Road worth more than 1,300 billion VND in Hanoi is being paved with asphalt, preparing to open to traffic

SÓNG HỮU |

Hanoi - Ring Road 2.5, Dam Hong - National Highway 1A section is being paved with asphalt on the entire route, preparing for technical traffic opening on February 10.

According to Lao Dong reporters' records, nearly 9 months after the restart of construction, the Ring Road 2.5 project, Dam Hong - National Highway 1A section, is entering the final completion phase of the final items.

Mr. Dinh Van Huynh (representative of the supervision consulting unit) said that the Ring Road 2.5 project, Dam Hong - National Highway 1A section, is divided into 5 main bidding packages.

At this time, contractors are implementing completion work such as asphalt concrete pavement, green trees, lighting systems, electricity and water items...

From 10 PM on February 5th to the morning of February 6th, many machines and workers were mobilized to deploy the asphalt paving item on the entire route.

It is expected that by February 7, the asphalt paving item will be completed.

a
a
a
Machinery and workers are mobilized to asphalt the road surface of the Ring Road 2.5 project, Dam Hong - National Highway 1A section. Photo: Song Huu

Mr. Dinh Van Huynh said that according to the plan, the road will be technically opened to traffic on February 10th, ensuring synchronous connection with the technical opening plan of the Ring Road 2.5 - Giai Phong intersection tunnel project, serving people to travel to welcome the Binh Ngo Lunar New Year.

No later than March 31, 2026, the project will complete all items, ensuring synchronization and meeting the conditions for handover and commissioning according to regulations.

a
A section has been asphalted. The lighting system and green trees on the route are also being completed. Photo: Song Huu
a
Workers overnight construct items of the project. Photo: Song Huu
a
L3 bridge across the Lu River, an important item of the Ring Road 2.5 project, Dam Hong - National Highway 1A section. Photo: Song Huu
a
The bridge deck concrete paving item is being implemented by the contractor. Photo: Song Huu

Informing Lao Dong Newspaper, a representative of Hoang Mai - Hanoi Co., Ltd. (the project enterprise) said that up to this point, the site clearance of the project has basically been completed, only 1 household in Dinh Cong ward has not demolished the encroaching boundary construction.

Currently, the project enterprise is actively and proactively coordinating with Dinh Cong Ward People's Committee and this household to soon agree on a plan to return the site for the project.

a
a
a
It is expected that on February 7, the asphalt paving item will be completed. Photo: Song Huu

The Ring Road 2.5 project, Dam Hong - National Highway 1A section, is invested in the form of a BT (build - transfer) contract with a length of 1.6km, with a total investment of about 1,317 billion VND.

The project started in 2014, was expected to be completed in 2017 but was delayed.

By 2020, the project was temporarily suspended when it had only reached about 40% of the workload. The reason was due to problems in site clearance and extension of the BT contract appendix.

At the end of May 2025, the Ring Road 2.5 construction project, Dam Hong - National Highway 1A section, was restarted after about 5 years of suspension.

SÓNG HỮU
RELATED NEWS

Ring Road 2.5 Project: More than 30 households receiving compensation from 2003 have handed over land

|

Hanoi - More than 30 households receiving compensation from 2003 have moved assets and belongings to hand over land for the Ring Road 2.5 project, Nguyen Trai - Dam Hong section.

Hanoi Ring Road 2.5: Construction overnight, will be open to traffic at the end of January

|

Hanoi - Contractors are urgently constructing day and night to complete Ring Road 2.5, Dam Hong - National Highway 1A section by the end of January 2026.

Ho Chi Minh City names Pham Khac street in the city center

|

Ho Chi Minh City - The approximately 300m long road connecting Nguyen Thi Minh Khai street with Nguyen Dinh Chieu street is officially named after Pham Khac.

Nhan Dan Newspaper launches MV "Song From A Secret Garden – Secret Garden in Vietnam" promoting Vietnam tourism

|

On the morning of February 6th, Nhan Dan Newspaper in coordination with IB Group Vietnam organized the launch of the music video "Song From A Secret Garden – Secret Garden in Vietnam", recording the performance of the Secret Garden band at famous landmarks in Ninh Binh province.

Reformatory school for children who violate the law and the inner world

|

Behind the closed walls of the reform school is the daily life of children who have fallen and violated the law.

Tan Son Nhat airport is expected to welcome a record 165,000 passengers/day during the Binh Ngo Tet holiday

|

Ho Chi Minh City - Forecast that the number of passengers through Tan Son Nhat airport will reach a record of 165,000 passengers/day, the Ho Chi Minh City Department of Construction requests units to coordinate regulation.

US does not rule out military measures if diplomacy with Iran becomes deadlocked

|

The US affirms diplomatic priority in approaching Iran, but warns that military options remain open if upcoming negotiations do not reach an agreement.

Mr. Nguyen Van Dung elected Vice Chairman of Ho Chi Minh City People's Council

|

Ho Chi Minh City - After more than 2 years holding the position of Vice Chairman of Ho Chi Minh City People's Committee, Mr. Nguyen Van Dung was re-elected by the City People's Council as Vice Chairman of Ho Chi Minh City People's Council.

Phường Cầu Giấy cảm ơn người dân di chuyển mộ phục vụ dự án Vành đai 2,5

Đặng Tiến |

Hà Nội - UBND phường Cầu Giấy tri ân người dân đã đồng thuận di chuyển 359 phần mộ, góp phần đẩy nhanh tiến độ dự án đường Vành đai 2,5.

Ring Road 2.5 Project: More than 30 households receiving compensation from 2003 have handed over land

SÓNG HỮU |

Hanoi - More than 30 households receiving compensation from 2003 have moved assets and belongings to hand over land for the Ring Road 2.5 project, Nguyen Trai - Dam Hong section.

Hanoi Ring Road 2.5: Construction overnight, will be open to traffic at the end of January

SÓNG HỮU |

Hanoi - Contractors are urgently constructing day and night to complete Ring Road 2.5, Dam Hong - National Highway 1A section by the end of January 2026.