Hanoi is determined to complete site clearance for National Highway 6 before June 30, 2026

Minh Hạnh |

Hanoi - Facing traffic pressure on National Highway 6, the government is focusing highly on site clearance, with the goal of completing the entire project before June 30.

After the Lunar New Year holiday, the density of people and vehicles traveling on National Highway 6, the section passing through Phu Nghia commune, increased again. Meanwhile, this road is already often overloaded. People hope the project will be completed soon to reduce dust and congestion, especially during peak hours.

Mr. Nguyen Van Hai, an employee working at Hanoi Metro, said that during peak hours, the road is often congested due to the narrow cross-section, while the construction process generates a lot of dust. "People really hope the project will be completed soon so that travel is more convenient and safer," Mr. Hai said.

According to Mr. Le Anh Dung - Head of Phu Nghia Commune Economic Department, the project passes through the commune with a length of about 7.8km. To serve construction, the locality must recover 1,444 land plots with a total area of 32.34ha.

As of the end of February 23, the commune has recovered and handed over to investors 298 land plots, with an area of 19.85ha; including 64 public land plots (13.42ha) and 234 agricultural land plots (6.43ha). Thus, there are still 1,446 land plots with a total area of 12.49ha that need to continue site clearance.

According to the direction of the Hanoi People's Committee, the entire project site clearance work must be completed before June 30, 2026. This means that in the next 4 months, the volume of more than 1,100 remaining land plots must be completely handled, the progress is calculated in detail by week, by stage, without delay at any stage.

Immediately after operating the two-level local government model, Phu Nghia commune established a Land Clearance Steering Committee and working groups to propagate, mobilize, and mobilize the entire political system to participate.

Identifying site clearance for National Highway 6 as the key task for 2026, right on the first official working day of the Binh Ngo year, the Phu Nghia Commune Site Clearance Steering Committee worked with the investor to review the progress and specifically review each part of the work.

According to Mr. Trinh Tien Tuong - Secretary of the Party Committee, Chairman of the People's Council of Phu Nghia commune, the project is of particular importance to the socio-economic development of the locality. Although the workload is still large, the commune is determined to complete it in accordance with requirements and deadlines assigned by the Hanoi City People's Committee.

According to the plan, the work of confirming the origin of land and related population must be completed before March 31 to serve as a basis for preparing a compensation plan. The completion of the compensation and support plan is expected to be completed before April 15; organize payment and handover of land from April 15 to May 15. For some key sections, the commune sets a goal to complete them completely before March 25 to create continuous route sections, meeting the conditions for handover to synchronous construction contractors. After May 15, cases of non-compliance will be handled according to regulations.

If we don't do it quickly, if we don't do it drastically, it will be difficult to ensure progress. We must run on time, not slow," Mr. Trinh Tien Tuong emphasized.

Along with accelerating site clearance, leaders of Phu Nghia commune also requested the investor to direct contractors to mobilize maximum manpower and vehicles to immediately construct the sections that have been handed over, avoiding the situation of having land but deploying at a snail's pace.

Early site handover is identified as a key factor for the project to reach the finish line soon. With a specific roadmap and clearly assigned responsibilities, Phu Nghia commune is gradually "counting down" to the goal of completing site clearance before June 30, 2026, leaving no room for hesitation or delay.

Minh Hạnh
RELATED NEWS

Decisively clear land for key projects in Hanoi

|

Hanoi - Site clearance for key projects such as Hanoi National University, Hoa Lac High-Tech Park, Thang Long Avenue is being drastically directed by Hoa Lac commune.

Progress of site clearance for National Highway 6 project

|

Hanoi - The City People's Committee requests communes and wards to complete the site clearance of the National Highway 6 project on schedule as committed.

Live broadcast of Vietnam women's futsal team against Australia at the Southeast Asian Championship

|

Live football match between Vietnam women's futsal team and Australia women's futsal team at the 2026 Southeast Asian Women's Futsal Championship at 1:30 PM today (February 24).

Gold price today 24. 2: Gold rings rebound, the world reverses direction

|

Gold price today 24. 2: The world gold market reversed to decrease. Domestically, gold rings are still slightly adjusted upwards.

Lao Cai Chairman requests clarification of the cause of the explosion at the gold phosphorus plant

|

Lao Cai - Chairman of the Provincial People's Committee requests urgent investigation to clarify the cause of the explosion at the gold phosphorus factory in Tang Loong Industrial Park.

Two nurses donate blood to save critically ill pregnant woman

|

Quang Tri - Two nurses at Quang Ninh Regional General Hospital donated blood to save a woman with ectopic pregnancy.

Camera records scene of passenger car crashing into 4 cars in a chain reaction on the highway

|

Lam Dong - Dashcam recorded the scene of a passenger car crashing into cars traveling in the same direction in front, causing a chain collision of 5 cars.

US focuses firepower on the Middle East, Iran attack plan submitted to Mr. Trump

|

US President Donald Trump's threats to attack Iran do not reveal much about US goals.

Decisively clear land for key projects in Hanoi

SÓNG HỮU |

Hanoi - Site clearance for key projects such as Hanoi National University, Hoa Lac High-Tech Park, Thang Long Avenue is being drastically directed by Hoa Lac commune.

Hà Nội tăng tốc giải phóng mặt bằng hồ điều hòa Phú Đô

Minh Hạnh |

Hà Nội đẩy nhanh giải phóng mặt bằng Dự án hồ điều hòa Phú Đô - công trình khẩn cấp giảm ngập khu vực phía Tây Thủ đô.

Progress of site clearance for National Highway 6 project

KHÁNH AN |

Hanoi - The City People's Committee requests communes and wards to complete the site clearance of the National Highway 6 project on schedule as committed.