Image of construction through the National Day holiday on September 2 at the Long Thanh airport construction site

HÀ ANH CHIẾN |

Dong Nai - Thousands of officers, engineers and workers are still working hard through the National Day holiday on September 2 at the Long Thanh airport construction site.

On September 1, according to information from Vietnam Airports Corporation (ACV), the Long Thanh international airport project (abbreviated as Long Thanh airport) is bustling, with construction atmosphere throughout the ceremony.

Accordingly, in the joyful atmosphere of the whole country towards the 80th anniversary of the August Revolution and National Day on September 2, at the large construction site of the Long Thanh airport project (Dong Nai province), the construction pace is still maintained urgently, resolutely, and without rest.

The construction teams operate continuously 24/7, deployed simultaneously in many key items such as: passenger terminal, runway, aircraft parking lot and other synchronous technical infrastructure.

According to ACV, Long Thanh airport is simultaneously implementing packages, units mobilizing nearly 14,000 human resources and about 3,000 machines to organize hundreds of construction teams.

In particular, package 5.10 for the construction of the passenger terminal - an item considered a priority gasoline (gantt) of the entire Long Thanh airport project, a consortium of contractors mobilized nearly 6,000 human resources and construction machinery to ensure progress.

Up to now, the passenger terminal has completed the underground reinforced concrete structure and 4 floors; basically completed the installation of steel structure, installed glass wall support, rough construction and is implementing the work of completing the foundation, ceiling, and brick embankment.

The terminal equipment system such as: luggage handling (BHS), aircraft handling (VDGS), escalators, and pedestrian elevators (ES/MW), the contractor has transported materials and equipment to the project and is installing them.

Regarding the items of inland traffic and technical infrastructure, the consortium of contractors mobilized more than 3,300 human resources, machinery to construct the technical tuynel system, regulating lake drainage lines, power supply systems, roads and overpasses.

For packages such as fuel supply systems; connecting transportation; aircraft parking lots; 2nd runway; cargo terminal, contractor consortium mobilizes thousands of human resources and machinery to speed up construction.

Some images of the construction during the ceremony at the Long Thanh airport construction site.

Thi cong mai nha ga hanh khach san bay Long Thanh.
Construction of the roof of the Long Thanh airport passenger terminal. Photo: ACV
Thi cong phia ben trong nha ga hanh khach san bay Long Thanh.
Construction inside the Long Thanh airport passenger terminal. Photo: ACV
Thi cong phia ben trong nha ga hanh khach san bay Long Thanh.
Construction inside the Long Thanh airport passenger terminal. Photo: ACV
Cong nhan trong co tao cac mang xanh tai du an san bay Long Thanh.
Workers grow grass to create green areas at the Long Thanh airport project. Photo: ACV
Cac ong long ra may bay tai du an san bay Long Thanh.
Flight pipes at the Long Thanh airport project. Photo: ACV
Toan canh nha ga hanh khach san bay Long Thanh thi cong vao ban dem.
Overview of the Long Thanh airport passenger terminal under construction at night. Photo: ACV

The Long Thanh airport project is targeted to be determined to basically complete the project by December 19, 2025, inaugurate it according to regulations, and move towards commercial exploitation in early 2026.

HÀ ANH CHIẾN
RELATED NEWS

Long Thanh airport is under construction through the September 2 ceremony, racing against the schedule of December 19, 2025

|

Dong Nai - The Long Thanh airport project will basically be completed on December 19, 2025, put into operation and commercial exploitation in the first half of 2026.

Approving the proposal for the project to extend the Ben Thanh - Suoi Tien metro line to Long Thanh airport

|

Dong Nai - The Provincial People's Committee approved the investor's proposal to extend the Ben Thanh - Suoi Tien metro line to Long Thanh airport under the form of public-private partnership (PPP).

Prioritizing the recruitment of local workers to work at Long Thanh airport

|

More than 3,000 job opportunities for students and people when the Long Thanh Airport Project comes into operation in 2026, in which, priority will be given to recruiting local workers.

Maintaining the "steel shield", police officers worked through the night to protect security for the parade

|

At Hanoi Station, Le Duan Street, hundreds of police officers were on duty, ensuring security, order and safety for the September 2 National Day parade.

emotional final training session of the People's Public Security parade

|

Hanoi - The People's Public Security parade groups practiced the final session, ready to successfully complete the A80 mission.

The double raincoat bridge appeared in Ho Chi Minh City before the National Day holiday on September 2

|

HCMC - Many people in the nearby sea area quickly checked in, recording images of the phenomenon of a double rainbow appearing in the sky.

Hanoians' families support accommodation for dozens of veterans attending the A80 Festival

|

Hanoi Mr. Trung Kien (born in 1986) on Hao Nam Street welcomed dozens of veterans attending the A80 Ceremony home, providing free accommodation and meals.

immerse yourself in the bustling atmosphere before the A80 parade and parade

|

Since the afternoon of September 1, on the streets, a parade has passed, people have lined up to get the most beautiful locations.

Long Thanh airport is under construction through the September 2 ceremony, racing against the schedule of December 19, 2025

HÀ ANH CHIẾN |

Dong Nai - The Long Thanh airport project will basically be completed on December 19, 2025, put into operation and commercial exploitation in the first half of 2026.

Approving the proposal for the project to extend the Ben Thanh - Suoi Tien metro line to Long Thanh airport

HÀ ANH CHIẾN |

Dong Nai - The Provincial People's Committee approved the investor's proposal to extend the Ben Thanh - Suoi Tien metro line to Long Thanh airport under the form of public-private partnership (PPP).

Prioritizing the recruitment of local workers to work at Long Thanh airport

HÀ ANH CHIẾN |

More than 3,000 job opportunities for students and people when the Long Thanh Airport Project comes into operation in 2026, in which, priority will be given to recruiting local workers.