Trillion-VND road in Hanoi has been technically opened to traffic but still has site clearance problems

SÓNG HỮU |

Hanoi - Ring Road 2.5, Dam Hong section - National Highway 1A, technically opened to traffic 2 months ago, but so far site clearance has not been completed.

The investment project to build Ring Road 2.5, Dam Hong - National Highway 1A section was started in 2014 with a length of 1.6km, total investment of about 1,317 billion VND under the BT (build - transfer) contract form, expected to be completed in 2017.

However, the project progress was delayed due to problems in site clearance and waiting for BT contract extension.

By 2020, when only about 40% of the workload was completed, the project had to be temporarily suspended.

After 5 years of suspension, by the end of May 2025, Hoang Mai - Hanoi Construction Investment Co., Ltd. (project enterprise) will organize the Groundbreaking Ceremony for the 2.5 Ring Road project, Dam Hong - National Highway 1A section.

s
Ring Road 2.5, Dam Hong section - National Highway 1A technically opened to traffic on the 10th. 2. Photo: Song Huu

The Hanoi Traffic Construction Investment Project Management Board said that the section from Km0+320 (lane 192 Le Trong Tan) to Km1+600 (adjacent to the Ring Road 2.5 and Giai Phong tunnels) with a length of 1,280m has been technically opened to traffic from February 10, 2026.

For the remaining items, the investor/project enterprise continues to deploy construction to complete the project.

Currently, the Ring Road 2.5 project, Dam Hong - National Highway 1A section, still has problems in site clearance.

Specifically, in Dinh Cong ward, there are still 2 cases of encroachment on the red line boundary that have not been cleared (located in the sidewalk construction section).

Currently, the investor/project enterprise is coordinating with Dinh Cong Ward People's Committee to implement it.

s
Mr. N.D. V's household (Dinh Cong ward) has an area of about 29m2 that has not been demolished for site handover. Photo: Song Huu

In Phuong Liet ward, there are still 2 households with an area of 59.3m2 (1 household recovered 6.1m2/12.98m2 and 1 household recovered 53.2m2/110.9m2) belonging to the project of the Housing and Urban Development Investment Corporation located within the sidewalk area of the Ring Road 2.5 project that have not carried out site clearance work.

On January 27, 2026, Phuong Liet Ward People's Committee issued Document No. 216/UBND-BQLDA to the Housing and Urban Development Investment Corporation to coordinate and sign land clearance contracts for the above 2 households.

s
Business activities are still taking place at the location where land is recovered, recorded on March 22. Photo: Song Huu

The Hanoi Traffic Construction Investment Project Management Board proposed that the City People's Committee consider and give opinions directing the Housing and Urban Development Investment Corporation to sign a land clearance contract with Phuong Liet Ward People's Committee for 2 households with an area of 59.3m2 located within the boundary of Ring Road 2.5.

Dinh Cong Ward People's Committee coordinates with relevant functional units to definitively handle the remaining contents for cases of re-encroachment within the project scope.

SÓNG HỮU
RELATED NEWS

Hanoi removes site clearance, accelerates construction of Ring Road 2.5 - Linh Nam

|

Hanoi accelerates site clearance for Ring Road 2.5 - Linh Nam project, but many obstacles put the progress at risk of slowing down.

Ring Road 2.5 Project: Land recovery for households that do not comply with handover is about to be enforced

|

Hanoi - By March 30, if households do not comply with handing over land for the Ring Road 2.5 project, Vinh Hung ward will enforce land recovery according to regulations.

Request Phuong Liet and Dinh Cong wards to definitively handle the existence of site clearance for Ring Road 2.5

|

Hanoi requests Phuong Liet and Dinh Cong wards to urgently handle the existing problems in site clearance for the Ring Road 2.5 Project (Dam Hong - National Highway 1A section).

1.6km of Ring Road 2.5 risks missing handover deadline in March 2026

|

Hanoi - If the relevant parties do not promptly remove obstacles in site clearance, 1.6km of Ring Road 2.5 will miss the handover deadline in March 2026.

Fire engulfs truck carrying construction materials on elevated Ring Road 3

|

Hanoi - A truck carrying construction materials was traveling on Ring Road 3 elevated (section passing through Nguyen Xien) when it suddenly caught fire.

Khanh Hoa mobilizes and appoints many key officials

|

Khanh Hoa - The locality has just announced decisions on personnel work, transferring and appointing many officials to hold key positions in agencies and units.

Director of the Department of Cinema: Many pirated movie websites exist thanks to advertising revenue

|

While Vietnamese cinema continuously records positive signals in terms of quality, revenue and number of theater audiences, the problem of pirated movies is still a difficult problem.

Mobilizing excavators to clear firewood and garbage at Hai Tien beach after Lao Dong Newspaper's reflection

|

Thanh Hoa - After Lao Dong Newspaper reflected the situation of firewood and garbage overflowing like "pillars" at Hai Tien beach, local authorities mobilized machinery to collect it.

Hanoi removes site clearance, accelerates construction of Ring Road 2.5 - Linh Nam

Minh Hạnh |

Hanoi accelerates site clearance for Ring Road 2.5 - Linh Nam project, but many obstacles put the progress at risk of slowing down.

Ring Road 2.5 Project: Land recovery for households that do not comply with handover is about to be enforced

SÓNG HỮU |

Hanoi - By March 30, if households do not comply with handing over land for the Ring Road 2.5 project, Vinh Hung ward will enforce land recovery according to regulations.

Request Phuong Liet and Dinh Cong wards to definitively handle the existence of site clearance for Ring Road 2.5

SÓNG HỮU |

Hanoi requests Phuong Liet and Dinh Cong wards to urgently handle the existing problems in site clearance for the Ring Road 2.5 Project (Dam Hong - National Highway 1A section).

1.6km of Ring Road 2.5 risks missing handover deadline in March 2026

HỮU CHÁNH |

Hanoi - If the relevant parties do not promptly remove obstacles in site clearance, 1.6km of Ring Road 2.5 will miss the handover deadline in March 2026.