slow construction of the billion-dollar road connecting Lao Cai - Lai Chau

Đinh Đại |

Lao Cai - The project to upgrade National Highway 279 connecting Lai Chau with IC16 intersection is being constructed sluggishly, lacking measures to ensure traffic safety.

The project to connect the traffic of the Northern mountainous provinces with a total investment of more than 6,000 billion VND aims to shorten the journey to Hanoi capital of the Northern mountainous provinces.

The project consists of 2 routes, of which route 1 is 147 km long, connecting Lai Chau with the Hanoi - Lao Cai expressway, starting point at IC16 intersection, ending point at the old Lai Chau city hospital intersection.

Bui bam bua vay nguoi di duong vi Quoc lo 279 thi cong cham. Anh: Dinh Dai
Dust surrounds road users because National Highway 279 is under construction. Photo: Dinh Dai

Recorded by Lao Dong on July 31, the section through Van Ban commune (Lao Cai province), part of the XL-01 package constructed by Dong Duong Group Joint Stock Company and the XL-02 package implemented by Construction Investment Company Limited, project 656, both have slow and unfinished construction progress.

Observation along the route shows that many construction sites are still messy, lacking warning signs and ropes in dangerous areas, posing a potential risk to traffic safety.

According to people's reflection, the interrupted construction not only affects the travel process but also causes difficulties for the production and transportation of agricultural products of the people.

Vehicles are often damaged due to the dense road surface, potholes.

Chang chit o voi, o ga cung nhung doan duong loi lom khien viec di chuyen cua nguoi dan gap nhieu kho khan. Anh: Dinh Dai
The potholes and bumpy roads make it difficult for people to move around. Photo: Dinh Dai

Ms. Nguyen Thi Hoa, a resident of Van Ban commune, Lao Cai province, shared: "This road has been under construction for several years but is still not completed. The road is dusty when it is sunny, muddy when it rains.

The construction unit lacks measures to protect the safety of the project, so collisions and accidents often occur. Therefore, children going to school or the elderly going to the market must move very carefully.

Viec thi cong do dang khien qua trinh di chuyen cua nguoi dan gap nhieu kho khan, nguy hiem. Anh: Dinh Dai
Unfinished construction causes unsafety on the route. Photo: Dinh Dai

According to Van Ban Commune Police, in the past, contractors have carried out construction of items such as excavation, leveling, asphalt paving, building drainage ditches, burying markers, guardrails, etc.

However, the delay in construction progress has led to the road surface deteriorating, concave, forming many "potholes", "elephant potholes", dust pollution, noise pollution seriously affecting the daily life and activities of residential areas along the road, causing frustration for the people.

At the same time, it directly affects traffic participation on National Highway 279 with a large volume of vehicles.

Thieu day cang, bien canh bao tai nhung vi tri thi cong dang do. Anh: Dinh Dai
Lack of ropes and warning signs at unfinished construction sites. Photo: Dinh Dai

Talking with Lao Dong, Mr. Vu Khanh - representative of Project Management Board 2, Ministry of Construction admitted that the project still has many shortcomings as reflected by the people of Van Ban commune.

According to Mr. Khanh, because people have not agreed to the compensation price at some sections, the construction is still unfinished. However, the local government has now promoted and mobilized people to continue the construction of the road.

Mot doan Quoc lo 279 thi cong dang do ngay phia truoc tru so Cong an xa Van Ban, tinh Lao Cai. Anh: Dinh Dai
A section of National Highway 279 under construction right in front of the headquarters of Van Ban Commune Police, Lao Cai Province. Photo: Dinh Dai

Regarding the lack of measures to ensure traffic safety, Mr. Khanh said that investors will strengthen inspections, urge contractors to stretch ropes and put up signs at dangerous locations to warn people. At the same time, water regularly to limit dust from the road construction process.

"Currently, the progress of the entire route is about 60%, we are also urgently urging the contractor to speed up construction. In particular, if any team is slow to construct and is not guaranteed, we will immediately replace it with another unit. Everything must be completed before December 31, 2025 according to the plan, affirmed a representative of Project Management Board 2.

Reporter's records through Van Ban commune, Lao Cai province
Đinh Đại
RELATED NEWS

Lao Cai Trade Union stands side by side with businesses to care for workers

|

Lao Cai - The Provincial Industrial Parks Trade Union had a working session to grasp the operational situation of a number of companies in the area.

Lao Cai spends 17 billion VND to renovate and beautify Coc Leu bridge

|

Lao Cai - The Coc Leu Bridge Renovation and Renovation Project and the area on both sides of the Coc Leu Bridge approach road, Lao Cai Ward have completed the contractor selection.

On the construction site of a 454 billion VND waste treatment plant in Lao Cai

|

Lao Cai - Many items of the 454 billion VND "Industrial waste treatment plant and hazardous waste" project in Tang Loong Industrial Park are being completed for early operation.

Museums under the Ministry of Culture, Sports and Tourism open free of charge on September 2

|

Following the direction of Party Central Committee member, Minister of Culture, Sports and Tourism Nguyen Van Hung, museums under the Ministry of Culture, Sports and Tourism, Vietnam Ethnic Culture and Tourism Village, and Vietnam Contemporary Arts Theater will open for free to serve tourists and the public on September 2.

hospital tricks continue to lure patients to outside clinics

|

HCMC Although the HCMC health sector has strongly warned about the situation of brokers in hospitals, this situation still occurs every day.

Digital assets are not currency, need to be properly recognized

|

SBV Deputy Governor Pham Tien Dung emphasized that digital assets are not currencies, it is necessary to properly recognize the nature and potential of this type.

20h News: Ring Road 4 of Hanoi Capital Region finalizes construction start date in August

|

20h News: The North is about to have severe heat again, forecasting the highest temperature; finalizing the time to start construction of the Ring Road 4 expressway in the Hanoi Capital region...

Resolving policies and regimes for cadres and civil servants affected by the arrangement before August 31

|

Conclusion No. 183 requires directing the handling and settlement of regimes and policies for cadres and civil servants affected by the restructuring of the apparatus before August 31, 2025.

Lao Cai Trade Union stands side by side with businesses to care for workers

Đinh Đại |

Lao Cai - The Provincial Industrial Parks Trade Union had a working session to grasp the operational situation of a number of companies in the area.

Lao Cai spends 17 billion VND to renovate and beautify Coc Leu bridge

Tô Công |

Lao Cai - The Coc Leu Bridge Renovation and Renovation Project and the area on both sides of the Coc Leu Bridge approach road, Lao Cai Ward have completed the contractor selection.

On the construction site of a 454 billion VND waste treatment plant in Lao Cai

Đinh Đại |

Lao Cai - Many items of the 454 billion VND "Industrial waste treatment plant and hazardous waste" project in Tang Loong Industrial Park are being completed for early operation.