About 350 workers will construct Rach Mieu 2 Bridge through the April 30 ceremony

Thành Nhân |

Ben Tre - About 350 workers will work on the construction of Rach Mieu 2 bridge during the April 30, 2025 holiday.

On April 27, Mr. Tran Van Thi - Director of My Thuan Project Management Board (Ministry of Construction) - said that during the upcoming April 30 and May 15 holidays, at the Rach Mieu 2 bridge project site, the units will continue to maintain construction in 3 shifts, 4 teams, with a total of more than 20 construction teams, more than 80 equipment units, about 350 workers and 50 technical staff.

The road section of this project has 14 main construction teams, 60 equipment teams, 30 technical staff and about 155 workers. They will construct the above foundation layer of stone; cast concrete and install a median strip; construct ramp branch box culverts; construct asphalt concrete on the road surface...

For the bridge section on the project route, there are 3 main construction teams, 5 equipment teams, 5 technical staff and about 45 workers. They will construct items such as: Xoai Hot bridge: construction of material embankment behind the abutment; construction of the transitional section behind the abutment; Song Ma bridge: construction of cross-beams; pouring concrete for the bridge deck; construction of the My Tho bridge expansion joints.

As for the main bridge (Rach Mieu 2 bridge), there are 3 main construction teams, more than 15 equipment teams, 15 technical staff and about 150 workers. They will construct items such as: dismantling the dragon fruit burning scaffolding; removing cast iron cars; casting railing edges; removing the cable-stayed railing system.

Cong trinh du an cau Rach Mieu 2 da hoan thanh duoc 85,05% khoi luong. Anh: Ban QLDA My Thuan cung cap
The Rach Mieu 2 Bridge project has completed 85.05% of the volume. Photo: Provided by My Thuan Project Management Board

According to Mr. Thi, it is expected that by June 30, 2025, the Rach Mieu 2 bridge project will complete all 5/5 bridges on the route and basically complete the approach road. It is expected that the entire Rach Mieu 2 Bridge project will be completed and put into operation in August 2025.

Director of My Thuan Project Management Board Tran Van Thi added that up to now, the Rach Mieu 2 bridge project has completed 85.05% of the volume, exceeding the general progress by more than 4% compared to the plan. In particular, the main bridge (Rach Mieu 2 bridge) is more than 14% ahead of schedule.

Accordingly, up to now, the road section on the entire route has been completed 14/14km (100%). Of which, about 7/14km of asphalt concrete has been spread in each segment and it is expected to complete the entire route on the Ben Tre side before June 30, 2025.

Regarding the bridge section on the route, 4/6 bridges have been completed; the remaining 2 bridges under construction are the main bridge and the Song Ma bridge. Of which, Song Ma bridge is expected to be completed in June 2025.

As for the main bridge, the main cable-stayed bridge bridge was closed on April 19, 2025, and is currently in the process of dismantling the girder casting, constructing completed items such as: track edge, median strip, lighting, bridge deck expansion joints...

Khoang 350 cong nhan thi cong cau Rach Mieu 2 xuyen le 30.4.2025. Anh: Ban QLDA My Thuan cung cap.
About 350 workers will construct Rach Mieu 2 Bridge through the April 30, 2025 ceremony. Photo: Provided by My Thuan Project Management Board.

Previously, at the meeting on the situation of investment in developing the transport infrastructure system in the Mekong Delta in the afternoon of April 21, 2025 in Can Tho City, the Prime Minister asked the Ministry of Construction to direct the investor, the contractor accelerated the construction progress of Rach Mi 2 Bridge project, striving to complete and clear the whole car before the National Day 2.9225.

The Rach Mieu 2 Bridge project has a starting point at the intersection between National Highway 1 and Provincial Road 870 in Chau Thanh District, Tien Giang Province, and an end point connecting to National Highway 60 at the Ham Luong Bridge approach road in Ben Tre Province. This project has a scale of 4 lanes, a design speed of 80km/h, with a total investment of more than 6,810 billion VND.

Thành Nhân
TIN LIÊN QUAN

Journey connecting the two banks of the Tien River at the Rach Mieu 2 bridge project

|

Ben Tre - Rach Mieu 2 Bridge, connecting Tien Giang and Ben Tre, has been officially closed after more than 3 years of construction.

Rach Mieu 2 Bridge worth over VND6,800 billion officially closed

|

Ben Tre - Rach Mieu 2 Bridge has just held a closing ceremony, marking an important milestone in the construction progress.

At the Rach Mieu 2 bridge construction site before the closing time

|

Ben Tre - Rach Mieu 2 Bridge is a key traffic project in the Mekong Delta and will officially close on April 19, 2025.

Subjects prioritized by Hanoi as Ward and Commune Secretaries after the reorganization

|

Hanoi - For the position of Commune Secretary after the arrangement, the city will prioritize considering cadres who are City Party Committee members or District-level Secretaries.

Allocate 1,000 billion VND to deploy additional expressway connecting to Long Thanh airport

|

Ba Ria - Vung Tau - The Provincial People's Council has approved the allocation of 1,000 billion VND to deploy the expressway connecting Long Thanh and Ho Tram in 2025.

Vietnam Military History Museum is crowded with visitors before the grand ceremony on April 30

|

Before the grand ceremony on April 30, the Vietnam Military History Museum welcomed a large number of visitors, customers lined up to buy tickets.

Reasons for Quang Tri's proposal to terminate FLC Group's agricultural project

|

After many years of delay, the FLC Group's FAM Quang Tri High-Tech Agricultural Zone project is at risk of being terminated.

13,000 people participate in the General parade, parade on Le Duan Street in Ho Chi Minh City

|

HCMC - 13,000 people participated in the General parade, marched on Le Duan Street - in front of Thong Nhat Hall (District 1).

Journey connecting the two banks of the Tien River at the Rach Mieu 2 bridge project

Thành Nhân |

Ben Tre - Rach Mieu 2 Bridge, connecting Tien Giang and Ben Tre, has been officially closed after more than 3 years of construction.

Rach Mieu 2 Bridge worth over VND6,800 billion officially closed

Thành Nhân |

Ben Tre - Rach Mieu 2 Bridge has just held a closing ceremony, marking an important milestone in the construction progress.

At the Rach Mieu 2 bridge construction site before the closing time

Thành Nhân |

Ben Tre - Rach Mieu 2 Bridge is a key traffic project in the Mekong Delta and will officially close on April 19, 2025.