On January 17, Dong Nai Provincial People's Committee said it would start construction of the Cai River road project in early February 2026.
The Cai Riverside road project has a starting point from Ha Huy Giap road in Tran Bien ward to the end of the route adjacent to Tran Quoc Toan road in Tam Hiep ward, with a total length of 4.6 km, total investment of 3,960 billion VND.
Previously, at the end of 2023, two main packages of the project were implemented, including: Construction package No. 10 - construction of 5 bridges on the route (Chim Tau bridge, Rach Gio bridge, Tan Mai bridge, Ba Bot bridge, Suoi Linh bridge) and access roads at both ends of the bridge; Construction package No. 20 - construction and installation of items to relocate high-voltage and medium-voltage power lines, transformer stations and lighting.
This is a key project of Dong Nai province, of important significance in promoting socio-economic development and creating urban development space.