Extension until the end of the year for a road built for more than 6 years but not completed in Ca Mau

NHẬT HỒ |

The project to upgrade and expand the Ninh Quoi - Ngan Dua road (DT978) was extended to 2026 but has not been completed after more than 6 years of construction.

On March 20, the Office of the People's Committee of Ca Mau province said that the Provincial People's Committee has decided to adjust the implementation time of the Ninh Quoi - Ngan Dua road upgrade and expansion project, extending it to 2026.

The project implementation time is adjusted from the 2019–2025 period to 2019–2026. Previously, the project had been adjusted many times through decisions and documents of the Bac Lieu Provincial People's Committee (old).

The project has a total investment of more than 271 billion VND, a length of about 10.9km, passing through Ninh Quoi and Hong Dan communes (Ca Mau province). The project is designed according to level IV plain road standards, design speed of 60km/h; road surface width of 7m, roadbed width of 9m, high-grade road surface structure A1, with drainage system and auxiliary works.

Đường Ninh Quới - Ngan Dừa vào mùa mưa khó qua lại, ảnh chụp năm 2021. Ảnh: Nhật Hồ.
Ninh Quoi - Ngan Dua road is difficult to cross in the rainy season, photo taken in 2021. Photo: Nhat Ho.

According to the Ca Mau Provincial Traffic Construction Project Management Board, to date, the project has completed over 91% of the construction volume; the contractor has completed the entire route and 4 bridges, and 1 bridge is still under construction.

The main reason for the slow progress is obstacles in site clearance work. Ca Mau Provincial People's Committee has requested relevant units to urgently review and thoroughly handle cases that have not been handed over land to soon complete the project.

Although it has reached more than 90% of the volume, many sections on the route are still not completed, causing difficulties for traffic. In the sunny season, the road surface is dusty; in the rainy season, many potholes and craters appear, water stagnates into large puddles, posing a potential risk of traffic unsafety, especially at night.

Đường Ninh Quới - Ngan Dừa đến nay vẫn chưa hoàn thành, ảnh chụp năm 2026. Ảnh: Nhật Hồ.
Ninh Quoi - Ngan Dua road has not been completed to date, Ca Mau extends until the end of 2026, photo taken in 2026. Photo: Nhat Ho.

Mr. Nguyen Van Ut, living along the route, said: "The Can Tho - Ca Mau expressway started construction in January 2023 and was completed by 2025, while this road has been built since 2019 and has not been completed yet, I don't know when it will be completed.

Notably, bridge 6000 (near the old Ninh Hoa Commune People's Committee headquarters) has not completed the access road, people have to cross a narrow temporary iron bridge, while the bridge abutment shows signs of subsidence, posing a potential risk of traffic unsafety.

The section from Ba Hien bridge to bridge 8000 in Hong Dan commune is a difficult area to travel to because the road surface is not complete and often damaged.

The prolonged construction has caused traffic connecting the center of Hong Dan, Ninh Thanh Loi, Vinh Loc communes with Quan Lo - Phung Hiep road, National Highway 1A to face many difficulties.

NHẬT HỒ
RELATED NEWS

Ca Mau strives to accelerate disbursement of public investment capital

|

Ca Mau province strengthens supervision and review of project progress to remove difficulties and obstacles, and promote disbursement of public investment capital right from the beginning of 2026.

Slow progress, resort project in Khanh Hoa gets land use extension

|

Khanh Hoa - Locality extends land use progress for Nha Trang Seahorse Resort & Spa resort project after this project is behind schedule.

Ca Mau invests trillions of VND to open a series of traffic routes connecting urban areas

|

Ca Mau approves investment policy for many large transport projects with a total capital of thousands of billions of VND, connecting main roads to expand urban development space.

Ho Chi Minh City considers and proposes disciplinary action against 7 party members

|

Ho Chi Minh City is considering and disciplining 7 party members for serious violations, of which 5 cases were expelled from the Party and proposed to expel 2 more people.

Middle East may lag 20 years behind due to Iran's unprecedented attack on Qatar

|

Iran's attacks on Qatar on March 18-19 caused heavy damage, disrupted LNG supplies and could cause the Middle East to decline for up to 20 years.

Motel fire in highland Tuyen Quang, nearly 100 tourists escaped

|

Tuyen Quang - At the time of the fire, 95 tourists were promptly supported to move to a safe place.

Announcing the list of elected delegates to the Hanoi People's Council

|

The list of 125 people elected as delegates to the Hanoi City People's Council of the XVII term 2026-2031 has been announced.

People whose lives are not brilliant, but make other people's light

|

Not everyone has a brilliant life. Some people choose to be quiet behind, becoming a fulcrum for others to shine.

Nhà Thiếu nhi ở Cà Mau làm hơn 10 năm vẫn còn dang dở

NHẬT HỒ |

Nhà Thiếu nhi tỉnh (cơ sở 2) tại Bạc Liêu thi công kéo dài hơn 10 năm, nhiều hạng mục dở dang, xuống cấp, trong khi hàng tỉ đồng tạm ứng vẫn chưa thu hồi.

Ca Mau strives to accelerate disbursement of public investment capital

NHẬT HỒ |

Ca Mau province strengthens supervision and review of project progress to remove difficulties and obstacles, and promote disbursement of public investment capital right from the beginning of 2026.

Slow progress, resort project in Khanh Hoa gets land use extension

Hữu Long |

Khanh Hoa - Locality extends land use progress for Nha Trang Seahorse Resort & Spa resort project after this project is behind schedule.

Ca Mau invests trillions of VND to open a series of traffic routes connecting urban areas

NHẬT HỒ |

Ca Mau approves investment policy for many large transport projects with a total capital of thousands of billions of VND, connecting main roads to expand urban development space.