Completion of nearly 500 billion VND 6-lane road at the Northwest gateway

Minh Chuyên |

Phu Tho - After nearly 3 years of construction, the project to renovate and upgrade National Highway 6 bypassing Hoa Binh city (old) has been completed.

The project has a total investment of nearly 474 billion VND, invested by Project Management Board 6 (Ministry of Transport, now Ministry of Construction).

The route is renovated and upgraded with a total length of about 5 km, starting point at Km73+500, ending point at Km78+500 on National Highway 6, belonging to Thong Nhat and Hoa Binh wards, Phu Tho province.

According to the design, after completion, the road has a cross-section of 20.5 m wide, meeting the standard of a level III plain road with a scale of 6 lanes. Including 4 motorized lanes, design speed of 80 km/h and 2 mixed lanes, each lane about 2 m wide.

Expanding the road surface helps increase traffic capacity, gradually overcoming the prolonged overload situation on National Highway 6 - the axis connecting Hanoi with the Northwest provinces.

Tuyen duong mang lai dien mao moi cho khu vuc. Anh: Minh Chuyen
The road brings a new look to the area. Photo: Minh Chuyen

The contractors constructing the project include Truong Thanh Co., Ltd.; Ngoc Minh Construction and Trading Joint Stock Company - UDIC (responsible for construction and ensuring traffic safety throughout the route) and 1/5 Construction Co., Ltd. (construction, ensuring traffic safety for the bridge section).

The project was started on March 1, 2023, expected to be completed in 18 months (August 2024). However, due to difficulties and obstacles, the project has had to be extended many times.

It's a bit of a bit of a bit of a bit of a bit of a bit.

Xe co qua lai tap nap tren tuyen duong. Anh: Minh Nguyen
Traffic is bustling on the road. Photo: Minh Nguyen

On January 16, actual records of Lao Dong Newspaper reporters showed that the project has been completed, traffic is bustling, and the road marking system and median strip have been installed, ensuring safety and aesthetics of the road.

Mr. Nguyen Van Thien (30 years old, residing in Thong Nhat ward) shared that since the road was completed, travel is more convenient, traffic congestion and collisions have decreased significantly, and the area's appearance is more spacious than before.

Giai phan cach moi duoc xay dung tren tuyen duong. Anh: Minh Nguyen
The new median strip is built on the road. Photo: Minh Nguyen

Talking to Lao Dong Newspaper, Mr. Vu Trong Huan - Project Director said that the project has been completed so far, and it is expected that handover will be carried out from now until before the Lunar New Year.

The completion of the project not only meets the increasing travel needs of people but also has important significance in connecting trade, attracting investment, and promoting socio-economic development of Phu Tho province and the Northwest region provinces.

Video recorded by PV on the road.
Minh Chuyên
RELATED NEWS

Phase 1 of Dong Dang - Tra Linh route receives completion order in 2026

|

Cao Bang - The Minister of Construction has just paid a visit and directed the construction progress of the Dong Dang - Tra Linh expressway.

Hanoi informs about the progress of the extended To Huu road - National Highway 6 and Provincial Road 419

|

Hanoi - Voters proposed that the City People's Committee invest funds and direct the acceleration of the construction progress of traffic road projects in Chuong My ward.

Hanoi dismantles, relocates works, and hands over land for National Highway 6

|

Hanoi - National Highway 6, Ba La - Xuan Mai section, will have a cross-section extended to 50-60 m, and many bridges on the route will also be built.

Hai Phong introduces Colonel Bui Trung Thanh to run for National Assembly Deputy XVI

|

Hai Phong - City Police organize to collect voters' opinions, introduce people to run for National Assembly deputies of the XVI term and People's Council deputies of the XVII term.

It's a bit of a bit of a bit of a bit of a bit of a bit.

It's a bit of a bit of a bit of a bit of a bit of a bit.

U23 Vietnam - U23 UAE score prediction: 1 goal difference

|

The match between U23 Vietnam and U23 UAE could end with only 1 goal scored.

The Party Committee of the Vietnam General Confederation of Labor announces decisions on personnel work

|

On the morning of January 16, the Party Committee of the Vietnam General Confederation of Labor held a conference to announce decisions on personnel work.

Ho Chi Minh City Chairman requests breakthrough solutions to combat traffic jams and flooding

|

Ho Chi Minh City - Existing problems such as traffic jams, flooding, environmental pollution, administrative reform, and investment promotion need to be clarified and have effective solutions to overcome.

Sticking to the road, maintaining peace at the gateway of the Capital towards the 14th Party Congress

|

Hanoi - In the days leading up to the 14th Party Congress, the Police and Traffic Police force day and night stick to the route, maintaining security and safety at the gateway to the Capital.

Phase 1 of Dong Dang - Tra Linh route receives completion order in 2026

Duy Dũng |

Cao Bang - The Minister of Construction has just paid a visit and directed the construction progress of the Dong Dang - Tra Linh expressway.

Hanoi informs about the progress of the extended To Huu road - National Highway 6 and Provincial Road 419

Anh Tuấn |

Hanoi - Voters proposed that the City People's Committee invest funds and direct the acceleration of the construction progress of traffic road projects in Chuong My ward.

Hanoi dismantles, relocates works, and hands over land for National Highway 6

Anh Tuấn |

Hanoi - National Highway 6, Ba La - Xuan Mai section, will have a cross-section extended to 50-60 m, and many bridges on the route will also be built.