Ho Chi Minh City - Moc Bai and Gia Nghia - Chon Thanh Expressway to start construction on August 19

MINH QUÂN |

Ho Chi Minh City - Gia Nghia - Chon Thanh Expressway and Ho Chi Minh City - Moc Bai Expressway are required by Prime Minister Pham Minh Chinh to start construction on August 19.

The above directive was issued at the 6th session of the Southeast Coordination Council and the 4th session of the Steering Committee for the implementation of Resolution 98 of the National Assembly on piloting a number of specific mechanisms and policies for the development of Ho Chi Minh City, taking place on August 2.

At the meeting, Prime Minister Pham Minh Chinh directed the promotion of the implementation of key infrastructure projects in the Southeast region.

The Prime Minister requested localities in the right region to work with Ho Chi Minh City to successfully implement the International Financial Center project, making efforts to start the construction of Ring Road 4 on the occasion of August 19, while speeding up the Can Gio international transit port project under the form of public-private partnership (PPP), promoting the basic completion of Long Thanh international airport in 2025.

In addition, the Prime Minister directed the Ministry of Finance and localities to carefully review problems in regional traffic projects such as the Gia Nghia - Chon Thanh expressway and the Ho Chi Minh City - Moc Bai expressway to promptly resolve them, ensuring the start of construction on schedule on the occasion of August 19.

Thu tuong Pham Minh Chinh phat bieu ket luan hoi nghi.  Anh: VGP/Nhat Bac
Prime Minister Pham Minh Chinh delivered a concluding speech at the conference. Photo: VGP/Nhat Bac

Prime Minister Pham Minh Chinh also requested to continue studying the Loc Ninh - Bien Hoa railway line connecting Cai Mep port and Can Gio port; at the same time, study the possibility of building a metro or urban railway connecting Tan Son Nhat and Long Thanh airports.

The Ho Chi Minh City - Moc Bai (Tay Ninh) expressway project has a total length of 51.2 km, starting point connecting with Ho Chi Minh City Ring Road 3 in Cu Chi district (old), ending point intersecting with National Highway 22 in Ben Cau district (old), Tay Ninh province.

Phase 1 will invest in the construction of a 4-lane expressway, while deploying auxiliary works such as rest stops, smart traffic systems, toll collection systems, etc.

The total investment of the entire project (including interest costs) is about VND 19,617 billion, under the BOT form.

The Ho Chi Minh City - Moc Bai Expressway is expected to be completed and put into operation by the end of 2027, contributing to reducing the load on National Highway 22, synchronizing the belt road system with great capacity, ensuring safety and high speed on the Ho Chi Minh City - Tay Ninh transport corridor.

This route will connect the industrial chain - Moc Bai urban area - Ho Chi Minh City - Cai Mep port - Thi Vai, associated with the Xuyen A economic corridor, promoting the socio-economic development of Ho Chi Minh City, Tay Ninh in particular and the Southeast region in general.

The Gia Nghia (Dak Nong) - Chon Thanh (Binh Phuoc) expressway project has a total length of about 124 km, of which the section passing through Dak Nong province is about 23.1 km long, the section passing through Binh Phuoc province is about 101.03 km long.

The expressway is planned to have 6 lanes. The first phase will be built with 4 complete lanes; after reaching the maximum traffic volume around 2045, 2 more lanes will continue to be expanded. The total preliminary investment of the project is about VND 25,540 billion, under the BOT form.

When put into operation, this expressway will promote the socio-economic development of Dak Nong and Binh Phuoc, while strengthening the connection between the Southeast region and the Central Highlands, contributing to reducing the load on National Highway 14 - the main traffic route between the two regions.

MINH QUÂN
RELATED NEWS

HCMC approves the most important component project of the HCMC - Moc Bai Expressway

|

HCMC - The HCMC People's Committee has just approved component project 1 to invest in the construction of the HCMC - Moc Bai expressway under the BOT form with a total investment of more than VND 10,400 billion.

HCMC prepares to reclaim land, build resettlement areas to build the North-South high-speed railway

|

Ho Chi Minh City will approve compensation and resettlement for the North-South high-speed railway project in October 2025, and hand over the site to the construction unit in December 2026.

Perspective of the 124 km Gia Nghia - Chon Thanh Expressway

|

Dong Nai - The Gia Nghia - Chon Thanh Expressway project is planned with a scale of 6 lanes, designed speed of 120 km/h.

Ky Duyen, Hoa Minzy as team captains, reveal interesting things about the 2025 Drafting Star

|

On August 2, the artists were present at the launch of the 2025 Star Enrollment Program: When the Fatherland calls our names.

Apartment prices are over 80 million VND/m2, it is difficult for people with a salary of 50 million VND/month to buy

|

Hanoi - The average selling price of apartments in Hanoi is gradually beyond the affordability of the entire middle- and high-income group.

Big fire at a match factory in Tay Ninh

|

Tay Ninh - On the evening of August 2, a major fire broke out at a match factory in Tan Hoi Industrial Cluster (Tan Hoi commune), burning down the entire factory.

Storm Gil strengthens into a hurricane, at risk of many new storms

|

Storm Gil has strengthened into a typhoon in the Pacific basin and is experiencing very active storm and tropical depression activities.

Indonesia's most intense volcano bursts out for the second consecutive day

|

Indonesia's most intense Lewotobi Laki volcano has been on the rise for the second consecutive day, creating a column of ash and volcanic material up to 18km high.

HCMC approves the most important component project of the HCMC - Moc Bai Expressway

MINH QUÂN |

HCMC - The HCMC People's Committee has just approved component project 1 to invest in the construction of the HCMC - Moc Bai expressway under the BOT form with a total investment of more than VND 10,400 billion.

HCMC prepares to reclaim land, build resettlement areas to build the North-South high-speed railway

MINH QUÂN |

Ho Chi Minh City will approve compensation and resettlement for the North-South high-speed railway project in October 2025, and hand over the site to the construction unit in December 2026.

Perspective of the 124 km Gia Nghia - Chon Thanh Expressway

ĐÌNH TRỌNG |

Dong Nai - The Gia Nghia - Chon Thanh Expressway project is planned with a scale of 6 lanes, designed speed of 120 km/h.