Approved 9.1 billion VND to salvage Phong Chau bridge and vehicles

Tô Công |

Phu Tho - The Vietnam Road Administration (Ministry of Transport) has approved spending more than 9 billion VND to salvage the collapsed Phong Chau bridge and the vehicles involved.

Accordingly, the project to overcome the consequences of natural disasters at Phong Chau bridge will be implemented under an emergency order with a provisional budget of more than 9.1 billion VND from the State budget, spent on salvaging the bridge and sunken vehicles, and at the same time spent on traffic diversion, ensuring traffic, and arranging staff on duty.

The Department of Transport of Phu Tho province is the agency assigned by the Vietnam Road Administration to implement the project, and at the same time carry out procedures for appointing construction contractors and managing project progress and quality.

Tung phan ket cau cua cau Phong Chau bi sap se duoc cat, truc vot len bo. Anh: To Cong.
Each structural part of the collapsed Phong Chau bridge will be cut and salvaged to shore. Photo: To Cong.

The project will immediately salvage sunken vehicles located outside the steel truss span, bring them closer to shore and lift them into the staging area using a 150-ton specialized crane.

For vehicles stuck in the steel truss that cannot be salvaged immediately, the construction unit will use a 400-ton crane on shore and 2 ships equipped with salvage equipment to lift the steel truss out of the water and cut each span. The tugboat will bring each span of the steel truss to shore and use a specialized 150-ton crane on shore to lift, lift, and place it in the staging area. During the process of cutting the steel truss spans, the construction unit will also simultaneously take the vehicles stuck inside out and tow them to shore.

Mot chiec thung xe tai duoc cau len bo. Anh: To Cong.
A truck bed is lifted ashore. Photo: To Cong.

With steel truss spans and vehicles buried deep under layers of sand and silt, the construction unit will use hoses and suction to remove the sand and silt before salvage.

For the concrete bridge deck, piers, piles, and submerged abutments, the contractor will use a 400-ton crane on shore and two ships equipped with salvage equipment to lift them to the water surface. The concrete will be demolished by an excavator equipped with a concrete chisel on board.

Quan doi da ha thuy mot so nhip cau phao de thu nghiem. Anh: To Cong.
The army has launched several pontoon bridge spans for testing. Photo: To Cong.

As for the collapsed T7 bridge pier, it cannot be demolished or towed, so the Vietnam Road Administration has not yet calculated the cost of handling it. For now, the authorities will put up buoys to warn of waterway traffic safety, and when the water recedes, they will survey and find a way to demolish it.

Previously, on September 9, Phong Chau bridge across the Red River connecting Tam Nong and Lam Thao districts of Phu Tho province collapsed, pulling down pillar T7 and collapsing two main spans of the bridge (spans 6 and 7), causing many vehicles to fall into the river, with 8 victims currently identified as missing.

Cong tac tim kiem nan nhan mat tich vu cau Phong Chau duoc trien khai ca ngay lan dem va tren mot doan luu vuc song dai hang chuc km. Anh: To Cong.
The search for the missing victims of the Phong Chau bridge incident was carried out day and night and over a stretch of river basin tens of kilometers long. Photo: To Cong.

After many days of search and rescue at the site of the bridge collapse and dozens of kilometers downstream of the Red River, up to now, the functional forces of Phu Tho province have recovered, identified the victims and handed over 4 bodies to the families for burial.

Meanwhile, the military agency is urgently completing the reinforcement of the two river banks (about 400m downstream from the collapsed bridge), moving towards installing a temporary pontoon bridge to replace Phong Chau bridge, serving the travel needs of the people.

Tô Công
TIN LIÊN QUAN

Thêm 1 nạn nhân vụ sập cầu Phong Châu được tìm thấy

Tô Công |

Phú Thọ - Thi thể được phát hiện trên sông Hồng sáng ngày 23.9 đã được xác định là 1 trong số các nạn nhân mất tích vụ sập cầu Phong Châu.

Bắt đầu trục vớt phương tiện và phần cầu Phong Châu bị sập

Tô Công |

Phú Thọ - Các lực lượng chức năng đang phá dỡ, trục vớt các phần của cầu Phong Châu bị sập, từng bước đưa các phương tiện còn nằm dưới sông lên bờ.

Thử nghiệm nhịp cầu phao đầu tiên thay cầu Phong Châu sập

Tô Công |

Phú Thọ - Quân đội đã hạ thủy những nhịp cầu phao đầu tiên để thử nghiệm trước khi chính thức lắp đặt cầu phao hoàn chỉnh tạm thay thế cầu Phong Châu bị sập.

Rác chất thành "núi", tràn ra đường gom Đại lộ Thăng Long

Tô Thế |

Rác thải sinh hoạt, rác thải xây dựng bị đổ trộm la liệt dọc theo tuyến đường gom Đại lộ Thăng Long (Hà Nội).

Trung Quốc công bố loạt chính sách mới thúc đẩy kinh tế

Ngọc Vân |

Ngày 24.9, Trung Quốc công bố một loạt chính sách mới nhằm thúc đẩy nền kinh tế, bao gồm cắt giảm lãi suất thế chấp và tỉ lệ dự trữ bắt buộc.

Gặp khó vì chưa được phê duyệt đề án vị trí việc làm

Bảo Hân |

Các cơ sở giáo dục nghề nghiệp thuộc hệ thống công đoàn gặp nhiều khó khăn, vướng mắc do chưa được phê duyệt đề án vị trí việc làm.

Lượng rác khổng lồ trôi nổi trên vịnh Hạ Long

Nguyễn Hùng |

Quảng Ninh - Sẽ mất rất nhiều thời gian để xử lý lượng rác khổng lồ tràn ra vịnh Hạ Long, chủ yếu từ các khu nuôi trồng thủy sản bị bão số 3 đánh tan tành.

Cựu sếp Nhà Xuất bản Giáo dục nhận hối lộ đều đặn

Việt Dũng |

Suốt quá trình tạo điều kiện cho doanh nghiệp trúng các gói thầu tổng trị giá cả nghìn tỉ, hàng năm ông Nguyễn Đức Thái nhận hối lộ tới 20 tỉ của nữ đối tác.

Another victim of Phong Chau bridge collapse found

Tô Công |

Phu Tho - The body discovered on the Red River on the morning of September 23 has been identified as one of the missing victims of the Phong Chau bridge collapse.

Started salvaging vehicles and collapsed Phong Chau bridge

Tô Công |

Phu Tho - Authorities are demolishing and salvaging parts of the collapsed Phong Chau bridge, gradually bringing vehicles still in the river to shore.

Testing the first pontoon bridge span to replace the collapsed Phong Chau bridge

Tô Công |

Phu Tho - The army has launched the first spans of the pontoon bridge for testing before officially installing the complete pontoon bridge to temporarily replace the collapsed Phong Chau bridge.