Disbursement reached 6.7%, Hung Yen requests to accelerate project progress

Mai Hương |

Hung Yen - The Provincial People's Committee requests to accelerate the disbursement of public investment capital, remove obstacles and soon start the Nghi Xuyen culvert project.

On April 16, Mr. Lai Van Hoan - Vice Chairman of Hung Yen Provincial People's Committee - chaired a meeting to listen to the Construction Investment Project Management Board No. 1 report on the disbursement results of public investment capital in the first quarter of 2026, the second quarter plan and the progress of the Nghi Xuyen culvert construction project to drain water from the Cuu An River to the Red River.

According to the report, in 2026, the Board was assigned to be the investor of 61 projects, with a total investment of nearly 49,800 billion VND; of which 40 projects are under construction and 21 projects are in preparation.

Disbursed value in the first quarter reached 536.4 billion VND, equivalent to 6.7% of the year plan. For the Nghi Xuyen culvert project, the total investment of 250 billion VND from the provincial budget, is implementing surveys and drawing construction drawings, expected to be completed in May 2026, striving to start construction in the third quarter of 2026.

At the meeting, delegates clarified the causes of the problem, proposed solutions to remove obstacles, especially in site clearance, ensuring material sources and improving contractor capacity.

Phó Chủ tịch UBND tỉnh Lại Văn Hoàn phát biểu chỉ đạo tại cuộc họp. Ảnh: Tất Đạt
Vice Chairman of the Provincial People's Committee Lai Van Hoan delivered a directive speech at the meeting. Photo: Tat Dat

Concluding the meeting, Mr. Lai Van Hoan requested the Construction Investment Project Management Board No. 1 to operate decisively, closely monitor the progress of each project; closely coordinate with departments, branches, and localities to remove difficulties and accelerate site clearance.

Localities need to mobilize the entire political system, linking the responsibility of heads of communes and wards with the progress of site handover, considering this as a criterion for evaluating tasks.

The Project Management Board is required to urge contractors to perform "3 shifts, 4 teams", deploy immediately when there is site clearance, proactively source materials, handle technical problems; strengthen supervision, strictly handle violations of progress and quality. Relevant departments and branches shorten appraisal time, promptly announce materials prices close to the market, and advise on flexible operating mechanisms.

Regarding the Nghi Xuyen culvert project, Mr. Lai Van Hoan requested to urgently complete the dossier, accelerate surveys and designs, ensure progress, and closely coordinate with the locality to start construction soon.

Mai Hương
RELATED NEWS

Dong Nai hands over more than 71 hectares of land for the 200MW hydropower plant project

|

Dong Nai - Chairman of the Provincial People's Committee requests to remove site obstacles for the Tri An Hydropower Plant expansion project, report before April 20.

Investing more than 175 billion VND to build 10 resettlement areas for the Ninh Binh - Hai Phong Expressway Project

|

Ninh Binh - Nearly 340 households affected by the Ninh Binh - Hai Phong Expressway Project, the section passing through the old Ninh Binh province, have been arranged new accommodation in resettlement areas.

92.5 trillion VND project in Hanoi: Hundreds of people come to hear information about land acquisition

|

Hanoi - The work of land acquisition and site clearance for the Olympic Sports Urban Area project, with an investment of 925 trillion VND, is being actively implemented by communes.

People excitedly attend the Buddha bathing ceremony during the Chol Chnam Thmay Tet holiday

|

Ho Chi Minh City - Chôl Chnăm Thmây Tet at Candaransi Pagoda attracts a large number of people, highlighted by the Buddha bathing ritual and imbued with the identity of the Khmer people.

Terminating the operation of the National Traffic Safety Committee from June 1, 2026

|

The Prime Minister decided to terminate operations and dissolve the National Traffic Safety Committee and the Traffic Safety Boards of localities from June 1, 2026.

Case of teacher punishing 5 students for self-injecting needles in their hands: Test results have been available

|

Ho Chi Minh City - 5 students who were punished by teachers by self-injecting needles into their hands have blood counts within normal limits and are continuing to be monitored for their health.

Government directs inspection of the arrangement and assignment of deputy-level leaders

|

The Government requests inspection and supervision of legal regulations on arranging and assigning the number of deputy-level leaders according to regulations.

Trusting Lao Dong Newspaper to maintain its No. 1 position in protecting workers

|

Hanoi - At a working session with Lao Dong Newspaper on the morning of April 16, Chairman of the Vietnam General Confederation of Labor Nguyen Anh Tuan expressed his belief that Lao Dong Newspaper will continue to maintain its number 1 position in protecting workers.

Dự án gần 9.600 tỉ đồng ở Hà Nội: Nhiều hộ đang tháo dỡ công trình để bàn giao đất

SÓNG HỮU |

Hà Nội - Nhiều người dân đồng thuận chủ trương dự án mở rộng Quốc lộ 6, hiện đang khẩn trương di chuyển tài sản, tháo dỡ công trình để giao đất cho dự án.

Dong Nai hands over more than 71 hectares of land for the 200MW hydropower plant project

HÀ ANH CHIẾN |

Dong Nai - Chairman of the Provincial People's Committee requests to remove site obstacles for the Tri An Hydropower Plant expansion project, report before April 20.

Investing more than 175 billion VND to build 10 resettlement areas for the Ninh Binh - Hai Phong Expressway Project

NGUYỄN TRƯỜNG |

Ninh Binh - Nearly 340 households affected by the Ninh Binh - Hai Phong Expressway Project, the section passing through the old Ninh Binh province, have been arranged new accommodation in resettlement areas.