Hundreds of workers work through the holidays at the Khanh Hoa - Buon Ma Thuot Expressway construction site

BẢO TRUNG |

Dak Lak - Hundreds of workers have postponed the National Day holiday on September 2 to focus on the construction of the Khanh Hoa - Buon Ma Thuot expressway on schedule.

On September 1, Mr. Dang Tho Dan - Head of the Traffic Project Management Department (Dak Lak Province Traffic Construction Investment and Rural Development Project Management Board) - said that contractors on the Khanh Hoa - Buon Ma Thuot Expressway are speeding up the construction progress of Component Project 3 right during the National Day holiday on September 2.

Cong nhan tang ca tren du an cao toc Khanh Hoa - Buon Ma Thuot dip le Quoc khanh 2.9. Anh: Bao Trung
Workers work overtime on the Khanh Hoa - Buon Ma Thuot expressway project on the occasion of National Day on September 2. Photo: Bao Trung

According to Mr. Dan, the construction progress and disbursement of public investment capital of the project are currently quite slow, not meeting the set requirements. Therefore, the investor has urged and requested contractors to take advantage of the time to speed up the construction progress.

Component project 3 has a route length of more than 48km, with a total investment of more than VND 6,165 billion. Of which, the construction package alone accounts for more than VND 4,216 billion.

By early September 2025, the authorities had disbursed VND 2,908.38 billion, reaching 68.9% of the contract value, 30.41% behind schedule.

Cac mui thi cong dang tich cuc lam viec de dam bao tien do du an. Anh: Bao Trung
The construction teams are actively working to ensure the project's progress. Photo: Bao Trung

Actual records at Component Project 3 (Khanh Hoa - Buon Ma Thuot Expressway) show that there are currently about 755 personnel working at the construction site, with 462 equipment and materials allocated to 41 construction teams.

Mr. Tran Cong An (worker at Construction Corporation No. 1 - CC1) said: "We are in charge of the construction of package No. 3 at the project. During the National Day holiday on September 2, all workers did not return to their hometowns to visit their families but stayed at the construction site to continue working".

Nhieu nguoi lao dong gac lai ky nghi le de o lai cong truong lam viec. Anh: Bao Trung
Many workers put aside the holiday to stay at the construction site. Photo: Bao Trung

According to Mr. An, from August 30 to now, workers are working under the 3-shift, 4-shift plan, urgently deploying the roadbed construction teams day and night.

Although tired, with the encouragement of the construction site commander, the brothers were determined to work to ensure the construction progress and disbursement in accordance with the commitment to the investor.

Mr. Dang Tho Dan - Head of Traffic Project Management Department - emphasized: "Faced with unfavorable weather conditions, we have requested contractors to be flexible with options to ensure construction progress".

According to Mr. Dan, for package 1, contractor Son Hai is increasing labor, machinery, and equipment to complete the service road and drainage system.

For package No. 2, Tan Nam contractor is taking advantage of favorable weather to speed up the construction progress of crushed stone aggregate, reinforcing cement and asphalt concrete, completing the construction of bridges on the route.

Cac phuong tien, may moc thi cong tren du an. Anh: Bao Trung
Construction vehicles and machinery on the project. Photo: Bao Trung

"The investor's goal is that by December 31, 2025, the entire Component Project 3 must complete the construction plan and disburse capital according to the set schedule.

Contractors, in addition to racing against time, need to construct according to the original drawings and designs, ensuring quality when accepting," Mr. Dan added.

BẢO TRUNG
RELATED NEWS

Two expressways worth over VND72,000 billion in the West are determined to finish on time

|

Can Tho - Two key expressways, Can Tho - Ca Mau and Chau Doc - Can Tho - Soc Trang, with a total investment of more than VND 72,000 billion, are being accelerated.

Workers work through the September 2 ceremony to ensure the progress of Quang Ngai Expressway

|

The Quang Ngai - Hoai Nhon Expressway project mobilized 3,000 human resources, constructing through the September 2 ceremony, striving to complete the project by the end of 2025.

Expressways in Lam Dong are congested due to many car collisions and accidents

|

Lam Dong - The collisions and accidents of cars on the two highways during rush hour during the September 2 holiday have slowed down vehicles.

Ministry of Construction informs about the North-South expressway rest stops during the holiday

|

The Ministry of Construction has just informed about rest stops on the North - South expressway during the September 2 holiday.

People report that the 2-month electricity bill is identical, without any wrong numbers

|

During the August electricity bill period, many people complained about the sudden increase in electricity bills compared to normal.

Reasons for not accepting salary at the A80 grand festival of filmmaker Le Bao Han

|

Le Bao Han shared about the show and behind-the-scenes of beautiful camera angles at the A80 event.

The billionaire suddenly revealed to lead the race for the Thai Prime Minister

|

The billionaire who owns one of Thailand's largest construction groups and is also the leader of the Bhumjaithai Party is leading the race for the Thai Prime Minister's seat.

President of the Vietnam Boxing Federation is absent from many activities

|

The President of the Vietnam Boxing Federation - Mr. Luu Tu Bao has been absent from many activities of this organization for more than half a year.

Two expressways worth over VND72,000 billion in the West are determined to finish on time

TẠ QUANG |

Can Tho - Two key expressways, Can Tho - Ca Mau and Chau Doc - Can Tho - Soc Trang, with a total investment of more than VND 72,000 billion, are being accelerated.

Workers work through the September 2 ceremony to ensure the progress of Quang Ngai Expressway

Viên Nguyễn |

The Quang Ngai - Hoai Nhon Expressway project mobilized 3,000 human resources, constructing through the September 2 ceremony, striving to complete the project by the end of 2025.

Expressways in Lam Dong are congested due to many car collisions and accidents

Duy Tuấn |

Lam Dong - The collisions and accidents of cars on the two highways during rush hour during the September 2 holiday have slowed down vehicles.

Ministry of Construction informs about the North-South expressway rest stops during the holiday

Xuyên Đông |

The Ministry of Construction has just informed about rest stops on the North - South expressway during the September 2 holiday.