Dozens of projects in Quang Ngai are behind schedule

Viên Nguyễn |

Dozens of investment projects in Quang Ngai are in a state of slow progress, unfinished or unable to operate due to legal obstacles, causing great waste of resources and affecting people's lives.

Market completed but cannot operate yet

In March 2016, the Chairman of Quang Ngai Provincial People's Committee approved Anh Viet My Joint Stock Company to invest in the Sa Huynh market project combined with a commercial - service housing area in Pho Thanh commune, Duc Pho town. The project is built on an area of 2,187m2, scale 1 ground floor, 1 floor with 322 business locations; the commercial - service housing area includes 57 land plots around the market, height from 1 to 3 floors with a total investment of about 40.3 billion VND.

Although it has been completed since the end of 2018, Sa Huynh New Market is still closed and not operating. Reporters' records show that while Sa Huynh New Market is considered the most spacious in Sa Huynh ward, it is "inactive", and small traders still have to take advantage of the sidewalks and roadsides in front of the market to trade.

A small trader said that when the market was just completed, she registered to do business, but after the market was built, it... closed, no one announced the reason.

Notably, Anh Viet My Joint Stock Company previously planned to transfer the assets of the new Sa Huynh market to Duc Pho town (old), but so far the transfer has not been carried out due to legal obstacles, although the project has been concluded by the Government Inspectorate. According to the inspection conclusion, the Quang Ngai Provincial People's Committee's approval of the investor to approve the investment policy decision without organizing auctions or bidding for land-using projects is a violation of the Land Law and the Bidding Law. At the same time, the investment policy decision of the project is not consistent with the land use plan and continues to violate the Land Law.

According to a reporter's source, the Sa Huynh market project combined with a commercial - service housing area in Pho Thanh commune is one of 7 violating projects that the Government Inspectorate has transferred information to the Ministry of Public Security for consideration according to its authority.

In Quang Ngai, there are currently about 65 projects facing difficulties and obstacles, leading to slow progress and causing great waste, including 50 residential area and urban area projects; 4 commercial - service projects; 11 projects in other fields.

A typical example is the Tinh Phong Commercial - Service and Residential Area Project, invested by the Project Management Board for Investment, Construction and Land Development of Son Tinh district (old). The project has a total capital of more than 70 billion VND, implemented from 2017 - 2019 on an area of nearly 5ha, including items: Leveling, building a market area (4 kiosks, cages with 60 counters), transportation system, drainage, lighting, water supply, wastewater treatment, fire prevention and fighting...

However, after 8 years of implementation, the project is still in a deadlock. Currently, this area has only built some basic items such as cages, traffic roads, drainage systems... and has been abandoned for many years, seriously degraded.

Proposing special mechanisms to remove "knotholes

Mr. Nguyen Duc Thanh - Deputy Director of the Department of Finance of Quang Ngai province - said that in the past time, the province has attracted and licensed many projects. However, during the implementation process, some projects encountered legal obstacles, leading to prolongation and slow progress.

To remove prolonged backlogs, Quang Ngai Provincial People's Committee has established a Steering Committee to review and remove difficulties for backlog projects according to Decision No. 76/QD-UBND dated September 15, 2025, headed by the Chairman of the Provincial People's Committee.

After its establishment, the Steering Committee urgently reviewed each project, reported to the Prime Minister, the Ministry of Finance and central ministries and branches, and proposed to apply a special mechanism - similar to some other localities - to remove difficulties for 65 projects that are "stuck".

Currently, Quang Ngai province continues to review and update the list of problematic projects and is waiting for the direction of the Prime Minister and central agencies. After having a mechanism to remove obstacles, the Provincial People's Committee will apply current laws combined with special mechanisms to thoroughly handle and put projects into operation, avoiding prolonging waste and public outrage.

Viên Nguyễn
RELATED NEWS

9-storey market in Hanoi is about to be completed after many years of delay

|

Hanoi - After many years of delay, up to now, Thuong Cat market (Viet Hung ward) is under construction, expected to be completed in the first quarter of 2026.

Ca Mau points out 12 projects that are behind schedule and low in efficiency

|

Ca Mau - The Inspectorate of Ca Mau province concluded the inspection of 12 projects with difficulties, problems, delays, and long-term backlogs, risking loss and waste.

There is a plan to handle the abandoned headquarters after arrangement in Nghe An

|

Nghe An - The Provincial People's Committee has approved a plan to handle headquarters and public assets associated with the reorganization of the government apparatus according to a two-level model.

Miss Grand Vietnam Yen Nhi looks at and learns from experience for the journey through

|

Miss Grand Vietnam - Nguyen Thi Yen Nhi had a conversation with Lao Dong Newspaper in the Saturday afternoon coffee program.

Silver prices increase sharply, many stores temporarily stop selling

|

On December 27, the price of silver bars and gold bars skyrocketed. Many stores temporarily stopped selling, causing many people to not be able to buy and have to return.

Scene of a truck overturning carrying a charity group, killing 8 people in Lao Cai

|

Lao Cai - At the scene, the car overturned and was severely deformed. Functional forces determined that at least 8 people died.

The night of rescuing 80 people from the fierce flood by the commune police chief

|

At the 11th National Patriotic Emulation Congress, held this morning, the story of the commune police chief rescuing dozens of people from the flood center in the dark caused emotion.

Small heart, but faith and patriotism are not small

|

Shooter Trinh Thu Vinh shared that he has a small heart, but his belief and patriotism are not small at all.

9-storey market in Hanoi is about to be completed after many years of delay

KHÁNH AN |

Hanoi - After many years of delay, up to now, Thuong Cat market (Viet Hung ward) is under construction, expected to be completed in the first quarter of 2026.

Ca Mau points out 12 projects that are behind schedule and low in efficiency

NHẬT HỒ |

Ca Mau - The Inspectorate of Ca Mau province concluded the inspection of 12 projects with difficulties, problems, delays, and long-term backlogs, risking loss and waste.

Dự án chậm tiến độ, người mua nhà khó đủ đường

Bảo Chương |

TPHCM - Người mua nhà dự án chung cư Dream Home Riverside bức xúc vì đã đóng hơn 70% số tiền nhưng quá thời hạn bàn giao, dự án vẫn đứng hình.