The largest hydroelectric reservoir in the South doubled flood discharge, opened 3 gates

MINH CHÂU |

Dong Nai - Tri An Hydropower Reservoir continues to discharge flood water through the spillway with the flow increasing from 320m3/s to 480m3/s tomorrow, September 24.

On September 23, Mr. Vo Tan Nhan - Director of Tri An Hydropower Company signed a document announcing the increase in spillway discharge to regulate the Tri An Hydropower reservoir.

Speaking to Lao Dong newspaper reporter, Mr. Vo Tan Nhan - Director of Tri An Hydropower Company said that to ensure flood prevention capacity, combined with the water level downstream of the river at Bien Hoa hydrological station having passed the peak of high tide and is falling, and at the same time not releasing quickly and suddenly to avoid possible impacts on the downstream, Tri An Hydropower Company increased the amount of water released to regulate the reservoir.

According to the notice, at 12 noon on September 23, after 2 hours of spillway discharge, the upstream water level of the lake was 60.78m, the downstream water level at the factory was 4.7m, the water flow to the lake was 1,700m3/second.

It is expected that in the next 1-2 days, the water flow into the lake will be more than 1,400m3/second, the water flow discharged through the spillway will be 150m3/second, and the water flow through the power turbine will be 815m3/second.

At 9:00 a.m. on September 24, the spillway will be discharged with a water flow through the spillway of 320m3/second, water flow through the turbine generating electricity from 800 - 850m3/second, total water flow discharged downstream is from 1,120 - 1,170m3/second.

At 11:00 a.m. on September 24, the spillway will be discharged with the water flow through the spillway increasing to 480 m3/s, the water flow through the turbine generating electricity from 800 - 850 m3/s, the total water flow discharged downstream is from 1,280 - 1,330 m3/s.

Then, depending on the weather and the water level downstream of the Bien Hoa hydrological station, the company can change the water flow through the spillway. The company informs relevant local authorities and agencies to direct, coordinate and notify people downstream of the reservoir to proactively take preventive measures to avoid possible damage.

Previously, at 10:00 a.m. on September 23, Tri An Hydropower Plant discharged water from one gate with a flow rate of about 150m3/second.

Mr. Nhan added that tomorrow (September 24) at 9:00 a.m., another spillway gate will be opened and at 11:00 a.m., another spillway gate will be opened.

Tri An Hydropower Plant was inaugurated and put into operation in 1991. Currently, the plant has 4 units, with a total designed capacity of 400MW. This is the largest hydropower project in the Southern region, contributing greatly to the national grid, helping to regulate water sources for daily life, production, repelling salinity and regulating floods for downstream areas.

MINH CHÂU
RELATED NEWS

Factory fire near gas station in Ho Chi Minh City

|

Ho Chi Minh City - Ho Chi Minh City Police have controlled a factory fire near a gas station in Tan Hiep ward.

Ho Chi Minh City People's Committee headquarters nearly 120 years old will become a tourist attraction

|

Ho Chi Minh City - The headquarters of the People's Council - People's Committee of Ho Chi Minh City on Le Thanh Ton Street (nearly 120 years old) will be preserved and exploited as a tourist and educational destination.

Hanoi Party Secretary sets deadline for completion of "most expensive road on the planet

|

Hanoi - Regarding the progress of the Ring Road 1 project (Hoang Cau - Voi Phuc section), the Hanoi Party Secretary requested to complete the entire roadbed before September 2, 2026; complete the construction of 2 overpasses on the route before December 31, 2026.

Gia Lai drought, people dredge to find water sources to save crops

|

Gia Lai - The western region of the province is entering the dry season, many localities are facing severe water shortages.

Hanoi Traffic Police show trainees videos of accidents before driving test

|

Hanoi - Before the test, traffic police show trainees videos recording serious traffic accidents, thereby making them more aware of their responsibilities when holding the steering wheel.

Complete the installation of medical equipment at facility 2 of Bach Mai and Viet Duc Hospitals before June 30

|

Ninh Binh - The investor of Bach Mai Hospital and Viet Duc Friendship Hospital facility 2 project committed to complete the installation of equipment before June 30.

Salary reform from the Central to local levels, implemented in all 3 blocs

|

The Ministry of Home Affairs is assigned to carefully prepare the reform of salaries, allowances and other regimes from the Central to local levels, implemented in all 3 blocs.

Forecast of the risk of receiving strong storms and super typhoons in 2026

|

According to a representative of the meteorological agency, ENSO phase transition along with the impact of climate change leads to the risk of strong storms and super typhoons in 2026.

Hoa Binh Hydropower Plant continues to close another floodgate

Minh Nguyễn |

Hoa Binh Hydropower Plant continues to close another floodgate under the order of the Minister of Agriculture and Rural Development.

Hoa Binh Hydropower Plant closed one floodgate at night

Minh Nguyễn |

Hoa Binh Hydropower Plant just closed a floodgate at 1:00 a.m. on September 23 under the order of the Minister of Agriculture and Rural Development.

Water level rises to over 60m, largest hydroelectric reservoir in the South releases floodwaters

HÀ ANH CHIẾN |

Dong Nai - Tri An Hydropower Reservoir will discharge flood water through the spillway from 10am on September 23.