Urgently constructing the 500 kV Lao Cai - Vinh Yen transmission line project before the rainy season

Đinh Đại |

Lao Cai - Faced with the pressure of the upcoming storm season, contractors are speeding up the installation of steel poles for the 500kV Lao Cai - Vinh Yen transmission line to ensure the set progress.

The 500 kV Lao Cai - Vinh Yen transmission line project has a total length of about 229.95km/468 pole locations, passing through the two provinces of Lao Cai and Phu Tho.

The investor is Vietnam Electricity Group (EVN), the investor's representative is Power Project Management Board 1 (EVNPMB1), with a total capital of more than VND 7,410 billion.

The project started construction in Lao Cai province on March 30, 2025. According to the direction of the Prime Minister, the project must be completed and energized before August 19, 2025.

Nhieu vi tri cot thuoc du an duong day 500 kV Lao Cai - Vinh Yen da hoan thanh lap dat. Anh: Dinh Dai
Many pole locations of the 500 kV Lao Cai - Vinh Yen transmission line project have been completed. Photo: Dinh Dai

In Lao Cai province, the line is located in 13 communes: Xuan Quang, Thuong Ha, Xuan Hoa, Bao Yen, Phuc Khanh (old Lao Cai province); Khanh Hoa, Tan Linh, Lam Thuong, Luc Yen, Muong Lai, Cam Nhan, Yen Thanh, Thac Ba (old Yen Bai province).

The length of the route is about 139.66 km with 273 pillar locations (old Lao Cai has 100 locations, Yen Bai has 173 locations), and 132 anchorages.

Day la du an trong diem quoc gia, se dong dien truoc ngay 19.8.2025 theo chi dao cua Thu tuong Chinh phu. Anh: Dinh Dai
The project will be energized before August 19, 2025 according to the direction of the Prime Minister. Photo: Dinh Dai

On July 5, according to the reporter of Lao Dong Newspaper in communes such as Xuan Quang, Thuong Ha... of the new Lao Cai province, many additional pillars have now been completed, while others are in the process of making foundations to implement construction.

At the construction site, many machines, equipment and parts of the electric poles have been transported concentrated at the pole construction site to serve the construction process quickly.

Vi tri cot mong tru dien dang trong qua trinh lap dat. Anh: Dinh Dai
The location of the electric pole foundation is in the process of installation. Photo: Dinh Dai

Mr. Nguyen Van Minh (residing in Xuan Quang commune, Lao Cai new province) shared: "The Lao Cai - Vinh Yen transmission line project is a national key project. The early completion of construction to energize has a big role in ensuring energy security, serving production activities and industrial parks. Therefore, people are also looking forward to the day the project officially takes effect".

Khu vuc Tram bien ap, truyen tai dien dang trong qua trinh thi cong. Anh: Dinh Dai
The transformer station and power transmission station area is under construction. Photo: Dinh Dai

According to research, as of early July, the construction has completed digging the foundation at 259/273 locations, reaching 94.87%; casting the foundation at 243/273 locations, reaching 89.01%; erecting columns at 90/273 locations, reaching 32.96%; pulling the 01/132 cable about the anchor, reaching 0.75%.

Regarding site clearance, the compensation, support, and resettlement plan has been approved officially and 273/273 locations have been handed over.

Of which, 5/13 communes have completed payment and issued a decision to reclaim land; 3/13 communes have issued a decision to reclaim land, and have not yet completed payment to households; 5/13 communes have completed payment but have not yet issued a decision to reclaim land.

According to the investor's report, the packages in Lao Cai province are being implemented the fastest on the entire route. Faced with the pressure of the upcoming rainy season, the construction unit is speeding up the installation of steel poles for the 500kV Lao Cai - Vinh Yen transmission line to keep up with progress and ensure the safety of key national projects.

Cong tac thi cong dang duoc day manh trien khai de hoan thanh dung ke hoach. Anh: Dinh Dai
Construction work is being accelerated to complete on schedule. Photo: Dinh Dai

Meanwhile, according to Mr. Ngo Hanh Phuc, Vice Chairman of Lao Cai Provincial People's Committee, agencies, units and localities are urgently completing the organization of project site clearance; establishing a site clearance council to avoid affecting the overall progress of the project.

Recently, the Chairman of Lao Cai Provincial People's Committee established 3 Working Groups to clear the site of the Lao Cai - Vinh Yen 500kV transmission line project (the section passing through Lao Cai province).

The unit is responsible for checking the progress and site clearance situation after organizing local authorities at 2 levels (colluding and handing over documents on compensation and site clearance; resettlement support...).

At the same time, grasp the difficulties and problems in the process of implementing land procedures, compensation, site clearance, and guide localities to resolve them.

Đinh Đại
TIN LIÊN QUAN

Lao Cai Trade Union visits and presents support funds to the families of the deceased workers

|

Lao Cai - On the morning of July 5, a working delegation of the Provincial Federation of Labor visited, expressed condolences and presented support funds to the families of the deceased workers.

List of Secretaries and Chairmen of 99 communes and wards of Lao Cai province after the merger

|

Lao Cai - The list of Party Committee Secretaries and Chairmen of People's Committees of 99 communes and wards after the arrangement and merger has just been updated by the province.

Racing against storms to laid foundations for the 500kV Lao Cai - Vinh Yen power line

|

Despite the sunny weather, unusual rain, landslides and flash floods in Lao Cai and Yen Bai provinces, thousands of workers are still day and night, working hard at the Lao Cai - Vinh Yen 500kV transmission line project site.

10th grade valedictorian in Hanoi with 29.25 points: Less attending extra classes, waking up at 5am to study

|

student Be Ngoc Thuy Nhi, class 9A5, Van Ho Secondary School, Hai Ba Trung, is the valedictorian of the 10th grade entrance exam in Hanoi this year with a total score of 29.25.

Tickets to watch the VTV Cup volleyball final are being sold for 5 times more than the original price

|

Before the final match of the VTV Cup 2025, tickets are being sold at prices 5 times higher than the original price.

Vietnam U21 Women's Volleyball Team Wins 6th place VTV Cup 2025

|

On the afternoon of July 5, the U21 Vietnam women's volleyball team lost to U21 Thailand with a score of 1-3, thereby winning 6th place in the VTV Cup 2025.

Gold price today 5.7: Unexpected increase

|

Gold price today 5.7: When domestic gold is unchanged, world gold reverses and recovers.

Japan warns super earthquake and Tsunami could take 300,000 lives

|

Japan plans to respond to the risk of super earthquakes and sunsones at the Nankai drain, with the worst case scenario could be 300,000 people dead.

Lao Cai Trade Union visits and presents support funds to the families of the deceased workers

Huyền Thúy - Mạnh Hùng |

Lao Cai - On the morning of July 5, a working delegation of the Provincial Federation of Labor visited, expressed condolences and presented support funds to the families of the deceased workers.

List of Secretaries and Chairmen of 99 communes and wards of Lao Cai province after the merger

Đinh Đại |

Lao Cai - The list of Party Committee Secretaries and Chairmen of People's Committees of 99 communes and wards after the arrangement and merger has just been updated by the province.

Racing against storms to laid foundations for the 500kV Lao Cai - Vinh Yen power line

Nhóm PV |

Despite the sunny weather, unusual rain, landslides and flash floods in Lao Cai and Yen Bai provinces, thousands of workers are still day and night, working hard at the Lao Cai - Vinh Yen 500kV transmission line project site.