction of the Prime Minister.

Cat bang khanh thanh du an Duong day 500kV Lao Cai - Vinh Yen. Anh: Tuyet Lan
Cut the ribbon to inaugurate the Lao Cai - Vinh Yen 500kV Power Line project. Photo: Tuyet Lan
Tuyết Lan
RELATED NEWS

Lao Cai - Vinh Yen 500kV Power Line Project Powered 8 Months Ahead of schedule

|

The Lao Cai - Vinh Yen 500kV Power Line project has officially been successfully energized, 8 months ahead of schedule.

Another contractor to destroy forests to construct the 500kV Lao Cai - Vinh Yen line was fined

|

Lao Cai - The People's Committee of Thac Ba commune has just fined Dien 2 Construction and Installation Company Limited for destroying forests to construct the 500kV Lao Cai - Vinh Yen line.

Explaining why the National Assembly has not amended the Land Law at the 10th Session

|

The reason for not amending the Land Law immediately is the need for full and comprehensive assessments. The comprehensive amendment of the law will be studied in the coming time.

Secretary of the Hanoi Party Committee: "Must be determined to strictly implement the direction of General Secretary To Lam"

|

The Secretary of the Hanoi Party Committee said that the capital will be determined to solve and fundamentally overcome the situation of traffic congestion, air pollution, and pollution of rivers.

The fate ship and 8 people still lost in the middle of the ocean

|

Gia Lai - After 20 days of no news, fishing boats and 8 fishermen are still lost in the open sea, leaving behind tarrying roofs and hopeless concerns.

"Lanterns" move a house built by mistake on someone else's land back to the correct location

|

HCMC - In Chanh Hiep ward, the "genie" is moving a house that was mistakenly built on someone else's land back to the correct land location.

Israel launches 31 airstrikes in Lebanon despite ceasefire agreement

|

Many casualties after Israeli airstrikes in southern Lebanon, threatening a fragile ceasefire in the region.

Man dies in temporary house fire in Ho Chi Minh City

|

HCMC - On October 17, a fire broke out at a temporary house in Chau Pha commune (HCMC), killing one person.

Lao Cai - Vinh Yen 500kV Power Line Project Powered 8 Months Ahead of schedule

Thạch Lam |

The Lao Cai - Vinh Yen 500kV Power Line project has officially been successfully energized, 8 months ahead of schedule.

Another contractor to destroy forests to construct the 500kV Lao Cai - Vinh Yen line was fined

Đinh Đại |

Lao Cai - The People's Committee of Thac Ba commune has just fined Dien 2 Construction and Installation Company Limited for destroying forests to construct the 500kV Lao Cai - Vinh Yen line.

Thêm vụ tai nạn chết người tại dự án đường dây 500kV Lào Cai - Vĩnh Yên

Văn Đức |

Chưa đầy một tháng, tại công trình đường dây 500kV Lào Cai - Vĩnh Yên lại xảy ra vụ tai nạn lao động chết người.