Nearly 10,000 workers are working at the Long Thanh airport project

HÀ ANH CHIẾN |

Dong Nai - At the Long Thanh airport project site, nearly 10,000 experts, engineers, workers, and nearly 3,000 equipment and machinery are under construction.

Accelerating construction of the "sprint" phase

According to the reporter of Lao Dong Newspaper, these days at the Long Thanh airport project site in Binh Son commune, Long Thanh district, Dong Nai province, despite the peak of the hot and dry weather in the South, thousands of officers and workers are still speeding up the construction of the "sprint" phase.

Thi cong giai doan nuoc rut o du an san bay Long Thanh. Anh: HAC
Construction of the final stage of the Long Thanh airport project. Photo: HAC

On March 24, information from Vietnam Airports Corporation (ACV) - the investor of the Long Thanh airport component project 3 phase 1 - said that ACV and contractors have coordinated to review and agree on solutions to increase people, increase machinery, increase materials, and subcontractors to shorten progress.

Up to now, at the construction site, construction units have mobilized hundreds of construction teams with nearly 10,000 experts, engineers, workers, laborers and nearly 3,000 construction equipment to speed up the construction progress with the goal of basically completing the construction part before December 31, 2025 to celebrate the 14th National Congress of the Party; 80th Anniversary of the National Day of the Socialist Republic of Vietnam; 50th Anniversary of the Day of the complete Liberation of the South and National Reunification.

Progress of the main packages, for package 4.6 - Runway works, taxiways, aircraft parking lots... started in August 2023 and according to the contract schedule to be completed in July 2025.

However, the progress has been adjusted to complete and technically exploit the runway and taxiway before April 30, 2025 and is installing equipment and materials for the ILS/DME accuracy landing support system.

Goi thau 5.10 nha ga hanh khach san bay Long Thanh la duong gantt tien do cua toan bo du an. Anh: HAC
Package 5.10 of Long Thanh airport passenger terminal is the gant road for the entire project. Photo: HAC

For package 5.10 - The passenger terminal project is considered the heart of the Long Thanh airport project, the general progress of the entire project, the contractor is the Vietur consortium. The project started in July 2023, with completion scheduled for November 31, 2026 (39 months). However, the adjusted progress is to basically complete the construction before December 31, 2025.

Currently, this package has completed the construction of the underground reinforced concrete structure, floors 1, 2, 3, 4.

Contractors are constructing such as: completing the paving, installing the steel bridge connection, constructing the glass wall, constructing the water supply system, air conditioning, electrical system construction, fire prevention and fighting. The installation of the terminal equipment system is also under construction: passenger pipeline bridge, luggage handling area, aircraft parking lot...

Basically complete all construction of Long Thanh airport before December 31, 2025

Package 6.12 - the traffic project connecting route 1 and route 2 is expected to technically open to traffic on route 1 on April 30, 2025, complete route 2 in July 2025, complete the intersections, accept all, and put into use on September 2, 2025 (3 months ahead of schedule).

Other packages include: Package 4.7 - Aircraft parking lot project and other works; Package 4.8 - Inner Port Transport Project and Airport Infrastructure; Package 4.9 - Aircraft fuel supply system; Package 11.5 - Garage is also being accelerated by ACV.

ACV quyet tam hoan thanh co ban cong tac xay dung san bay Long Thanh trong nam 2025. Anh: HAC
ACV is determined to basically complete the construction of Long Thanh airport in 2025. Photo: HAC

According to ACV, all packages of component project 3 - Long Thanh airport phase 1 are in the process of implementation. ACV and contractors strive to focus all resources to basically complete the entire construction before December 31, 2025.

Mr. Duong Quang Dien - Permanent Deputy Director of the Long Thanh Airport Project Management Board - said: "In 2025, we are determined to basically complete the construction work of the Long Thanh Airport Project Phase 1".

HÀ ANH CHIẾN
RELATED NEWS

Prime Minister inspects progress of Long Thanh airport project

|

Dong Nai - Prime Minister Pham Minh Chinh and the Central working delegation inspect the progress of the Long Thanh airport project.

New proposal for railway line connecting to Long Thanh airport

|

The Ministry of Construction has just reported on the railway line connecting Long Thanh airport and Tan Son Nhat airport.

Expanding nearly 40km of road in Dong Nai connecting Long Thanh airport

|

Dong Nai - The project to upgrade and expand DT 773 route, nearly 40km long, passes through 3 districts of the province connecting Ho Chi Minh City Ring Road 4 and Long Thanh airport.

Assets increase sharply, billionaire Pham Nhat Vuong firmly holds the second richest position in Southeast Asia

|

With assets increasing by 2.8 billion USD, Mr. Pham Nhat Vuong, Chairman of Vingroup Corporation, rose to 2nd place in the list of the richest people in Southeast Asia.

Teachers point out inadequacies in regulations on seniority allowances for teachers

|

Many teachers have reported that their seniority allowances were cut when they moved to support positions, even though they have been teaching for decades, causing disadvantages when calculating pensions.

Young people in the cancer spinout

|

Increasingly young cancer causes many young people to face the same worries about illness, treatment costs and disruptions in studying, work, and the future.

Three scenarios that can change world gold prices in 2026

|

Gold prices still have room to increase next year, according to many experts.

357 households that have not yet handed over the land to build Ring Road 1 will be forced to work overnight

|

To ensure the progress of site clearance for Ring Road 1, Lang Ward proposed that the Hanoi People's Committee carry out a shortened process.

Prime Minister inspects progress of Long Thanh airport project

HÀ ANH CHIẾN |

Dong Nai - Prime Minister Pham Minh Chinh and the Central working delegation inspect the progress of the Long Thanh airport project.

New proposal for railway line connecting to Long Thanh airport

Xuyên Đông |

The Ministry of Construction has just reported on the railway line connecting Long Thanh airport and Tan Son Nhat airport.

Expanding nearly 40km of road in Dong Nai connecting Long Thanh airport

HÀ ANH CHIẾN |

Dong Nai - The project to upgrade and expand DT 773 route, nearly 40km long, passes through 3 districts of the province connecting Ho Chi Minh City Ring Road 4 and Long Thanh airport.