More than 2 years without completing the less than 1km long road

Tân Văn |

Although it has entered the third year since the start of construction, the nearly 1km long inner-city road located in the center of Pac Mieu town (Bao Lam district, Cao Bang province) is still in a state of disrepair, causing local people to be disappointed.

The road is in an important position, but there are no workers

The actual recording of the reporter on June 16 shows that the road is being constructed at an extremely important location - right in front of the Central Square, opposite the headquarters of the District Party Committee and People's Committee of Bao Lam district. This is an area considered the "facade" of Pac Mieu town. However, contrary to the expectation of a modern road that contributes to improving the urban landscape, this road is under construction.

Some sections of the road have been paved with sidewalk stones and light pole stands have been installed. However, most of them are still just soil, the drainage system is not yet complete, construction materials such as bricks, stones... are lying around on both sides of the road, not covered or protected, causing both loss of aesthetics and potential safety risks to passersby.

In particular, the construction site is completely devoid of workers and machinery. No construction warning signs, no project information boards - capital requirements according to regulations for works using public investment capital.

A resident living in Pac Mieu town shared with reporters: This road connects from the agricultural market to the central square, if completed, it will be very beautiful and convenient for travel, especially in the evening, people can walk coolly on the riverbank. But until now, it has not been completed, taking place year after year, making us very impatient.

Toan canh du an gan 1km duong dang do lam hon 2 nam chua xong o thi tran Pac Miau (Bao Lam, Cao Bang). Anh: Tan Van
Overview of the project of nearly 1km of unfinished road in Pac Mieu town (Bao Lam, Cao Bang) that has not been completed for more than 2 years. Photo: Tan Van

Difficulties in site clearance

According to information from Mr. Luc Van Thu - Director of the Bao Lam District Construction Investment Project Management Board, the construction of this road was started in 2023, with a total investment of more than 8 billion VND. The project is on the list of projects invested by the district budget, aiming to upgrade the technical infrastructure of the central area, improve inner-city traffic and connect neighboring residential areas.

However, up to now, the project has not been completed due to problems in site clearance (GPMB). Some households in the construction area have not agreed to hand over the land, leading to stagnant construction, and contractors cannot continue to synchronously deploy the items.

According to PV's research, in 2023, Bao Lam district allocated a total of more than 239 billion VND to invest in 98 basic construction projects in the area. Of which, 2 projects used central capital, 4 projects from provincial capital, 10 projects under district-level investment capital and the rest used capital from the national target program on sustainable poverty reduction. The unfinished road in the center of Pac Mieu town is one of these projects. The construction unit of this route is Dong Duong Company Limited.

In the context of urban renovation and construction of transport infrastructure being considered a driving force for socio-economic development, a road less than 1km long but not yet completed is a truly worrying image.

An inner-city road in the center of town - which is expected to become a highlight in terms of infrastructure, landscape and community connectivity - is becoming an "urban sadness" due to unnecessary delays. It is time to act more drastically to restore the spacious appearance of Bao Lam district center.

Tân Văn
TIN LIÊN QUAN

The road along To Lich River has been put into use for more than a year

|

Hanoi - The route reserved for bicycles and pedestrians along To Lich River is quite deserted, with few people passing through after more than 1 year of use.

Investing 1,484 billion VND to build a new road in Dong Anh district

|

Hanoi - The new route passing through the Dan Di auction area (Dong Anh district) is about 5.34km long; the total estimated investment is 1,484 billion VND.

Tuoi Tre Thu Do Newspaper receives Third Class Labor Medal

|

Hanoi - On June 18, the Capital Youth Newspaper held a ceremony to celebrate the 100th anniversary of the Vietnam Revolutionary Press Day and received the Third Class Labor Medal.

Decoding deposit record levels at credit institutions

|

Bank deposits reached nearly VND7.47 trillion in the first quarter of 2025. However, not all of this cash flow is residential savings.

Amending the Law on Product and Goods Quality to protect consumers

|

On the afternoon of June 18, the National Assembly voted to pass the Law amending and supplementing a number of articles of the Law on Product and Goods Quality.

Rearranging and reorganizing the trade union model in the People's Public Security

|

On the afternoon of June 18, the Ministry of Public Security coordinated with the Vietnam General Confederation of Labor to organize a conference to discuss and reach agreement on the project to reorganize and reorganize the trade union model in the People's Public Security.

Director of Phu Yen Provincial Police promoted to the rank of Major General

|

Phu Yen - Director of Phu Yen Provincial Police, Colonel Phan Thanh Tam was promoted to the rank of Major General according to the decision of the President.

Hàng chục hộ dân Đà Nẵng kín cửa vì tuyến đường chưa đến 1km chậm tiến độ

Thu Giang |

Đà Nẵng - Nhiều hộ dân sinh sống trên tuyến đường Bình Hòa 2 (quận Cẩm Lệ, Đà Nẵng) phải đóng cửa kín mít vì dự án thi công tuyến đường chậm triển khai.

The road along To Lich River has been put into use for more than a year

HỮU CHÁNH - ĐẶNG TIẾN |

Hanoi - The route reserved for bicycles and pedestrians along To Lich River is quite deserted, with few people passing through after more than 1 year of use.

Investing 1,484 billion VND to build a new road in Dong Anh district

KHÁNH AN |

Hanoi - The new route passing through the Dan Di auction area (Dong Anh district) is about 5.34km long; the total estimated investment is 1,484 billion VND.