Image of 2 billion-dollar bridges across the river in Hanoi facing difficulties, having to delay progress

SÓNG HỮU |

Hanoi - The road and railway bridges across the Duong River are under construction mainly in the middle of the river, while most of the land at both ends of the bridge has not been cleared.

The Duong River waterway upgrade project approved for investment by the Ministry of Transport (now the Ministry of Construction) includes 2 construction packages: railway bridge (XL01) and road bridge (XL02), with a total investment of nearly VND 1,850 billion.

The new railway bridge is about 1 km long, about 16.5 m upstream from the old Duong bridge center. The bridge is designed for a single-track railway with a gauge of 1,000 mm and 1,435 mm, with a design speed of 80 km/h.

The new Duong road bridge starts at the old Duong bridge intersection on Ngo Gia Tu street (Viet Hung ward), the end point is at the intersection between Ha Huy Tap street and Phan Dang Luu street (Phu Dong commune), about 700 m long, about 100 m downstream from the old Duong bridge center.

d
d
The Duong road bridge and railway bridge connecting Viet Hung ward and Phu Dong commune (Hanoi) are under construction in the middle of the river. Photo: Song Huu

Regarding construction and installation, the Railway Project Management Board (Ministry of Construction - investor) said that the current packages have completed the pillars under the river.

In particular, package XL01 (Duong railway bridge) has completed the main bridge piers; 3/6 abutments of overpasses; 3/6 sections of reinforced concrete retaining walls; about 80% of retaining wall items have corks; signal information has been moved to step 1 - phase 1. At the same time, complete the installation of a 100m and 40m girder at the location, install safety markings and temporary railway soil filling.

Currently, package XL01 is installing a 35m (N2) girder outside the construction site. The output reached 51% of the contract value. Package XL01 has been delayed in the underpass and main bridge abutments M1 and 2.

d
d
In the photo is the XL01 package, the construction of the Duong railway bridge. Photo: Song Huu

Package XL02 (Duong Road Bridge) has completed pillars T3, T4, T5 towers; casting SuperT 4/28 beams, the output reached 50.26% of the contract value.

Currently, contractors are constructing canals at the T4 and T5 pillars in the middle of the river and completing the arch tower.

d
d
d
The contractor is constructing canals at the T4 and T5 pillars in the middle of the river and completing the arch tower. Photo: Song Huu

The Railway Project Management Board said that to have a site for the project, it is necessary to reclaim a land area of 4.96 hectares, of which Viet Hung ward has 3.33 hectares/53 households (43 resettlement households) and Phu Dong commune has 1.63 hectares (1.63 hectares/89 households (70 resettlement households). The total number of households to be resettled is 113 households.

Up to now, the locality has only handed over 0.4ha (8%), so the contractor has only been able to construct the site within the dike, under the Duong River. For the remainder, Phu Dong commune has approved and paid compensation to 42/88 households; Viet Hung ward paid to 28/58 households.

d
A residential area in Phu Dong commune has not been cleared to construct the road leading to the bridge. Photo: Song Huu
d
After the new road and railway bridges are completed, the old Duong bridge will be demolished. Photo: Song Huu

Due to problems in site clearance, in October 2025, the Ministry of Construction had to approve an adjustment to the project, postponing the completion time to 2026 (instead of 2025 as originally planned).

The investor also sent an official dispatch requesting Hanoi City to direct relevant units to urgently speed up the site clearance progress, ensuring the project's construction progress.

SÓNG HỮU
RELATED NEWS

Latest information about Tu Lien Bridge project, Tran Hung Dao bridge in Hanoi

|

Hanoi - Hong Ha Ward has just informed about the site clearance for the Tu Lien Bridge and Tran Hung Dao Bridge project across the Red River.

Hanoi explains the compensation level of VND 290,000/m2 when reclaiming central land

|

Hanoi - Tay Ho Ward applies a unit price of VND 290,000/m2 corresponding to the Agricultural Land Price List of the City People's Committee prescribed when reclaiming land to build Dang Thai Mai Street.

People hope to receive adequate compensation when Hanoi reclaims land to build Tu Lien bridge

|

Hanoi reclaims land to build Tu Lien bridge, people hope to have a satisfactory compensation, support and resettlement policy, ensuring their rights according to regulations.

Black Friday super promotion, people watch out of curiosity, places are bustling with orders

|

Hanoi - On this year's Black Friday, the atmosphere at shopping malls and fashion streets has clearly differentiated.

Mr. Trump proposes to give Ukraine 100 billion USD in Russian assets

|

President Donald Trump has given Ukraine less than a week to respond to a peace deal with Russia.

Request to stop arbitrary renovation and repair at a temple area in Thanh Hoa

|

Thanh Hoa - After discovering the arbitrary renovation and repair at a temple in Hoang Giang commune, the local government requested to stop construction.

Forecast of high risk of storm No. 15 in the East Sea at the end of November

|

A cluster of thunderstorms is likely to develop into a low pressure in the Philippines, strengthen into a storm and enter the East Sea, becoming the 15th storm at the end of November.

The road connecting Do Duc Duc Duc - Me Tri becomes a black spot for waste due to project delays

|

Hanoi - The road connecting Do Duc Duc - Me Tri is degraded, flooded with garbage and odor, causing danger to people while the project has been behind schedule for many years.

Latest information about Tu Lien Bridge project, Tran Hung Dao bridge in Hanoi

SÓNG HỮU |

Hanoi - Hong Ha Ward has just informed about the site clearance for the Tu Lien Bridge and Tran Hung Dao Bridge project across the Red River.

Hanoi explains the compensation level of VND 290,000/m2 when reclaiming central land

SÓNG HỮU |

Hanoi - Tay Ho Ward applies a unit price of VND 290,000/m2 corresponding to the Agricultural Land Price List of the City People's Committee prescribed when reclaiming land to build Dang Thai Mai Street.

People hope to receive adequate compensation when Hanoi reclaims land to build Tu Lien bridge

SÓNG HỮU |

Hanoi reclaims land to build Tu Lien bridge, people hope to have a satisfactory compensation, support and resettlement policy, ensuring their rights according to regulations.