Hung Yen builds 7 resettlement areas to serve the Ninh Binh - Hai Phong expressway

Mai Hương |

Hung Yen - The Ninh Binh - Hai Phong expressway project through the province is on schedule, with a site handover rate of 85%.

According to the No. 2 Construction Investment Project Management Board, the Ninh Binh - Hai Phong expressway project through the province is 33.3km long, designed with a scale of 4 complete lanes, roadbed width of 24.75m, design speed of 120km/h. The project started in May 2025, expected to be basically completed in 2027 and put into operation from 2028.

The work of completing technical design documents, estimates and construction drawing designs for construction packages is being implemented on schedule. Regarding site clearance, the communes have basically completed the agricultural land with about 206.18 hectares; have handed over 28.2km to the investor for construction, reaching about 85%.

For residential land, localities are counting, publicizing plans, submitting for appraisal and approval, and at the same time building resettlement areas in 7/10 communes where projects pass through. Two new cemeteries are also under construction to serve the relocation of graves. In particular, for compensation and support for agricultural land clearance, localities have paid about 99%.

Pho Chu tich UBND tinh Lai Van Hoan cung lanh dao cac so, nganh, dia phuong kiem tra tien do thuc hien du an tai dia ban xa Hong Vu. Anh: Cong TTDT tinh Hung Yen
Vice Chairman of the Provincial People's Committee Lai Van Hoan and leaders of departments, branches and localities inspect the project implementation progress in Hong Vu commune. Photo: Hung Yen Provincial Portal

Packages B.01 (Ninh Co River Overpass), B.02 (Red River Overpass) and B.03 (Tra Ly River Overpass) are under construction, with a total output value of about 220 billion VND.

Vice Chairman of the Provincial People's Committee Lai Van Hoan has requested departments, branches, localities and investors to identify this as a national key project, which needs to closely follow the progress, especially accelerating site clearance for the remaining agricultural land, residential land and other types of land; completing resettlement infrastructure; removing obstacles in construction materials.

Hong Vu Commune People's Committee was assigned to coordinate with Land Fund Development Center No. 2 to propose and implement the construction of a road to the new water plant. Localities continue to mobilize and create consensus among people in the project area.

The Vice Chairman of the Provincial People's Committee also requested departments and branches to coordinate in advising on solving difficulties in the source of filling materials, guiding procedures for land allocation, and granting materials for exploitation to ensure progress. Project enterprises need to proactively work with neighboring provinces and cities to supplement materials; mobilize human resources and machinery to speed up the construction of bridges and roadbeds in sections with clean land, ensuring quality, aesthetics and labor safety.

Previously, Mr. Lai Van Hoan and leaders of departments, branches and localities inspected the construction site of the Red River overpass in Hong Vu commune, part of the Ninh Binh - Hai Phong expressway project through the province.

Mai Hương
RELATED NEWS

Mr. Tran Quoc Toan was elected to hold the position of Chairman of the Hung Yen Provincial Fatherland Front Committee

|

Hung Yen - On the morning of November 20, the Hung Yen Provincial Fatherland Front Committee met for the first time for the 2024-2029 term to elect the position of Chairman of the Provincial Fatherland Front Committee.

Hung Yen pays policies for people working outside the payroll

|

Hung Yen - Hung Yen province implements a payment policy for people working outside the payroll at associations after administrative reorganization.

Hung Yen tightens responsibility as a leader in implementing and disbursing projects

|

Hung Yen - On November 19, Chairman of the Provincial People's Committee Pham Quang Ngoc chaired a meeting to listen to reports on key projects and implementation progress of the Construction sector.

Black Friday super promotion, people watch out of curiosity, places are bustling with orders

|

Hanoi - On this year's Black Friday, the atmosphere at shopping malls and fashion streets has clearly differentiated.

Mr. Trump proposes to give Ukraine 100 billion USD in Russian assets

|

President Donald Trump has given Ukraine less than a week to respond to a peace deal with Russia.

Request to stop arbitrary renovation and repair at a temple area in Thanh Hoa

|

Thanh Hoa - After discovering the arbitrary renovation and repair at a temple in Hoang Giang commune, the local government requested to stop construction.

Forecast of high risk of storm No. 15 in the East Sea at the end of November

|

A cluster of thunderstorms is likely to develop into a low pressure in the Philippines, strengthen into a storm and enter the East Sea, becoming the 15th storm at the end of November.

The road connecting Do Duc Duc Duc - Me Tri becomes a black spot for waste due to project delays

|

Hanoi - The road connecting Do Duc Duc - Me Tri is degraded, flooded with garbage and odor, causing danger to people while the project has been behind schedule for many years.

Mr. Tran Quoc Toan was elected to hold the position of Chairman of the Hung Yen Provincial Fatherland Front Committee

Mai Hương |

Hung Yen - On the morning of November 20, the Hung Yen Provincial Fatherland Front Committee met for the first time for the 2024-2029 term to elect the position of Chairman of the Provincial Fatherland Front Committee.

Hung Yen pays policies for people working outside the payroll

Mai Hương |

Hung Yen - Hung Yen province implements a payment policy for people working outside the payroll at associations after administrative reorganization.

Hung Yen tightens responsibility as a leader in implementing and disbursing projects

Mai Hương |

Hung Yen - On November 19, Chairman of the Provincial People's Committee Pham Quang Ngoc chaired a meeting to listen to reports on key projects and implementation progress of the Construction sector.