The expressway resettlement area is still rice fields, people hope to start construction soon

Khánh Linh |

Lang Son - Although the people have given up land for the project, achieving a site clearance rate of over 99.5%, the expressway resettlement area has not yet started construction.

On June 18, the leader of the Trang Dinh District Investment and Construction Project Management Board (Lang Son) said that the unit had completed the assessment and selection of contractors for the Pac Luong Resettlement Area project, serving the construction of the Dong Dang - Tra Linh Expressway.

According to the selection results, the consortium won the bid including 8 enterprises: Hoang Ha Lang Son Company Limited (leading the consortium), Green Technology Solutions Joint Stock Company, Lang Son Water Supply and Drainage Joint Stock Company, Le Quang Trade and Technical Services Joint Stock Company, Hung Phat LS Construction Investment Company Limited, Thanh An Lang Son Construction Investment Joint Stock Company, Thanh Nam Investment and Development Joint Stock Company, and Tan Minh Construction and Trading Company Limited.

Immediately after approving the results of contractor selection, the investor will request the units to urgently implement the construction, expected to start construction before June 30, 2025.

According to the plan, the implementation process will simultaneously dredge the land surface layer of the project area and use excess land from the Dong Dang - Tra Linh expressway to build the resettlement area.

a
The area planned to build the Pac Luong resettlement area in De Tham commune, Trang Dinh district, Lang Son province. Photo: Khanh Linh

Up to now, about 90 households in 5 communes including Chi Lang, De Tham, Hung Viet, Hung Son and Chi Minh have registered to receive land in the concentrated resettlement area.

We aim to complete the land before the Lunar New Year 2026 to hand over to households. After that, the electricity and water systems will be constructed in parallel to ensure that people can stabilize their lives," informed the representative of the Project Management Board.

However, at the scene, everything was still a promise. In late June, heavy rain continuously fell on the border area, causing the risk of landslides, flooding, and rolling rocks throughout the project communes.

In a makeshift hut covered with a thin tarpaulin, Mr. Nong Van Tram (Coong village, Hung Son commune) quietly tied up tarpaulins that were deflated by the wind, eyes looking towards the black clouds on the top of the mountain.

"At the beginning of March, I received a notice of site clearance, and in the middle of the month, I demolished my house to temporarily live in. It was thought that the resettlement area would be started immediately, but until now, the shape of the machinery has not been seen. When it rains, the water is inundated, and I can't sleep well. Although it is a hundred-favorite inconvenience, we still accept it because we believe that the project will be implemented soon, Mr. Tram shared.

Nguoi dan xa Hung Son san sang dung nhung can lan tam de nhuong dat cho du an cao toc Dong Dang - Tra Linh. Anh: Khanh Linh
People in Hung Son commune are ready to build temporary shelters to give land to the Dong Dang - Tra Linh expressway project. Photo: Khanh Linh

Not far away, Mrs. Loc Thi Sen (Hung Son commune) and her two children built a temporary hut next to the stream. The worry of the rainy season fell on the shoulders of a woman nearly 70 years old.

"The land has been handed over, the houses have been demolished, now there is only a temporary hut. It's unbearable in sunny weather, but if it rains, all you have to worry about is landslides. We don't know where to turn, just hope the government will soon arrange a stable place to live," Ms. Sen choked up.

However, both the interspersed resettlement plan and the concentrated resettlement area in Pac Luong (De Tham commune) are still only on paper. The land planned to be built is still a vast rice field.

Previously, on April 15, the People's Committee of Lang Son province approved the plan to select contractors to implement the Pac Luong residential area project under the form of public-private partnership (PPP), to arrange resettlement for households affected by the Dong Dang - Tra Linh expressway project phase 1.

The project belongs to the Sub-project for site clearance in Trang Dinh district, with a total value of more than 53.6 billion VND, using state budget capital. Expected to be implemented from the second quarter of 2025, the implementation period is within 6 months.

With continuous rain, the water level of the Ky Cung River rises every day, flowing rapidly, and people hope that the resettlement project will be completed so that people can soon stabilize their lives and fulfill their dream of settling down and making a living.

Khánh Linh
RELATED NEWS

Binh Thuan plans to resettle people in the high-speed railway project

|

Binh Thuan is implementing resettlement and site clearance to serve the North-South high-speed railway project.

Da Nang supports resettlement and relocation of degraded apartment buildings

|

Da Nang - The Chairman of the Da Nang People's Committee approved a plan to support resettlement, relocation and clearance of Hoa Minh Apartment Complex (Thanh Khe Tay Ward, Thanh Khe District).

Over 2,000 billion VND in compensation and resettlement for Ca Mau - Dat Mui Expressway

|

Ca Mau - The project to reclaim land, compensate, support, and resettle to implement the expressway from Ca Mau city to Dat Mui is expected to cost over VND 2,000 billion.

Gia Lai Provincial Chairman directs handling of teacher's exam paper revision case

|

Gia Lai - Provincial Chairman requests functional sectors to intervene to definitively handle the case at Nguyen Van Cu Elementary School, clarify the responsibilities of violating collectives and individuals.

Designing an administrative center for 6,000 Ho Chi Minh City officials in Thu Thiem

|

Ho Chi Minh City - A large-scale administrative center serving 6,000 officials, along with a theater and central lake park, is being built in Thu Thiem New Urban Area.

Musician To Hieu is ready to confront Tan Bo in the scandal of owing hundreds of millions of VND

|

Regarding Tan Bo's denunciation related to money disputes, musician To Hieu affirmed that he is not worried and is ready to work with functional agencies.

Workers carrying the colors of spring, hoping for a full Tet with their families

|

Hanoi - In the days leading up to Tet, on the streets of the Capital, it is not difficult to see images of drivers busily carrying peach and kumquat trucks.

Phuoc An bridge connecting Ho Chi Minh City and Dong Nai reaches 50% of construction progress

|

Ho Chi Minh City - Phuoc An bridge across the Thi Vai River connecting to Dong Nai, with a total investment of nearly 4,900 billion VND, has reached nearly 50% of the construction progress.

Binh Thuan plans to resettle people in the high-speed railway project

Duy Tuấn |

Binh Thuan is implementing resettlement and site clearance to serve the North-South high-speed railway project.

Da Nang supports resettlement and relocation of degraded apartment buildings

Trần Thi |

Da Nang - The Chairman of the Da Nang People's Committee approved a plan to support resettlement, relocation and clearance of Hoa Minh Apartment Complex (Thanh Khe Tay Ward, Thanh Khe District).

Over 2,000 billion VND in compensation and resettlement for Ca Mau - Dat Mui Expressway

NHẬT HỒ |

Ca Mau - The project to reclaim land, compensate, support, and resettle to implement the expressway from Ca Mau city to Dat Mui is expected to cost over VND 2,000 billion.