Hanoi - On March 24, the City People's Committee issued a decision approving the route plan, location of Tu Lien bridge and the road at both ends of the bridge, at a scale of 1/500.

Accordingly, the project starts at the intersection with Nghi Tam Street, Tay Ho District; the end point is at the intersection with TC13 Axis, Dong Anh District, with a total length of about 3km.

Regarding the classification, Tu Lien Bridge is a special-grade project; the approach road is the main urban axis road. The cross-section of the road is divided into 2 sections.

Tu Lien Bridge has a typical cross-section of 43-44m (including 6 lanes for motor vehicles and mixed lanes, separated, sidewalks...).

The road south of the bridge has a typical cross-section of 48m (including an approach bridge in the middle, a parallel urban service road and sidewalks on both sides of the road).

The road north of the bridge has a typical cross-section of 60m (determined in the plan dossier, the location of the road connecting Tu Lien bridge to the new National Highway 3, at a scale of 1/500 approved by the Hanoi People's Committee in Decision No. 6381/QD-UBND dated December 11, 2024).

The main intersection at both ends of the bridge with the axes along the Red River TC5 and TC13 is an intersection at different degrees. The intersection of the road leading to the bridge with Nghi Tam Street is a different level intersection (the road leading to Tu Lien Bridge goes up high combined with the roundabout at the intersection and the approach bridge connecting the Nghi Tam dike), the service road intersects with the existing dike road.

Expanding the Huu Hong dike border gate at the intersection in accordance with the cross-section scale of the bridgehead road, ensuring traffic connection (specifically determined during the investment project establishment process).

The intersection with other level crossings is the intersection with a preliminary determination certificate according to approved zoning plans, which will be studied and supplemented, and accurately determined during the process of establishing investment projects to build the route and other level crossings approved by competent authorities.

KHÁNH AN
RELATED NEWS

New information on the construction of Tu Lien bridge

|

Hanoi - The interdisciplinary working group will review and evaluate the contents of the component projects of the Tu Lien Bridge and the road at both ends of the bridge.

Timelines for building Tu Lien, Tran Hung Dao, Ngoc Hoi bridges

|

Hanoi - The Office of the City People's Committee has just issued a notice on the conclusion and direction of the Chairman of the City People's Committee at the meeting to listen to a report on the progress of the implementation of 3 bridges.

Hanoi builds 3 underpasses for Tu Lien bridge project

|

Hanoi - The implementation of the Tu Lien bridge project will build 3 underpasses (including 2 closed tunnels about 0.16km and 0.1km long; 1 open tunnel about 1.05km long).

More heavy rain due to stronger cold air combined with 2 factors, dangerous weather

|

The increased cold air will cause prolonged heavy rain in the Central region. Floods on rivers from Ha Tinh to Quang Ngai are likely to rise again from November 2.

Dozens of workers in Thanh Hoa accuse the company of owing wages

|

Thanh Hoa - Dozens of workers in Quang Trung ward are worried about a garment company owing hundreds of millions of VND in September wages.

Hanoi enters the "season" of sidewalk renovation

|

Hanoi - At the end of the year, many streets in the capital are being renovated and paved with sidewalks, causing some impact on people's travel.

Emulation is the driving force for Thai Nguyen to reach the modern industrial province

|

Thai Nguyen - The 1st Patriotic Emulation Congress is an opportunity to arouse the spirit of dedication to create motivation for the province to develop, towards the goal of modern industry

Cooking thousands of meals to provide relief to people in flooded areas in Hue

|

HUE - After nearly 2 days of "red fire", the kitchen at Truong An Primary School (Thuan Hoa Ward) has cooked thousands of meals to send to people in flooded areas.

New information on the construction of Tu Lien bridge

KHÁNH AN |

Hanoi - The interdisciplinary working group will review and evaluate the contents of the component projects of the Tu Lien Bridge and the road at both ends of the bridge.

Timelines for building Tu Lien, Tran Hung Dao, Ngoc Hoi bridges

KHÁNH AN |

Hanoi - The Office of the City People's Committee has just issued a notice on the conclusion and direction of the Chairman of the City People's Committee at the meeting to listen to a report on the progress of the implementation of 3 bridges.

Hanoi builds 3 underpasses for Tu Lien bridge project

KHÁNH AN |

Hanoi - The implementation of the Tu Lien bridge project will build 3 underpasses (including 2 closed tunnels about 0.16km and 0.1km long; 1 open tunnel about 1.05km long).