Solutions to connect Tan Son Nhat and Long Thanh airports by road and rail

MINH QUÂN |

Ho Chi Minh City is simultaneously implementing belt, high-speed and urban railway projects to enhance the connection between Tan Son Nhat airport and Long Thanh airport.

Focus on completing 6 road projects

According to the Ho Chi Minh City Department of Construction, the entire Southeast region currently has 6 road projects being implemented to enhance connectivity to Long Thanh airport.

The 207 km long Ho Chi Minh City Ring Road 4 project, connecting the three localities of Ho Chi Minh City, Dong Nai and Tay Ninh, is in the investment preparation stage, expected to start construction between 2026 and be completed in 2028.

At the same time, five large projects with a total length of about 238 km are also being accelerated.

The Bien Hoa - Vung Tau Expressway is targeted to be completed by the end of 2025, while the Ben Luc - Long Thanh Expressway is expected to be put into operation in September 2026.

The Ho Chi Minh City - Long Thanh Expressway is also being expanded, with most of the volume completed in 2026, while Long Thanh Bridge will be completed in the first quarter of 2027.

Ho Chi Minh City Ring Road 3 will be technically open to traffic and will open 70.1 km of the route on December 19, 2025. By April 30, 2026, Ho Chi Minh City Ring Road 3 will open 24.2 km of highways and 45.9 km of technical traffic. By June 30, 2026, the entire Ho Chi Minh City Ring Road 3 project will be completed and opened to traffic.

Thi cong duong tren cao phia Dong dai 14,7 km thuoc Vanh dai 3 TPHCM. Anh: Anh Tu
Construction of the 14.7 km long eastern elevated road under Ho Chi Minh City Ring Road 3. Photo: Anh Tu

Provincial Road 25C - an important route connecting Long Thanh airport - has completed 7.6 km and is under construction for an additional 6.4 km, expected to be completed in 2025, except for the 2.65 km section waiting for site clearance.

According to the Ho Chi Minh City Department of Construction, by 2026, the Southeast region will complete about 394/598 km of the Ring Road and Expressway.

By 2028, the Ring Road, Expressway and National Highway system will be basically completed, creating an inter-regional transport infrastructure framework in accordance with the plan.

Promoting the railway system to serve Long Thanh airport

In addition to roads, railway connection is considered a strategic solution to reduce the burden on ground traffic and improve passenger and cargo transport capacity.

For the national railway, the Ministry of Construction is preparing to invest in two projects: the North-South high-speed railway line starting construction at the end of 2026 and completed in 2035 and the Bien Hoa - Vung Tau route.

Ho Chi Minh City also assigned Becamex Corporation to study the cargo railway line combined with passengers from Bau Bang to Cai Mep, to serve the industrial - logistics development of the whole region, expected to start construction in 2027 and be completed before 2035.

Du an san bay Long Thanh se don chuyen bay dau tien vao ngay 19.12 va dua vao khai thac nam 2026. Anh: Ha Anh Chien
The Long Thanh airport project will receive the first flight on December 19 and be put into operation in 2026. Photo: Ha Anh Chien

Regarding urban railways, Ho Chi Minh City has identified three main corridors directly connecting to Long Thanh airport.

The first route is metro line 2 connecting Ben Thanh - Tham Luong and the section extending to Thu Thiem, then connecting to Long Thanh. The Ben Thanh - Tham Luong section is being implemented with public investment capital, starting on January 15, 2026 and completing in 2030.

The Ben Thanh - Thu Thiem section and the Thu Thiem - Long Thanh route have been approved by the Prime Minister to be adjusted to an urban railway, with Ho Chi Minh City being the investment manager. The city has assigned Truong Hai Group to propose a project under the PPP method, aiming to start construction in 2026 and put into operation in 2030.

The second corridor is metro line No. 6, invested publicly by Ho Chi Minh City, prioritized before the Tan Son Nhat - Phu Huu section to connect directly with the Thu Thiem - Long Thanh route. This route also aims to start construction in 2026 and be completed in 2030.

The third corridor is metro line 1 extending from Suoi Tien to the new Dong Nai Administrative Center and Long Thanh airport. Of which, Ho Chi Minh City will build metro line 6 while Dong Nai will be the competent authority for the metro line extension 1. The goal is to complete the entire corridor by 2030.

MINH QUÂN
RELATED NEWS

Long Thanh prepares to welcome the first flight

|

Selected as the central bridge of the Inauguration Ceremony, starting construction of large-scale projects and works, meaning to welcome the 14th National Congress of the Party, Long Thanh International Airport is racing against time, ensuring standards and conditions for inauguration and welcoming the first flight.

HCMC proposes Prime Minister to speed up 2 metro lines connecting Tan Son Nhat and Long Thanh airports

|

Ho Chi Minh City proposed to prioritize speeding up the progress of urban railway line No. 2 and Thu Thiem - Long Thanh line to connect Tan Son Nhat and Long Thanh airports.

Mailisa cosmetics case: Ministry of Health talks about the mechanism for management and post-inspection of cosmetics

|

From the Mailisa cosmetics case, the leader of the Ministry of Health said that cosmetic management is under the mechanism of " product announcement enterprises - competent authorities conduct post-inspections".

Many dragon fruit gardens in Lam Dong are still flooded after floods, people are reluctant to re- product

|

Lam Dong - 2 days after the floodwaters receded, many dragon fruit gardens were still flooded, and gardeners were resumed.

A Say Hi Brother sings at a special wedding of 80 couples

|

Say Hi Brother Erik brought to the 2025 Happy Vietnam Festival a meaningful hit about love.

Ukraine suffers series of losses after Russia's large-scale airstrike

|

Russian UAVs and missiles attacked the railway center near Kiev and many energy facilities across Ukraine, causing damage to infrastructure, power and water outages.

New tropical depression is about to enter the East Sea, forecast path in the next 24 hours

|

According to the meteorological agency, the tropical depression in the central Philippines is forecast to enter the East Sea in the next 48 hours.

Driver driving in the wrong direction on the highway was fined after people sent a video to the traffic police

|

Lam Dong - The driver driving a car in the wrong direction on the highway was fined after people sent a journey camera video to the Traffic Police.

Mạng lưới giao thông huyết mạch kết nối "siêu sân bay" Long Thành

Anh Tú |

Đồng Nai- Để trở thành cửa ngõ hàng không quốc tế lớn khu vực, Long Thành đang hoàn thiện mạng lưới giao thông huyết mạch, tạo kết nối đa chiều.

Long Thanh prepares to welcome the first flight

HÀ ANH CHIẾN |

Selected as the central bridge of the Inauguration Ceremony, starting construction of large-scale projects and works, meaning to welcome the 14th National Congress of the Party, Long Thanh International Airport is racing against time, ensuring standards and conditions for inauguration and welcoming the first flight.

HCMC proposes Prime Minister to speed up 2 metro lines connecting Tan Son Nhat and Long Thanh airports

MINH QUÂN |

Ho Chi Minh City proposed to prioritize speeding up the progress of urban railway line No. 2 and Thu Thiem - Long Thanh line to connect Tan Son Nhat and Long Thanh airports.